This is a Statement of Work (SOW) for an HVAC Replacement Project at the Salt Lake City (SLC) Long Range Radar (ARSR) facility, issued by the Federal Aviation Administration's NAS Defense Programs, NDP Resource Services Team in April 2026.
The contractor must furnish all labor, materials, equipment, and supervision for demolition and installation of HVAC systems at the SLC ARSR site near Francis Peak, Utah. Scope includes removal and disposal of two existing HVAC units with associated ductwork, installation of two new 15-ton York Johnson Controls air conditioning units (model DSV180A2E1DAA0A-D or FAA-approved equivalent) with R-454b refrigerant, and installation of associated ductwork, controls, and components. All equipment and materials require FAA inspection and formal acceptance by the Contracting Officer's Representative (COR) prior to installation. The contractor must implement a temporary cooling solution with a 24-hour continuous run-in test under full-load conditions before system changeover, with documented test procedures and certification. Construction shall not commence until the contractor confirms in writing that all equipment and materials have been procured and are ready for inspection.
The contractor must deliver additional work including replacement of approximately 25 ceiling tiles, replacement of 20 fluorescent light fixtures (16 drop ceiling, 4 suspended) with LED lighting, performance of testing and balancing to confirm 15-ton cooling capacity and minimum 6,000 CFM delivery per unit, provision of maintenance equipment for R-454b systems, an arc flash study with updated protective device coordination analysis, and four hours of training for facility personnel. The project includes electrical work requiring compliance with FAA specifications and standards, security bar installation at exterior wall penetrations per FAA Order 1600.69D, and provision of operation and maintenance instructions upon completion. The FAA anticipates construction activities to last no longer than 30 days. The contractor must coordinate all work with the FAA on a "not to interfere with FAA operations" basis, maintain the facility's 24/7 operational status, provide a detailed temporary cooling plan for FAA approval, and comply with OSHA safety standards, security requirements, and all applicable FAA standards and specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| M001(I).pdf | ||
| 697DCK-26-R-00315.pdf | ||
| M002(I).pdf | ||
| Wage Determination UT20260096 05182026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Aviation Administration
NAS DEFENSE PROGRAMS
NDP RESOURCE SERVICES TEAM
AJW-B710
INFRASTRUCTURE PROGRAM
HVAC Replacement Project
Salt Lake City, UT
SLC ARSR
April 2026
SLC - ARSR HVAC Replacement April 2026
SUMMARY OF WORK PAGE 1
SUMMARY OF WORK
1.0 GENERAL SCOPE
The selected Contractor shall furnish all labor, product, equipment, materials, and supervision for the demolition and installation associated with the HVAC Replacement Project at the Salt Lake City (SLC) Long Range Radar (ARSR) site located near Francis Peak, UT.
“Demolition” includes but is not limited to removing and disposing of the existing 2 HVAC units and select sections of associated ductwork from the facility. “Installation” includes but is not limited to providing and installing 2 new 15-ton HVAC units with associated ductwork, HVAC controls, and all associated components at the site. Prior to mobilization and installation, all equipment and materials shall be reviewed, inspected, and formally accepted by a designated FAA Representative (COR or authorized designee) based on compliance with contract requirements and approved submittals.
Prior to transition from existing HVAC systems, the Contractor shall implement a temporary cooling solution to maintain continuous environmental control at the facility. The temporary cooling system shall successfully complete a continuous twenty-four (24)-hour operational run-in test under full-load equivalent conditions prior to use for facility support. The system shall operate without interruption, performance degradation, alarms, refrigerant faults, or loss of cooling capacity. Any failure or interruption during the test shall require correction and a full repeat of the twenty-four (24) hour test at no additional cost to the Government.
The Contractor shall provide test procedures, logs, and certification of successful completion for FAA review and acceptance prior to system changeover.
The following items are a summary of the project and are provided solely for the purpose of describing the general nature of the work. The Contractor is responsible for accomplishing all items of work identified in the applicable drawings, specifications, and provisions of the contract.
The Contractor shall provide a temporary cooling plan that details sequencing, redundancy, and contingency measures to ensure uninterrupted facility operations during construction.
Contractor shall provide drawings as necessary including but not limited to Contractor-proposed modifications to design and field conditions. Temporary cooling systems shall not be placed into service until FAA acceptance of required submittals and successful completion of the run-in test.
Construction shall not commence until the Contractor provides written notification to the FAA confirming that all equipment and materials have been procured, are on site or readily available, and are ready for FAA inspection and acceptance.
SUMMARY OF WORK PAGE 2
The Contractor shall provide field drawings, letters, and reports as requested by the FAA. This includes but is not limited to the temporary cooling plan, certified test reports required by this SOW, HVAC system run-in documentation, all material submittals requiring FAA approval prior to mobilization, and documentation of refrigerant recovery and disposal in accordance with applicable regulations.
A. General
1. SLC ARSR is an active operational facility that runs 24 hours a day, 7 days a week.
2. All work shall be coordinated with the FAA and be accomplished on a “Not to interfere with FAA operations” basis.
3. Construction material shall be stored only in FAA approved areas.
4. Construction staging shall be allowed only in the FAA approved areas.
5. The Contractor shall provide all temporary services required for construction including but not limited to a temporary HVAC unit.
6. The Contractor shall clean up and restore the site grounds to its original condition after the work has been performed.
B. Demolition
1. Remove and properly dispose of existing packaged HVAC units (2 units). Provide certificate of disposal for refrigerant.
2. Remove and properly dispose of the associated ducting in accordance with M001(I), controls and other related components.
3. Relocate interferences for the new equipment as needed to allow clearance for new ductwork. All relocations must be done with prior approval from the COR.
4. Patch all wall openings left as a result of the demolition to match surrounding areas.
5. Due to the critical equipment inside this facility, reliable cooling is required throughout the project. Prior to switching over to the new units, a 24-hour continuous run-in test is required.
6. The Contractor shall provide the FAA with a temporary cooling plan detailing how they intend to remove/install the new units while also maintaining the redundant cooling required at this facility. This temporary cooling plan must be submitted to and approved by an FAA representative before construction.
A. Installation
New Air Conditioners
1. Provide and install 2 each new York Johnson Controls 15-Ton Air Conditioning Units (DSV180A2E1DAA0A-D), or FAA approved equal, and all associated components into
SUMMARY OF WORK PAGE 3
the general locations shown on installation drawing M001(I). Exact locations are to be field determined. The minimum characteristics of the new air conditioning units shall be as follows:
a. Commercial application
b. R-454b Refrigerant
c. 15 tons nominal Capacity
d. Economizer
e. Low Ambient Cooling
f. FreezeStat
g. Hinged Access Doors
h. Return Air Smoke Detector
i. 208-230V / 60 hertz / 3 phase
j. GFCI Outlet – Powered
2. Mount unit curbs or stands to concrete using concrete anchor/studs. Secure new units per manufacturer’s instructions.
3. Provide a Manufacturer’s Start-Up Report.
4. “Zoom-loc” press fittings and any other similar fittings are not to be used in this project. Only soldered connections should be made. Solder connections only with 15% silver during nitrogen purge.
5. Contractor is to provide a minimum of 3-year extended warranty for all HVAC units.
6. Connect units to previously installed Government Furnished (GFE) OAS HVAC controller. Contractor will be responsible for providing and installing ¾” conduit from the controller and properly sized thermostat wire to each new unit.
a. OAS HVAC controller is limited to a single-stage input for heating. If the HVAC unit has two-stages of heating, Contractor shall install a time delay to ensure both stages of heating do not energize simultaneously.
Ductwork
1. Existing ducting shall remain in place and be utilized per SMACNA standards as shown on associated installation drawing M001(I). A non-motorized counterbalanced back-draft damper shall be installed in the supply ductwork for each HVAC unit to prevent back-flow to a non-active unit during normal operation.
Field verify that access doors are currently installed downstream of each back-draft damper and near security bar locations (if applicable). If access doors are not present, provide and install new 14”x14” access doors (Greenheck HAD Type or
SUMMARY OF WORK PAGE 4
FAA approved equal) at the specified locations. No new ductwork installation is required under this scope.
2. Existing return ducting and grilles shall remain in place and be utilized at the general locations shown on installation drawing M001(I). Existing return duct sections shall be cleaned, resealed, and repaired as required to ensure airtight performance and compliance with system operation requirements. Cleaning and repair shall include removal of deteriorated sealants, surface preparation of galvanized components, application of galvanized-compatible protective coating/paint where corrosion or coating loss is present, and resealing of all joints to restore system integrity.
3. Dimensions shown on drawings are airway (interior) dimensions. Existing interior ductwork shall remain in service and shall be utilized as part of the final airflow system. External insulation shall remain in place unless disturbed during installation activities.
4. Existing exterior ducting shall remain in place and shall not be fully replaced under this scope. Amend any damaged or degraded areas and sealing. Any disturbed or repaired areas shall be restored using a protective coating similar to VentureClad 1577CW or FAA approved equal.
5. All new hangers shall be trapeze style. Other hanger styles can be submitted to the FAA for review/approval.
6. All ductwork bonding shall comply with the latest revision of FAA Standard FAA- STD-019, “Lightning Protection, Grounding, Bonding and Shielding Requirements for Facilities”.
7. Ductwork shall not interfere with access panels, entrances and egresses, and other critical equipment. All existing ductwork shall remain in place and shall not be modified except for two (2) existing diffusers, which shall be replaced and surrounding ductwork adjusted in the field to redirect airflow to a 45-degree discharge pattern to properly cool radar equipment below diffusers. All transitions, seals, and interfaces associated with this adjustment shall be cleaned, secured, and properly sealed to maintain system performance and air balance.
Ceiling Tiles
1. Replace damaged or missing ceiling tiles with new.
a. It is anticipated that approximately 25 ceiling tiles need to be replaced.
2. Tiles shall be similar in size and style as existing.
3. Existing grid may be reused/modified if possible.
LED Lighting
1. Replace existing fluorescent lighting 20 total fixtures (16 drop ceiling, 4 suspended) with new LED lighting as follows:
SUMMARY OF WORK PAGE 5
a. New LED Lighting shall be a one-for-one replacement with existing fluorescent bulbs & fixtures, providing equal or greater light (lumens) per sq ft.
b. Actual Fixture location shall be altered to accommodate new ductwork.
c. LED light fixtures shall be similar design to existing. Drop ceiling models installed into the same circuits as the existing lights. Lights shall be RAB EZPAN2X4-40N/D10LED Troffer (4000K Color Temperature), or FAA approved equal.
i. LED fixture must be fully sealed to prevent bug entry.
ii. Troffer surface mount kit required for all surface mounted lights.
iii. It is anticipated that 16 drop ceiling lights need to be replaced.
d. In areas requiring hanging light due to ductwork or other interference, utilize Lithonia SBL4 48L (4000K Color Temperature) or FAA approved equal.
i. The FAA anticipates 4 hanging lights need replacing.
Security Bars
1. The Contractor shall repair or install security bars as needed at any penetrations of exterior walls of secured areas caused by installation or otherwise deemed within the scope of this project, i.e., inside of ductwork, exhaust fan penetrations, etc.
in accordance with the latest revisions of FAA Order 1600.69D.
Electrical
1. All electrical work shall comply with the latest revision of FAA specification FAA-C- 1217H, “Electrical Work, Interior”.
2. All equipment grounding shall comply with the latest revision of FAA standard FAA- STD-019G, “Lightning Protection, Grounding, Bonding and Shielding Requirements for Facilities”.
3. All bonds shall be exothermic welds or FAA approved pressure connections.
4. Contractor shall confirm breaker size prior to construction and replace if necessary per unit manufacturer specifications. Breakers may be oversized if the associated disconnect is properly fused for the serviced equipment.
5. Provide and install properly sized stainless steel Heavy Duty disconnects and connecting wires for each new air conditioner unit. Outdoor disconnects shall be NEMA 3R minimum rating. Each disconnect shall be fused to match manufacturer rating for supported equipment.
6. Provide updated printed Panel schedules to affected Panels.
7. Label each new/reused disconnect with Voltage, Phases, and Source Panel &
Breaker info. Labels shall be plastic engraved nameplates with white letters and black background. Letter size must be 1/8" for controls, 3/16" for devices on control panel covers and 3/8" for safety switches, air conditioning equipment and other equipment devices. Nameplates must be secured to equipment, cabinets and to controls with adhesive backing.
SUMMARY OF WORK PAGE 6
8. Utilize Liquid-Tite type flexible conduit when flexible application is required. Flex conduit shall not exceed 6’ individual length.
9. EMT Conduit is only allowed on the interior of FAA facilities. All outdoor conduits shall be rigid steel with threaded connections.
10. Where EMT is used, only compression-type fittings are acceptable.
Testing and Balancing
1. Perform an operational check of all newly installed equipment.
2. Confirm the cooling capacity is 15-tons per unit and each unit delivers a minimum of 6,000 CFM.
3. Testing & balancing to confirm system operation is within manufacturer’s published blower performance curve for the installed configuration.
4. Confirm proper operation of all dampers.
5. Confirm compressor operation and staging (if applicable) for the controls and air conditioning units and economizers.
6. Balance airflow as shown on M001(I). Provide a Certified Test & Balance Report upon completion of project.
Maintenance Equipment:
1. Provide the following equipment to the FAA for continued maintenance of the new R-454b HVAC Equipment.
a. Valve Manifold (Fieldpiece SMAN482V with associated hoses or FAA approved equal)
b. Recovery Machine (Fieldpiece MR45 or FAA approved equal)
c. Vacuum Pump (Fieldpiece VPX7 or FAA approved equal)
d. Vacuum Gauge (Fieldpiece MG44 or FAA approved equal)
e. Digital Refrigerant Scale (Fieldpiece SR47 or FAA approved equal)
f. Recovery Tank (Mastercool 62010 or FAA approved equal)
g. 4 sets of replacement filters – Manufacturer Recommended
h. 1 Spare set of disconnect fuses (if applicable)
i. 1 Spare set of evaporator fan belts
Arc Flash Study:
1. The Contractor shall perform a complete short-circuit, protective device coordination, and arc flash hazard analysis in accordance with NFPA 70E, NFPA 70 (NEC), IEEE 1584, OSHA requirements, and applicable FAA standards. An arc flash study shall be required for all new electrical equipment including disconnects, modifications to existing electrical distribution systems, changes to protective devices or settings, electrical refurbishments, or where existing arc flash documentation is missing, outdated, or invalid. Studies shall be based on field-
SUMMARY OF WORK PAGE 7
verified data and reflect the final installed condition. Arc flash warning labels shall be provided and installed on all applicable equipment.
2. Determine arc flash boundary distances, incident energy levels and required Personal Protective Equipment (PPE) for each piece of newly installed equipment.
3. Submit an updated detailed Arc Flash Report to the COR or designated FAA representative.
Training:
1. Provide new equipment training to the facility personnel for all newly installed equipment. Training shall consist of at least 4 hours detailing the new units and individual components of the system, including Filter Replacement, Lock Out Procedures, and any special features of installed equipment.
1.2 APPLICABLE DOCUMENTS
A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and contract drawings referenced in this and the following divisions form a part of this specification and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract.
B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
1. Code of Federal Regulations (CFR):
a. OSHA General Industry Safety and Health Standards (29 CFR 1910), OSHA
Construction Industry Standards (29 CFR 1926). OSHA 2202 is a condensed version of 29 CFR 1926. Each is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.
b. National Emission Standards for Hazardous Air Pollutants (40 Cfr, Part 61).
2. SMACNA Handbooks: Sheet Metal and Air Conditioning Contractors’ National
Association
3. Federal Standard (313A): Preparation and the Submission of Material Safety Data
Sheets.
4. FAA Specification 1217H: Electrical Work, Interior.
5. FAA Standard 019g: Lightning and Surge Protection, Grounding, Bonding, and
Shielding Requirements for Facilities and Electronic Equipment.
6. FAA Order 1600.69D: FAA Facility Security Management Program
7. List of Drawings:
SUMMARY OF WORK PAGE 8
These listed drawings are for information only, expressing existing conditions and construction details. The contractor shall verify dimensions, locations, and sizes on the applicable drawings prior to installation.
Project Documentation M001(I) HVAC Installation M002(I) Reference Images
Existing Project Related Documentation (For reference only)
1.3 DEFINITIONS
A. Federal Aviation Administration (FAA) - The terms "Federal Aviation Administration" (FAA) and "government" as used herein denotes the "owner".
B. Project Engineer (PE) - The term "Project Engineer (PE)” as used herein denotes the "Government’s representative".
C. Contracting Officer (CO) - The term "Contracting Officer" (CO) as used herein denotes the person designated to act for the Government in the performance of this contract.
D. Contracting Officers Representative (COR) - The term "COR” as used herein denotes the representative of the Contracting Officer at the job site. The term is synonymous with the FAA terms "Resident Engineer" (RE).
E. Contractor and Subcontractor - The term "Contractor" as used herein denotes the firm who will perform and complete the work required by the Contract. The term "subcontractor" as used herein denotes the person or firm retained by the Contractor to perform a particular unit of work required by the Contractor. Subcontractors shall be required to meet all specifications required of the Contractor.
1.4 CONSTRUCTION CONDITIONS
A. Period of Performance - The FAA anticipates construction activities to last no longer than 30 days.
B. Site Location - 41°01'58.6"N 111°50'18.5"W - Google Maps
C. Submittals - Prior to submitting orders, the contractor shall submit specifications for each new component of the installation for approval. Examples of required submittals include the new HVAC units, disconnects, backdraft dampers, diffusers, placards, curbs or stands, duct insulation, etc. Contractor shall provide submittals for
SUMMARY OF WORK PAGE 9
samples, certificates, reports, catalog cuts, letters, shop drawings, maintenance and operations manuals, etc. as required throughout the project. All documents shall be submitted to the COR.
D. Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases.
Specifications shall govern over drawings. If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the RE. No work shall be done until agreement has been made with the RE.
E. Inspection
1. Access for Inspection - The Contractor shall allow the RE complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the RE before being obscured by the next operation of the Contractor. In all cases, the RE shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the RE, may, at the option of the RE be opened for inspection at no additional cost to Government.
The RE will inspect all work in progress up to completion and final Contractor’s Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The RE will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.
2. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The RE will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.
F. Project Coordination - The Contractor shall be required to coordinate his/her construction activities with the FAA through the COR. All work which affects the facility shall be coordinated and approved by FAA personnel through the COR at least forty-eight (48) hours in advance of the scheduled work. Failure to notify and obtain
SUMMARY OF WORK PAGE 10
the necessary approval may result in a rescheduling of the work. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, seventy-two
(72) hours in advance. Each shutdown shall be limited and off-peak hours shall be required for testing or power shutdowns, with the facility placed back in service at the end of the workday, or as stipulated by the FAA.
G. Layout of Work - The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications.
It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.
H. Permits, Inspection, Licenses, Certificates - The Contractor shall obtain and pay fees for permits, inspections, licenses, or certificates required by Federal, State and City/Town officials as necessary to perform the work, prior to starting construction, and in a timely manner to avoid delays in starting the job. The Contractor shall submit evidence that they have obtained all required permits, inspections, licenses, and/or certificates.
I. Compliance with Local and Other Codes - The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.
J. Stop Work Orders – The COR may issue a “stop work order” if any part of the work being performed by Contactor or subcontractor fails to comply with the contract. The Contractor shall not be allowed any extension of time or compensation for damages by reason of, or in connection with, such work stoppage. Serious violations shall be corrected immediately upon notice. Non-serious violations shall be corrected within 24-hours of the non-compliance notice. The Contractor may resume work, at the COR’s discretion, once satisfactory corrective action has been taken to correct the unsafe and unhealthy condition.
K. Protection of Existing Vegetation, Improvements and Structures - The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by
SUMMARY OF WORK PAGE 11
the Contractor or any subcontractors, shall be repaired or replaced to their original conditions by the Contractor at no additional cost to the government. Repairs shall be approved by the COR and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.
L. Schedules
1. Schedule - The Contractor shall, within ten (10) calendar days from date of award of contract, submit to the CO for approval a practical project schedule. The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO. The project schedule shall include a milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).
2. Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.
3. Hours of Work – Shall be approved by the COR. Most of the work is expected to be performed during normal working hours; however, some work may be required afterhours. Work on weekends and Federal holidays shall be approved in advance by the COR in writing.
M. Site Access - Access to the site will be via a pre-determined route identified and agreed upon at the pre-construction conference.
N. Special Permits - The Contractor shall obtain and submit evidence of all necessary permits for the work. The Contractor shall abide by all requirements dictated by the city, state, federal, airport authority or municipality for such permits without any additional cost to the government.
O. Waste Disposal - The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site.
SUMMARY OF WORK PAGE 12
Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of offsite in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste.
The Contractor, at no additional cost to the government, shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the COR.
P. Cleanup - The work site shall be kept clean and orderly during the progress of work.
After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.
Q. O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new equipment. This information will then be retained by the COR (and the FAA) and used to reflect the as-constructed conditions.
R. Warranties - Documentation for the warranties shall be provided to the government upon completion of the project.
1.5 SAFETY
OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:
A. Safety Plan - The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site.
The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.
B. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The COR may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.
C. Lock Out / Tag Out – The Contractor shall employ and detail lock-out / tag-out procedures to employees working with and around electrical systems. When accessing
SUMMARY OF WORK PAGE 13
an electrical panel, a FAA technician must be present prior to interrupting and energizing the breakers.
D. Safety Data Sheets - The Contractor shall have Safety Data Sheets (SDS) conforming to
Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each SDS shall be submitted to the COR and one (1) copy of each SDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable SDS on file at the site until such SDS arrives on site.
E. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.
F. HAZCOM Program - The Contractor shall have a hazard communications (HAZCOM) program. The Contractor and each subcontractor shall submit a copy of their HAZCOM program as well as a copy of their current OSHA 200 form, if requested.
G. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.
H. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site.
The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.
I. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
2.0 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT
2.1 MATERIAL DELIVERIES
All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the pre-construction conference.
2.2 STORAGE AND PROTECTION
SUMMARY OF WORK PAGE 14
The Contractor, through the COR, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas. The storage and protection of Contractor material shall be the sole responsibility of the Contractor. The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.
2.3 PERTINENT INFORMATION
Any pertinent information listed about the contractor-furnished material and equipment shall be submitted to the COR.
3.0 EXECUTION
3.1 WORK SEQUENCE
The ARSR is an active operational facility, which runs 24 hours a day, 7 days a week;
therefore, all work shall be coordinated and accomplished on a “not to interfere with FAA operations” basis. Some of the work performed may have to be accomplished after hours to accommodate Air Traffic Operations. This site may require pre-scheduling due to enhanced security requirements. Many of the steps of this project can be done simultaneously or in a different order.
3.2 CONTRACTOR USE OF PREMISES
A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required.
B. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency vehicles at all time. Do not use these areas for parking or storage of materials.
Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
C. Use of the Existing Building - Maintain the existing building in a watertight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building during the construction period.
SUMMARY OF WORK PAGE 15
END OF SECTION