FY24 PWS Train 1 Diffusers Blower and RAS Pumps 7.13.24.pdf
PDF 222 KB Posted
- Attached to
- TRAIN 1 DIFFUSERS
- Solicitation number
- 20244321003
About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity to replace the Train 1 Bioreactor Diffusers, two Blowers, and 4 Return Activated Sludge (RAS) Pumps at the Nogales International Wastewater Treatment Plant (NIWTP) in Arizona.
The key requirements are to replace the specified equipment at the NIWTP to maintain safe and reliable operations. The contractor must provide all labor, materials, and services to complete the work, including securing necessary permits, meeting safety requirements, and providing warranties on the new equipment. The contract has a period of performance of 180 days. This is a 100% Small Business Set-Aside solicitation under NAICS code 221320, with an offer due date of August 12, 2024. The federal agency involved is the International Boundary and Water Commission, United States Section (IBWC). Award will be made on a best value basis considering technical acceptability, technical approach, past performance, and price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USIBWC Nogales Field Office
Replace Train 1 Diffusers, Blowers and 4 RAS Pumps
NIWTP, Nogales, Arizona
April 26, 2024
FY24 PWS Train 1 Diffusers Blower and RAS Pumps 4 26
Performance Work Statement
Nogales International Wastewater Treatment Plant
1.1 Project Overview
The United States Section of the International Boundary and Water Commission (USIBWC) has a requirement to complete the replacement of the Train 1 Bioreactor Diffusers, two Blowers and
4 RAS Pumps in the Nogales International Wastewater Treatment Plant (NIWTP). Replacing the Train 1 Diffusers, two Blowers and 4 RAS Pumps is required to maintain safe and reliable operations of NIWTP.
NIWTP Process
The NIWTP is a Modified Lutzack Enttiger (MLE) Biological Nutrient Removal (BNR) type facility. The NIWTP treatment Capacity is 14.74 MGD and has been operating at or above capacity since constructed in 2009.
The facility consists of a headworks, three Bioreactor basins commonly served by five 400 hp
Spencer centrifugal blowers with each basin separated into seven zones , three circular clarifiers, four return activated sludge (RAS) pumps, two 2.5 meter belt filter presses, one aerobic digester, one waste storage lagoon, five traveling bridge filters and a Ultraviolet distinction facility.
1.2 General
This is a non-personnel services Contract to perform the replacement of Train 1 Diffusers, two
Blowers and 4 RAS Pumps. The Government shall not exercise any supervision or control over the Contract service providers performing the services herein. Such Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.3 Description of Services
The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, permits, and supervision necessary to perform the work as defined in this Performance Work
Statement (PWS).
Specifically, to replace the current Diffusers in Train 1 at the NIWTP, as well as replace two
Blowers and replace 4 RAS Pumps .as per the plant maintenance and repair manuals. Work needs to be done to recover the designed operational capabilities and improve efficiencies as the inflow volume is being increased and since these are critical elements in the effective operation of the NIWTP.
NIWTP, Nogales, Arizona
April 26, 2024
FY24 PWS Train 1 Diffusers Blower and RAS Pumps 4 26
1.4 Objective
To have a fully functional and proper Train 1 Diffusers, two Blowers and 4 RAS Pumps that meets the specifications.
1.5 Project Location
The NIWTP is located in Rio Rico, Santa Cruz County, Arizona, approximately nine miles north of the United States (U.S.)-Mexico border. The treatment plant is situated between the Santa
Cruz River to the east and Arizona Highway 19 to the west. There is a railroad track between the highway and the treatment plant.
The NIWTP address is:
865 East Frontage Road, Rio Rico, Arizona, 85648
1.6 Work Restrictions
The Contractor is responsible for conducting business between the hours of 8:00 AM thru 5:00
PM, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings.
Railroad deliveries block the railroad crossing to/from the plant at random times. The secondary crossing is located about half a mile south of the main entrance and remains open most of the time however, it may not be suitable for all large vehicles.
SECTION 2
PROJECT REQUIREMENTS
2.1 Work Requirements
A. Replace Train 1 Diffusers:
Drain and remove all debris such as grit, sand, rags, sludge and any other items not part of original installation Bioreactor 1 Basin. Remove and dispose off site all removed diffusers and corresponding pipe and accessories which are no longer serviceable.
Replace approximately 3,510 membrane diffusers with same brand, model and specification of membranes as originally .installed. Replace corresponding pipelines and appurtenances that are broken, cracked or in any way no longer serviceable. Make replacements where required to meet standards set for original installation. Review and propose as applicable any new product or system that may be applicable to this task.
NIWTP, Nogales, Arizona
April 26, 2024
FY24 PWS Train 1 Diffusers Blower and RAS Pumps 4 26
B. Replace Blower #3 and #4:
The contractor is to return Aeration Blowers Units BLR-313 & BLR-314 to original as installed condition, performance, and function. This work encompasses replacement, installation and testing of components of blower system to include, electric motor, motor to blower coupling, blower, inlet valve (V-313-1 & V-314-1), pressure gauges, seals, butterfly check valve (V-313-2
& V-314-2), wiring, sensors, flexible couplings, replacement of various hardware components such as nuts, bolts, washers and the like. The work DOES NOT include replacement of control panels.
The government will provide new Spencer model Blowers, new 400hp electric motors, new inlet valves.
C. Replace RAS Pumps
There are 4 pumps connected through a manifold. Three are functioning correctly and one extra is off on standby as back up. Replace as applicable to each existing RAS pump one at a time and ensuring the system is always functional. Ensure replaced pumps are a completed functional system. Start up and Test pumps as appropriate.
1. The Contractor shall provide all labor, equipment, tools, materials, and services to replace Train 1 Diffusers, Blower #3 and Blower #4 and 4 RAS Pumps of the NIWTP with new exact replacements of the existing and fit all existing equipment connections as required.
2. The Contractor shall remove and properly dispose of the existing inoperable equipment and removed parts.
3. The Contractor shall furnish and install new Train 1 Diffusers, two Blowers and 4 RAS
Pumps exact replacements including any ancillary pipes, cables, etc.
4. The Contractor shall start up and test the new Train 1 Diffusers, Blower and 4 RAS
Pumps in accordance with pump manufacturer recommendations.
5. Contractor shall ensure proper functioning and operation of the new pumps and motors.
6. The Contractor shall provide manufacturer’s warranties and update the O&M manuals and the shop drawings.
7. Replaced equipment shall have a life expectancy of 20 years or more.
8. Proposed technology shall be able to interface with the current NIWTP SCADA system.
9. Implementation and installation of the technology shall not interfere with the continued operation of the wastewater treatment plant.
10. Obtain any and all required permits [i.e., Arizona Department of Environmental Quality
(ADEQ), Environmental Protection Agency (EPA) and Union Pacific Railroad
Company (UP)]
11. Clearance of all personnel working on the project.
12. Contractor shall:
• Identify the primary team members to include major subcontractors.
• Contractor shall provide minimum ten (10) years of experience in dewatering technology design for wastewater treatment plants. Describe the Contractor’s experience leading this type and magnitude of project.
• Include a narrative or list describing the roles and responsibilities of each team member.
• Provide resumes for all key personnel.
• Demonstrate prior experience with similar complexity. Provide a list of successful projects utilizing the proposed dewatering technology within the past seven (7) years with a minimum of three (3) years of consistent operation
• Provide a cost estimate of the proposed dewatering technology, including but not limited to, design, equipment, installation, training and potential O&M expenses.
• Provide a baseline schedule that includes, but is not limited to, the time required to obtain permits, design, equipment, installation and training of USIBWC staff for the proposed dewatering technology.
• Design shall be stamped and sealed by a licensed Professional Engineer in
Arizona.
2.2 Existing Train 1 Diffusers Specifications
1. Manufacturer: Sanitaire - SANITAIRE PROJECT#: 07-6666S
2. Model: SILVER SERIES II LP
3. Size: 9”
4. Type: Fine Air Diffuser Membrane Disc
2.3 Existing RAS Pump Specifications
1. Manufacturer: CORNELL PUMP CORNELL FILE MP13997
2. Model: 14NHG-VC18DB Impeller Diameter 17.5" .05°
3. Type: Vertical Dry Pit Centrifugal Pump
4. Capacity: 3610 @22.6@ 600
5. Speed: 600RPM
2.4 Existing Blower Specifications
1. Manufacturer: Spencer
2. Model: C62R1634IA1
3. Type: Power Mizer® Multistage Centrifugal Cast Blowers
2.5 Existing Blower Motor Specifications
1. Manufacturer: Baldor Electric Company, Winding: 18WGY241, 50° C AMB-CONT
2. Horsepower: 400
3. RPM: 3565
4. Service: 460 V, 60 Hz: 3 phase
5. Enclosure: TEFC
6. Temperature Rise: 11°c
7. Type: 18152M
8. Service Factor: 1.15
2.6 Project Schedule
A. The Contractor shall prepare a project schedule which shall reflect completion of all work under this SOW.
B. Schedule Updates
1. The Contractor shall submit a monthly report of the actual work progress and update the schedule as appropriate.
a. The Contractor shall indicate on the schedule those activities that were added, updated, or revised.
b. The progress report shall show the activities or portion of activities completed during the reporting period as an actual completion percentage for each activity.
c. The progress report shall state the percentage of the work completed and scheduled as of the report date.
C. Constraints and work restrictions shall be included in the work schedule.
2.7 Clean-Up and Disposal of Waste Materials
A. The Contractor shall be responsible for the cleanup and disposal of waste materials and rubbish from the site, field office(s), and staging area(s).
B. The disposal of waste materials and rubbish shall be in accordance with applicable
Federal, state, and local laws and regulations and with the requirements in this Contract.
Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply.
1. All waste unless otherwise noted in these specifications shall be disposed of at a licensed landfill or waste disposal facility.
2. Recyclables
a. The Contractor shall dispose of recyclable and reusable products through waste disposal only as a last option.
b. Scrap metal shall be donated or sold to scrap dealers or recycle centers whenever possible.
C. No excess materials shall be deposited within Government property unless compliance confirmed by the Government.
D. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, shall remove all temporary facilities, including, buildings, unused materials, concrete forms, and other like materials, which are not a part of the permanent work.
2.8 Warranty
A. The Contractor shall warrant that work performed under this SOW conforms to the
Contract requirements and is free of any defect in workmanship performed by the
Contractor or any subcontractor or supplier at any tier for a period of at least one (1) year after the completion of work.
B. The Contractor shall obtain warranties from responsible subcontractors, suppliers, and manufacturers, within sixty (60) days after completion of the applicable item of work, but no later than the date of warranty commencement.
C. Starting date of warranty is date of Government acceptance of the work.
D. A warranty requires that if a warranted item fails to meet Contract requirements, it shall be repaired, replaced, or have other remedial actions taken to bring the item into compliance with the Contract requirements. Any item damaged due to failure or malfunction of item warranted under this Contract shall be repaired or replaced at no cost to the Government.
2.9 Inspection and Acceptance Terms
Work will be inspected by the technical representative as outlined in attached QASP.
SECTION 3
DELIVERABLES
3.1 General
A. Deliverables include, but are not limited to:
1. Project Work Plan
a. Within 14 calendar days from contract award, Contractor shall provide work plan.
b. Work plan shall identify the equipment, personnel, and technical approach to be used to complete the work.
c. Work plan shall include Health and Safety Plan and Job Safety Hazard Analysis
d. USIBWC will review the draft work plans and provide comments to the
Contractor within 10 calendar days of receipt of the work plans.
e. The Contractor shall submit final work plans within 10 calendar days of receiving comments from USIBWC.
f. Work can commence only after written approval of the work plan by the COR.
2. Schedule
3. Project Schedule is to be delivered to the COR within seven (7) Calendar Days of contract award. The Contractor shall provide manufacturer’s warranties and update
O&M manuals and the shop drawings.
SECTION 4
PROJECT COORDINATION & ADMINISTRATION
4.1 General
A. The Contractor shall provide all materials, equipment, labor, and services required by this
PWS to perform the work for the Contract sum and within the Contract period of performance – 180 days.
B. The Contractor shall be responsible for ensuring that all its suppliers, manufacturers and subcontractors have reviewed all applicable documents relative to their work. The
Contractor shall provide all labor, material, equipment, and services not provided by the
Contractor’s suppliers, manufacturers, fabricators, and/or subcontractors.
4.2 Security
The Contractor is responsible for securing the work site, equipment, and materials from vandalism and theft.
4.3 Safety
A. The Contractor is solely responsible for worksite safety while performing work or inspections on Government property. The Contractor shall implement a safety program that protects the lives and health of personnel in the project area, prevents damage to property, and avoids work interruptions.
B. The Contractor is responsible for being cognizant of and ensuring compliance with the requirements set forth. Such responsibility shall apply to both the Contractor’s operations and those of the Contractor’s subcontractors.
C. The Contractor shall comply with all provisions of all applicable regulations of the
Occupational Safety and Health Administration (OSHA), 29 CFR 1910, Occupational
Safety and Health Standards, and 29 CFR 1926, Construction Standards.
1. The OSHA 29 CFR 1910 and 29 CFR 1926 can be accessed at http://www.osha.gov or http://www.gpo.gov/fdsys/.
D. The Contractor’s personnel shall be required to use appropriate personal protective equipment such as, but not limited to hard hats, safety goggles, welding shields, face shields, protective footwear, protective gloves, and hearing protection.
E. The Contractor shall perform daily housekeeping. The Government will not provide trash dumpsters.
4.4 Coordination
A. Contract operations shall be coordinated to ensure efficient and orderly progress of each part of the work. In addition to a Project Manager, the Contractor shall provide other administrative and supervisory personnel as required for proper coordination and administration of the work.
B. The Contractor’s Project Manager shall be available to the Government during business hours, as well as in emergencies.
C. After award of the Contract, the Contractor shall not remove, or exchange personnel identified in their proposal unless employment with the Contractor ceases, they are unavailable due to a medical emergency, or they are requested to be replaced by the
Government. Replacement can only take place after written approval from the CO.
http://www.osha.gov/ http://www.gpo.gov/fdsys/
D. The Contractor shall notify the maintenance inspector and the COR within twenty-four (24) hours of any personnel changes in the Project Superintendent, Project Manager, any Field
Superintendents, the Quality Control Manager, or any Safety and Health Officers.
SECTION 5
PROJECT MEETINGS
5.1 General
A. A kickoff meeting is to be held prior to commencing any work and within 15 days of contract award.
B. The Contractor, the COR, or the CO may schedule project meetings at any time.
C. When USIBWC schedules a meeting, the COR shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting.
The COR shall prepare the meeting agenda and distribute to all invited attendees.
D. When the Contractor schedules a meeting, the Contractor shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The Contractor shall prepare the meeting agenda and distribute to all invited attendees.
5.2 Progress Meetings
A. If needed, the COR will schedule progress meetings once the Contractor has mobilized onsite. The COR will conduct and issue minutes of the meetings. Meeting minutes will become official Contract correspondence.
B. The Government may call other meetings on an "as needed" basis.
C. The purpose of these meetings shall be to analyze the progress of the work, resolve conflicts, and in general coordinate the operation of all organizations active at the project site.
SECTION 6
REGULATORY REQUIREMENTS
6.1 Contractor's Responsibility
A. It is the Contractor’s responsibility to perform work in compliance with all applicable requirements of federal, state, and local laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, applicable requirements of the Waste Discharge
Requirements for the United States Section of the International Boundary And Water
Commission South Bay International Wastewater Treatment Plant Discharge to the
Pacific Ocean Through the South Bay Ocean Outfall Order No. R9-2021-0001 as amended by Order No. R9-2023-0009, NPDES No. CA0108928.
B. It shall be the responsibility of the Contractor to acquire copies of all applicable codes, regulations, and standards for ready reference.
C. Prior to the beginning of work, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities.
D. The Contractor shall be responsible for and shall give and maintain all notices required by applicable regulations, laws, or permitting authorities pertaining to work on of this project.
E. In instances where requirements are in conflict, the stricter standard shall apply.
F. All inspections, observations, or tests required for code compliance are the responsibility of the Contractor.
6.2 Permits
A. Prior to the beginning of work, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities. The Government is not responsible for any existing or newly introduced permits required before, during and/or after work on of this project.
B. The Contractor shall be responsible for and shall give and maintain all notices required by applicable regulations, laws, or permitting authorities pertaining to work on of this project.
SECTION 7
MEASUREMENTS AND PAYMENTS
7.1 Progress Payment
A. Invoices shall only include the cost for the work completed during the monthly progress period.
B. Progress payments do not constitute acceptance of any portion of the work and do not reduce the Contractor’s liability to replace unsatisfactory work, material, or equipment.
C. No progress payment will be made when, in the judgment of the Government, the work is not proceeding in accordance with the provisions of the Contract.
7.2 USIBWC Payment Processing
A. The Contractor shall submit invoices via the Invoice Processing Platform (IPP) System.
Further information on IPP will be provided at time of award.
B. The invoice for this Contract shall not be combined with any other work or other
Contracts; it shall be for this Contract only.
--End of Performance Work Statement—