About this file
The document is a Questions and Answers (Q&A) file for a bathroom remodel solicitation (Notice ID FY2557011021) at the IBWC Falcon Field Office in Falcon Heights, TX. The Q&A provides critical clarifications about the project, including confirmation of four bathrooms to be renovated, specific requirements for lighting, electrical work, fixtures, and finishes. Key details include replacing one light fixture, removing certain electrical outlets, installing wall waste receptacles, adding inside door locks, repairing walls, and addressing shower stall conditions. The project requires ADA compliance, and contractors must perform asbestos and lead paint inspections with potential abatement.
The related federal contract opportunity is a solicitation (FY255701021) issued by the International Boundary and Water Commission, seeking a lowest-price, technically acceptable contractor for the bathroom upgrade. The project is classified under NAICS code 236118 (Residential Remodelers) with a full and open competition approach. Critical dates include a quote submission deadline of March 31, 2025, at 3:00 PM MST, with quotes valid for 90 days. The contractor must complete work within 180 days after award, with a site visit available between March 18-20, 2025. Invoicing will be conducted electronically through the Invoice Processing Platform, and contractors must have an active Unique Entity Identifier (UEI).
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions.docx | DOCX document | |
| SBU IBWC Form 358 Nondisclosure Agreement 20220929.pdf | ||
| CLIN Structure.docx | DOCX document | |
| PWS FY25 Falcon Bathroom Upgrade.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice ID FY2557011021 Bathroom remodel ***Please submit IBWC Form 358 if you wish to receive drawings pics.***
1) Are As Builts available? If yes, can you please provide? See drawing with Falcon Bathroom Facilities and some pictures of current bathrooms.
2) Is it three or four bathrooms? (in the PWS document, in one sentence it states three bathrooms, and elsewhere it states four bathrooms). There are four (4) Bathrooms inside the Power Plant
3) Is plumbing plan available? If yes, can you provide. The drawing shows current plumbing available and locations. ***Please submit IBWC Form 358 if you wish to receive drawings pics.***
4) Does this project include to replace or install new fire sprinkler heads? N/A for this project
5) Does this project include to replace or install new fire alarm devices? N/A for this project
6) Is there currently a company (or companies) that provides fire alarm services and fire sprinkler system services? This item N/A for this project.
7) Does Contractor need to inspect for asbestos and lead paint (currently written in current scope of work)? Yes, if they find something that needs to be inspected
| 8) | If the Contractor needs to inspect for asbestos and lead paint, would the Contractor need to abatement asbestos and/or lead paint if they are found? If yes, how should Contractor price this, since currently it is unknown if there is asbestos or lead paint? Yes, Please include the inspection in the Quote/Bid |
| 9) | The current pricing schedule table, has to provide price for ‘Perform assessment/inspection, please clarify for what to provide assessment/inspection price for? Is it for asbestos and lead paint? Yes, you can include this cost in this CLIN, but mainly to perform the inspection and develop all the material list required to perform this project |
| 10) | Current scope of work states to replace all lighting fixture, but during bid site visit, it was mentioned to replace only one (1) light fixture, please confirm? Yes one for the Generator’s floor bathroom light fixture with extractor. |
| 11) | Should light switches and outlets be replaced, including wiring? Just plug and cover plate |
| 12) | Do we need to paint the hard ceiling in Bathroom #4 (lower level)? Yes |
13) In Bathroom #1 – Single user, do you want the electrical outlet on the lower wall to remain? NO this plug or outlet will be removed
| 14) | In Bathroom #1 – Single user, there are two small holes, one in the floor wall and another in the lower wall, do you want these to be repaired and/or patched? Yes please repaired and painted |
| 15) | Do you want wall installed waste receptacles in each bathroom or freestanding (by Owner)? Yes, please include them in the quote |
| 16) | Do you want locks in the door handle for each bathroom door? Yes, inside locks |
| 17) | Is Contractor to replace acoustical ceiling tiles as needed (broken or damaged ones)? Yes |
| 18) | Please confirm that we are not replacing the shower stall in Bathroom #3 - mens? The trim will stay just fix the wall and install glass Shower Door |
| 19) | We highly recommend not to construct the shower wall to the ceiling because it might run into moisture issues, and relocating the light fixture will be difficult, please confirm that an alternative can be proposed? Yes |
| 20) | The Shower stall base seems to be in bad condition or not looking good, should the contractor propose a solution? Such as to remove the shower stall, and install new shower base and walls with the tiles? Yes |
| 21) | In Bathroom #4, should contractor propose to replace urinal? Urinal stays historical |
| 22) | In bathroom #4, should contractor propose to install wall hung urinal toilet partition? This should reduce sanitary concerns due to close proximity of two (2) compartment sink. N/A |
| 23) | Please confirm, whether the existing toilet partitions in Bathroom #4 are to remain or be replaced? Yes just divider with door needs to be painted |
| 24) | Please confirm if Bathroom #4, to move and install a new mop wash station and to install one (1) new faucet with vanity furniture in addition to replacing two (2) compartment sinks? Yes , please include the cabinets and decorative mirror with light |
| 25) | Does the project need to follow ADA requirements? Yes, Superintendent and COR will perform the inspection |
| 26) | Is there an estimated budget range for this project? N/A |