Attachment_L_Past_Performance_Questionnaire.docx

DOCX document 23 KB Posted

Attached to
EROS O&M Federal contract opportunity
Solicitation number
G15PS00003
Issued by
Department of the Interior US Geological Survey

About this file

Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to EROS O&M, newest first.
File Type Posted
Sol_G15PS00003_Amd_000001.pdf PDF
Attachment_K_Reference_Information_Sheet.docx DOCX document
Attachment_B__asset_for_Cafe_Equipment.xls XLS spreadsheet
Attachment_J_Wage_Determinations.pdf PDF
Attachment_H__Release_of_Claims.doc DOC document
Attachement_C__Asset_listings2.xlsx XLSX spreadsheet
Attachment_F___Furnished_equipment_Far_52.245-1_property.xlsm XLSM spreadsheet
Sol_G15PS00003.pdf PDF
Attachment_A__PM_listings.xls XLS spreadsheet
Attachment_D__Work_order_other_than_PMs.xls XLS spreadsheet
Attachment_I_Non_Disclosure.doc DOC document
Attachment_E__Lawn_Mowing_site_map.pdf PDF
Attachment_G__FAR_52.245-2__Government_Property_Installation_Operation.xlsm XLSM spreadsheet
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment L

RFP- G15PS00003

Past Performance Questionnaire Competition Sensitive – For Official Use Only

Contractor: ____________________________ Evaluation Period: ______________________ Contract Number: _______________________ Government Technical Representative (Name and Phone #): _____________________________

Please indicate your relative level of agreement in the box provided:

(O = outstanding; VG = very good; A = acceptable; M = marginal; UN = unsatisfactory; or N/A)

1. Quality of Product or Service:

Contractor provided a product or service that conformed to contract requirements, specifications, and standards of good workmanship.

Contractor submitted accurate reports.

Contractor utilized personnel that were appropriate to the effort performed.

2. Schedule:

Tasks required under this effort were performed in a timely manner and in accordance with the period of performance of the contract.

Contractor was responsive to technical and/or contractual direction.

3. Cost Control:

Contractor performed the effort within the estimated cost/price.

Contractor submitted accurate invoices on a timely basis.

Contractor demonstrated cost efficiencies in performing the required effort.

4. Business Relations:

Contractor demonstrated effective management over the effort performed.

Contractor maintained an open line of communication so that the COR and/or technical point of contact were apprised of technical, cost, and schedule issues.

Contractor presented information and correspondence in a clear, concise, and businesslike manner.

Contractor promptly notified the COR, technical POC, and/or Contracting Officer in a timely manner regarding urgent issues.

Contractor cooperated with the Government in providing flexible, proactive, and effective recommended solutions to critical program issues.

Contractor made timely award to, and demonstrated effective management of, its subcontractors.

5. Key Personnel:

The labor turnover in key personnel labor categories was minimal and did not adversely affect performance.

Contractor did not frequently propose personnel to fulfill the requirements of the contract that were clearly unqualified.

For statements indicating “outstanding” or “unacceptable”, please provide a brief explanation on the attached page. Please include any other comments you may have.

Attachment L

RFP- G15PS00003

Past Performance Questionnaire Competition Sensitive – For Official Use Only

Contractor: ____________________________ Contract Number: _______________________

NARRATIVE EXPLANATION (attach extra pages, if needed):

Source Selection Information-See FAR 2.101 and 3.104.