This is a Scope of Work document from the Ohio Department of Natural Resources (ODNR) Division of Wildlife for wetland embankment stabilization services at Magee Marsh Wildlife Area in Oak Harbor, OH. The project involves maintenance and refreshment of armoring stone on wetland embankment slopes across four sites totaling 4,875 linear feet (Site 1: 2700', Site 2: 500', Site 3: 700', Site 4: 975'). The contractor must provide all labor, materials and equipment to mow vegetation, repair damage from burrowing and wave action, level slopes to 2:1 grade, place Type "B" toe stone (12" x 24") and Type "D" riprap (4" x 12") in a 12-18" thick ribbon from top to bottom of embankments. Mandatory site visits are available by appointment on March 6th and 13th, 2025 at 12:00 PM, and all work must be completed by June 30, 2025.

Contractor bids must be submitted on a per linear foot basis for evaluation, with the final contracted length of embankment and/or sites to be determined based on available project budget. The contract will be awarded to the lowest responsive and responsible bidder. Preference calculations include 5% for the first preference and 2% each for second and third preferences, including Buy American, Buy Ohio, and Veteran-Friendly Business preferences. Prevailing wage rates apply, and contractors must comply with all federal, state and local regulations. The project includes F.O.B. Destination/Pre-Paid/Allowed terms with the contractor bearing freight costs. A staging area is provided for stone stockpiling.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Ohio Department of Natural Resources is requesting bids for: Division of Wildlife Embankment

Stabilization Services

Name or Title of the Service or Supply: Magee Marsh WA Wetland Embankment Stabilization

Ordering Division and Address

Ohio Division of Wildlife

Magee Marsh Wildlife Area

13229 W. State Route 2

Oak Harbor, OH 43449

Project Overview: Contractor shall include the supply of all labor, materials and equipment required to complete the wetland embankment stabilization located at Magee Marsh Wildlife Area. All services must comply with specifications listed below to include but not limited to the following items and comply with federal, state, and local governmental laws, regulations, codes and ordinances. All work will be completed in a manner consistent with customary industrial practices. Contractor shall ensure that the job site is cleaned up, dispose of any debris, and leave no open hazards at the end of every workday.

All itemized scope items below are by contractor unless noted otherwise.

Address of Work Location

Magee Marsh Wildlife Area

13229 West State Route 2

Oak Harbor, OH 43449

Scope of Services:

This project is for the maintenance and refreshment of armoring stone (type “D” Riprap) on wetland embankment slopes on various structures at Magee Marsh wildlife area (figure 1). Bidders will be expected to provide and place all crushed stone. The contractor is expected to (1) mow or grub all vegetation (up to 5” DBH), leaving no more than 3” above ground level, (2) repair any damage from burrowing rodents and wave action prior to armor stone placement, (3) level and smooth the slopes, repairing embankment slopes back to a minimum of 2:1 slope in preparation for armor stone placement. Toe stone (Type “B” rip rap) will be positioned at the base of the structure to prevent downward migration of the placed material. The type “D” armoring stone must be placed, fit, and compacted. Contractors must bid on all tasks per linear foot to be considered):

• Toe stone placement: a layer of Type “B” limestone riprap (measured 12” by 24”) installed along the proposed toe of the structure.

- Site 1 will require placement of new toe stone

- Site 2, 3, 4 -existing stone on the structure that measures 12” by 24” can be repositioned and used as toe stone.

• Place Type “D” limestone riprap (measured 4” by 12”) along the embankment slopes so that the resulting in a minimum ribbon between 12 to 18 inches thick. This will be up to the contractor to ascertain the amounts of stone needed throughout the length of embankment.

• The ribbon of armor stone must run from one foot from the top of the embankment to the bottom of the embankment.

• Approximate length of embankment to be armored.

- Site 1 = 2700 linear feet (figure 2)

- Site 2 = 500 linear feet (figure 3)

- Site 3 = 700 linear feet (figure 4)

- Site 4 = 975 linear feet (figure 5)

• Utilize Staging Area for additional stone stockpiling. (figure 6)

• Care must be taken not to create ruts more than 6 inches deep. All ruts on grass sod dikes will need to be backfilled, compacted, and seeded.

Contractor bids shall be submitted on a per linear foot basis to be considered for evaluation.

Project Timeline: The construction is scheduled to commence on approval of the project purchase order and all work must be completed by June 30, 2025.

F.O.B. DESTINATION/PRE-PAID/ALLOWED. The Contractor must provide Deliverables under this

Contract F.O.B. Destination/Pre-Paid/Allowed. The place of destination will be specified by the Ordering

Agency on the agency’s purchase order or other ordering document. Cost of the freight must be borne and paid by the Contractor unless otherwise stated.

All risk of loss, regardless of the cause, will remain with the Contractor until title to the Deliverable passes to the State. Unless otherwise provided in this Contract, the State will determine whether the

Contractor provided each Deliverable required in this Contract and has fully met all work requirements of this Contract. Title to any Deliverables will pass to the State on Acceptance of the Deliverable.

Evaluation. The contract will be awarded to the lowest responsive and responsible bidder as determined by the State.

Contract Award: The contract will be awarded to the lowest responsive and responsible bidder. The final contracted length of embankment and/or sites (1, 2, 3, or 4) to be armored will be determined based on the accepted bid price per linear foot and the available project budget. Bidders must submit pricing on each site per linear foot per basis. Failure to do so may result in the bid being deemed non-responsive.

Preferences

The State will apply all preferences pursuant to Ohio Administrative Code 123:5-1-06.

Following the initial evaluation and scoring, all Proposals will be considered for preferences.

Preferences will be calculated at a rate of five percent (5%) for the first preference and two percent (2%) each for the second and third preferences. The preferences shall be combined and applied as a total percentage of the original Proposal to determine the score for evaluation purposes.

Preferences will only be applied if there is at least one Offeror that does not qualify for that particular preference. For purposes of qualifying for a preference, an Offeror failing to complete the certification for each preference will be deemed as not qualifying for that preference.

(a) For the Buy American preference, if any Offeror offers a product that is not a domestic source end product, the State will add the applicable percentage of the total available points to the total score of each Offeror offering a domestic source end product.

(b) For the Buy Ohio preference, if any Offeror is a Buy Ohio Offeror claiming the preference, the State will add the applicable percentage of the total available points to each Buy Ohio Offeror’s total score.

(c) If claiming the preferences in (a) and (b) based on the product(s) offered, an Offeror is only eligible to receive the preference if the cost of the product(s) offered exceeds 50% of the total offered cost for products and services. A Buy Ohio Offeror is also eligible to receive the Buy Ohio preference based on its significant economic presence in Ohio or a border state.

(d) For the Veteran-Friendly Business preference, the State will add the applicable percentage of the total available points to any certified veteran-friendly business Offeror’s total score.

Prevailing Wage: Prevailing Wage rates and requirements are applicable to this project.

Contractor’s Statutory Obligations

A. PREVAILING WAGES. Contractor shall comply with the prevailing wage requirements described under

R.C. Chapter 4115 that include, without limitation, the requirements described under this section. If the

Work is subject to payment of prevailing wage rates, the Contractor shall:

1. Pay to laborers and mechanics performing the Work the prevailing wage rates of the Project locality, as determined by the Ohio Department of Commerce, Wage and Hour Bureau;

2. Post in a prominent place readily accessible by all workers on the site, a legible listing of the current classifications of laborers, workers, and mechanics employed under this Agreement;

3. Ensure that the rates posted are current and remain posted in legible condition during the period of this Agreement; and not be entitled to an increase in compensation on account of an increase in prevailing wage rates, except as otherwise provided by applicable law.

The Contractor may access the Ohio Department of Commerce, Wage & Hour Bureau at its website, https://wagehour.com.ohio.gov/w3/webwh.nsf/wrlogin/?openform, to obtain the current wage rates.

B. COMPLIANCE WITH LAWS. Contractor, in the execution of its duties and obligations under this

Agreement, agrees to comply with all applicable federal, state, and local laws, rules, regulations, and ordinances.

C. DRUG-FREE WORKPLACE. Contractor agrees to comply with all applicable federal, state, and local laws regarding smoke-free and drug-free workplaces and shall make a good faith effort to ensure that none of its employees or permitted subcontractors purchase, transfer, use, or possess illegal drugs or alcohol, or abuse prescription drugs in any way while engaged in the Work provided for in this Agreement.

D. NONDISCRIMINATION OF EMPLOYMENT. Pursuant to R.C. § 125.111, Contractor agrees that

Contractor, any subcontractor, and any person acting on behalf of Contractor or a subcontractor, shall not discriminate, by reason of race, color, religion, sex, sexual orientation, age, disability, military status as defined in R.C. § 4112.01, national origin, or ancestry against any citizen of this state in the employment of any person qualified and available to perform the Work. Contractor further agrees that

Contractor, any subcontractor, and any person acting on behalf of Contractor or a subcontractor shall not, in any manner, discriminate against, intimidate, or retaliate against any employee hired for the performance of the Work on account of race, color, religion, sex, sexual orientation, age, disability, military status, national origin, or ancestry. If required by R.C. § 125.111(B) and Ohio Administrative

Code § 123:2-3-02, Contractor shall have a valid Certificate of Compliance (COC) from the Ohio

Department of Development demonstrating compliance with affirmative action program requirements.

E. USE OF MBE AND EDGE VENDORS. R.C. § 125.081 requires state agencies to set aside purchases for

Minority Business Enterprises (“MBE”) and R.C. § 122.92 requires the Department of Development, through the adoption of rules, to establish agency goals for contracting with Encouraging Diversity, Growth and Equity (“EDGE”) businesses which will be applied at the contract level. ODNR encourages

Contractor to purchase goods and services from Ohio-certified MBE and EDGE vendors.

F. CONFLICTS OF INTEREST. No personnel of Contractor who exercise any functions or responsibilities in connection with the review or approval of this Agreement or carrying out of any of the Work shall, prior to the completion of the Work, voluntarily acquire any personal interest, direct or indirect, that is incompatible or in conflict with the discharge and fulfillment of their functions and responsibilities with respect to the carrying out of the Work. Any such person who acquires, whether voluntarily or involuntarily, an incompatible or conflicting personal interest on or after the effective date of this

Agreement shall immediately disclose their interest to ODNR in writing. Thereafter, they shall not participate in any action affecting the Work, unless ODNR shall determine in its sole discretion that, considering the personal interest disclosed, their participation in any such action would not be contrary to the public interest.

Site Visit & Point of Contact

Site visits are mandatory and available by appointment only on Thursday’s March 6th & 13h, 2025 at

12:00 PM. To schedule an appointment, contact: Patrick Baranowski at 419-345-9393 or email

Patrick.baranowski@dnr.ohio.gov

Once a contract is awarded, failure of the bidder to have requested a site visit to become familiar with the facility and requirements of the bid will be insufficient reason to support any request to be released from the contract.

The awarded supplier will be required to sign an Addendum to Bid Quote or Personal Services

Agreement. Example attached.

All bidders must sign and attach the Standard Affirmation & Disclosure Form to their bid in Ohio Buys.

This may be signed electronically through Adobe or through a wet signature. If this is not attached, the winning bidder will be asked to sign before a contract can be routed for review.

mailto:Patrick.baranowski@dnr.ohio.gov

Contact Information: For inquiries or further details concerning this scope of services, please contact:

Patrick Baranowski

ODNR-Division of Wildlife

Assistant Wildlife Management Supervisor

Magee Marsh Wildlife Area

Email patrick.baranowski@dnr.ohio.gov

Phone 419-345-9393 mailto:patrick.baranowski@dnr.ohio.gov

Figure 1 Project overview map

Figure 2 Pump Channel Site 1

Figure 3 Pump Channel Inlet Site 2

Figure 3 East Marsh Site 3

Figure 4 Turtle Creek Site 4

Figure 5 Staging Area