Attachment_5_-_Aerial_View.pdf

PDF 139 KB Posted

Attached to
IT Fiber Upgrade Gainesville, FL Federal contract opportunity
Solicitation number
G17PS00735
Issued by
Department of the Interior US Geological Survey

About this file

Attachment 5 - Aerial View

View the file

Other files for this federal contract opportunity

Other files attached to IT Fiber Upgrade Gainesville, FL, newest first.
File Type Posted
Attachment_7_-_Auditorium_Floor_plan.jpg JPG image
Attachment_1_Davis_Bacon_Act_Wage_Determination.pdf PDF
Attachment_6_-_Site_Visit_Information.pdf PDF
Attachment_2_-_DI-137_Release_of_Claims.pdf PDF
Attachment_8_-_North_Modular_Floor_Plan.pptx PPTX presentation
Attachment_9_-_Main_Building_Floor_Plan.PDF PDF
Attachment_4_-_Form_WH-347_Wage_and_Hour_Division.pdf PDF
Sol_G17PS00735.pdf PDF
Attachment_3_-_Standard_Form_1413_Statement_and_Acknowledgement.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

G17PS00735 Attachment 5

In the image below, #1 is the main building, #2 is the auditorium (attached to main building), #3 is the North Modular Building,# 4 is the South Modular Building, and #5 is the Travis Smith Annex.

Distances – estimated from Google Earth

Starting Point End Point Straight Distance Adjusted for Vertical Run

Server Room Auditorium 95 ft (29 m) 124 ft (38 m) Server Room North Modular Bldg 117 ft (36 m) 152 ft (47 m) Server Room South Modular Bldg 223 ft (68 m) 290 ft (88 m) Server Room Travis Smith Annex 252 ft (77 m) 328 ft (100 m) Note – all adjustments are 1.3 of straight run, allowing for conduits up and down walls and ceilings as needed.