This spreadsheet outlines planned maintenance dredging, new work dredging, and placement area improvement projects for Fiscal Year 2023 for the Galveston District of the U.S. Army Corps of Engineers. Key details include maintenance dredging of channels such as the Houston Ship Channel, Freeport Harbor, and Corpus Christi Ship Channel is planned, with estimated quantities ranging from 800,000 to 2,500,000 cubic yards. New work projects include channel improvement projects for the Brazos Island Harbor, Freeport Harbor, and Sabine-Neches Waterway. Placement area improvements are scheduled for locations including the Galveston Harbor and Channel's Pelican Island and San Jacinto placement areas. Response dates range from January 2023 to August 2023, with award dates from February 2023 through October 2023. Estimated pricing is provided for most projects between $1,000,000 and $250,000,000. The soliciting agency is the U.S. Army Corps of Engineers Galveston District.
This sources sought notice from the U.S. Army Corps of Engineers Engineering District Galveston is seeking information from potential sources for various dredging, dredged material placement, and civil works projects planned for Fiscal Year 2023.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FY23 Programmatic Market Research Sources Sought Notice for the Galveston District.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FY22 OPERATIONS AND MAINTENANCE PROJECTS | |||||||||||||||||
| Fiscal Year | PROJECT TITLE | PROJECT DESCRIPTION | PROJECT AREA OF INTREST | WORK TYPE | NAICS CODE | OPERATION/PROJECT MANAGER | CONTRACTING OFFICE POC | ISSUE DATE | BID OPENING DATE | PROJECTED AWARD DATE | EST. START DATE | EST COMPLETION DATE | ESTIMATED QTY | ESTIMATED PRICE RANGE | DREDGE TYPE | PLACEMENT TYPE | |
| FY23 | Brazos Island Harbor Jetty and Entrance Channels with Optional Beach Placement | Maintenance dredging of Brazos Island Harbor Jetty and Entrance Channels with optional beach placement and option for Port Isabel | Brazos Island Harbor | PA Improvement | 237990 | JONES, SETH | Tate, Danelle- danelle.m.tate@usace.army.mil | 7/23/23 | 8/22/23 | 9/27/22 | 10/27/23 | 5/16/23 | 450,000 CY | Between $1,000,000 and $5,000,000 | Hopper | Upland Confined,/ BU | |
| FY23 | NEW WORK: Brazos Island Harbor Channel Improvement Project - Segment B | New Work Dredging | Brazos Island Harbor | New Work | 237990 | RAMOS-GINES, ORLANDO | SWG-CT-Execution-Proposals@usace.army.mil | 4/2/23 | 7/2/23 | 9/2/23 | 9/28/23 | 1/30/25 | 6,500,000 CY | Between $1,000,000 and $5,000,000 | Pipeline | Upland Confined | |
| FY23 | NEW WORK: BRFG-CRL, Brazos River Crossing | New Work Dredging | Brazos Island Harbor | New Work | 237990 | RAMOS-GINES, ORLANDO | SWG-CT-Execution-Proposals@usace.army.mil | 4/25/23 | 6/9/23 | 9/30/23 | 10/30/23 | 12/29/26 | 400,000 CY | Between $1,000,000 and $5,000,000 | Pipeline | Upland Confined | |
| FY23 | Buffalo Bayou- Engineering Design for improvement to roads to approach basins | Provide a concrete surfaced road from the top of the dam down the closest ramp intersecting a road crossing of the project to the approach basin and connect to existing concrete at approach basin | Buffalo Bayou | TBD | TBD | STANGELAND, GARY | Sewell, Teakeishia- Teakeishia.M.Sewell@usace.army.mil | TBD | TBD | TBD | TBD | TBD | TBD | TBD | N/A | N/A | |
| FY22 | Buffalo Bayou Engineering Design to repair dam faces | Design to repair the face of the dam where "cattle trails" have begun to erode the dam surface. | Buffalo Bayou | TBD | TBD | STANGELAND, GARY | Tate, Danelle- danelle.m.tate@usace.army.mil | TBD | TBD | TBD | TBD | TBD | TBD | TBD | N/A | N/A | |
| FY22 | Buffalo Bayou Stop Log Design | Design stackable stop logs to enable complete closure of a single conduit for each dam. | Buffalo Bayou | TBD | TBD | STANGELAND, GARY | TBD | TBD | TBD | TBD | TBD | TBD | TBD | N/A | N/A | ||
| FY22 | CCSC La Quinta-La Quinta Channel | Maintenance Dredging of the Sabine-Neches Waterway | Corpus Christi Ship Channel | Maintenance Dredging | 237990 | KINMAN, BELYNDA | Slater, Christy- christy.l.slater@usace.army.mil | 7/15/22 | 8/15/22 | 9/15/22 | 10/13/22 | 2/15/23 | 1,000,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Mixed | |
| FY23 | Corpus Christi Ship Channel - Entrance Channel Maintenance | Corpus Christi Ship Channel | Maintenance Dredging | 237990 | KINMAN, BELYNDA | 1/26/23 | 2/25/23 | 3/24/23 | 4/27/23 | 9/24/23 | 2,000,000 CY | Hopper | ODMDS | ||||
| FY23 | NEW WORK: Corpus Christi Ship Channel - Channel Improvement Project (Contract #4 - Inner Harbor) | New Work Dredging | Corpus Christi Ship Channel | New Work | 237990 | KINMAN, BELYNDA | Smith, Lucille- lucille.r.smith@usace.army.mil | 3/28/23 | 4/27/23 | 5/25/23 | 7/11/23 | 1/5/25 | 5,200,000 CY | Between $25,000,000 and $100,000,000 | Pipeline | Mixed/Marsh BU | |
| FY23 | Cedar Bayou Maintenance Dredging | Maintenance dredging of Cedar Bayou | Cedar Bayou | Maintenance Dredging | 237990 | FINN, LISA | Tate, Danelle- danelle.m.tate@usace.army.mil | 5/26/23 | 6/28/23 | 7/23/23 | 9/11/23 | 3/11/24 | TBD | Between $1,000,000 and $5,000,000 | N/A | Open Water | |
| FY22 | Cedar Bayou PA 6 Dike Raise | Project is for dike raising of PA 6 along the Cedar Bayou Channel. Project planned for FY22. | Cedar Bayou | PA Improvement | 237990 | FINN, LISA | Tate, Danelle- danelle.m.tate@usace.army.mil | 2/23/2022 | 3/24/22 | 5/3/22 | 6/8/22 | 4/24/23 | TBD | N/A | N/A | ||
| FY23 | Channel to Victoria Maintenance Dredging | Maintenance dredging of Channel to Victoria | Channel to Victoria | Maintenance Dredging | 237990 | SHERMAN, SCOTT | Tate, Danelle- danelle.m.tate@usace.army.mil | 1/29/23 | 3/1/23 | 3/29/23 | 4/25/23 | 10/24/23 | 800,000 CY | TBD | Pipeline | Upland Confined,/ BU | |
| FY23 | Channel to Victoria PA1 Improvements | Improvements to Channel to Victoria (CTV) Placement Area 1 | Channel to Victoria | PA Improvement | 237990 | SHERMAN, SCOTT | Sewell, Teakeishia- Teakeishia.M.Sewell@usace.army.mil | 5/9/23 | 6/12/2023 | 7/23/23 | 8/9/23 | 3/12/24 | N/A | Between $1,000,000 and $5,000,000 | N/A | Upland | |
| FY22 | Derelict Strutures Removal FY22 | The removal of derelict structures consists of all derelict structure located in the Fort Point Complex. The structures include the UHF Towers, Radioshack, obstacle course, and the boathouse storage (image provided below for orientation). The structures will need to be removed and | |||||||||||||||
| disposed of and real estate will be returned to pre-existing conditions. | Jadwin | Repairs/Construction | 237990 | DIAZ, ROGER | Slater, Christy- christy.l.slater@usace.army.mil | TBD | TBD | TBD | TBD | 6/24/22 | N/A | TBD | N/A | N/A | |||
| FY22 | Fort Point Marine Building 1 Repair FY22 | Repair Marine Building 1 to serve as a temporary operations maintenance building to house the ops maintenance crew. | Jadwin | Repairs/Construction | 237990 | DIAZ, ROGER | Tate, Danelle- danelle.m.tate@usace.army.mil | TBD | TBD | TBD | TBD | 9/1/22 | N/A | TBD | N/A | N/A | |
| FY22 | Fort Point South Guard House Replacement FY22 | The FY22 South Guard House Replacement is anticipated to consist of removal of the existing guard house and repairing utility lines and repairs the structural pad for the placement of a pre-fabricated guard house replacement structure | Jadwin | Repairs/Construction | 237990 | DIAZ, ROGER | Slater, Christy- christy.l.slater@usace.army.mil | TBD | TBD | TBD | TBD | 7/1/22 | N/A | TBD | N/A | N/A | |
| FY23 | NEW WORK: Freeport Reach No. 1,2, and 4-Channel Improvement Project | New Work Dredging | Freeport Harbor | New Work | 237990 | TATE, CARLOS | Smith, Lucille- lucille.r.smith@usace.army.mil | 12/27/22 | 2/2/23 | 3/24/23 | 4/20/23 | 9/21/25 | 17,000,000 CY | Between $100,000,000 and $$250,000,000 | H/P | ODMDS | |
| FY23 | Freeport Harbor -Jetty Channel and Inside Channel SATOC | Maintenance dredging of Freeport Harbor Entrance and Jetty Channel using Task Order of SATOC contract | Freeport Harbor | Maintenance Dredging | 237990 | EDWARDS, ARON | SWG-CT-Execution-Proposals@usace.army.mil | 6/6/23 | 7/6/23 | 9/15/23 | 10/27/23 | 1/19/23 | 2,000,000 CY | Between $5,000,000 and $10,000,000 | Hopper | ODMDS | |
| FY23 | Freeport Harbor - Jetty Channel and Inside Channel (Task Order) | Issue Task Order from Third Ordering Period of Freeport Harbor Entrance and Jetty Channel SATOC. | Freeport Harbor | TBD | 237990 | EDWARDS, ARON | Slater, Christy- christy.l.slater@usace.army.mil | 8/08/2022 | 8/18/22 | 9/09/2022 | 10/14/22 | 12/30/22 | 2,000,000 CY | Between $5,000,000 and $10,000,000 | Hopper | ODMDS | |
| FY23 | Freeport PA 1 Dike Raise | Containment dike raise for Freeport PA 1 including Mob/Demob, Levee Raise, Access |
Dike Preparation & Fly-Ash, Training Dike, Training Dike Fly-Ash subgrade
| stabilization, Perimeter & Lateral Ditches. | Freeport Harbor | PA Improvement | 237990 | EDWARDS, ARON | SWG-CT-Execution-Proposals@usace.army.mil | 7/11/23 | 8/10/23 | 9/8/23 | 10/5/23 | 10/3/24 | N/A | Between $5,000,000 and $10,000,000 | N/A | N/A | |||
| FY23 | Galveston Harbor and Channel-Entrance Channel and HSC Bolivar to Redfish | Maintenance Dredging | Galveston Harbor and Channel | Maintenance Dredging | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 12/13/22 | 1/15/23 | 2/17/23 | 3/14/23 | 9/14/23 | 2,500,000 CY | Between $10,000,000 and $25,000,000 | Hopper | Mixed | |
| FY23 | Galveston Harbor and Channel - Pelican Island PA Improvements | Project is for dewatering and dike raise of the Pelican Island PA and also replace an outfall structure in the PA. Project planned for FY22, but P&S development starting in FY21. Will try and put contract under PA MATOC being currently developed, if not will go IFB. | Galveston Harbor and Channel | PA Improvement | 237990 | COOK, ANDREW | Yocum, Jaclyn- Jaclyn.C.yocum@usace.army.mil | 3/14/23 | 4/12/23 | 6/12/23 | 7/11/23 | 7/11/24 | N/A | Between $5,000,000 and $10,000,000 | N/A | Upland Confined | |
| FY23 | Galveston Harbor and Channel - San Jacinto PA Improvements (PA MATOC Seed Project) | PA improvements | Galveston Harbor and Channel | PA Improvement | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 4/16/23 | 5/15/23 | 6/21/23 | 7/27/23 | 7/27/24 | N/A | Between $10,000,000 and $25,000,000 | N/A | Upland Confined | |
| FY22 | Galveston Harbor - San Jacinto PA Improvements Dewatering | Project is for dewatering and dike raise of the San Jacinto PA and also replace an outfall structure in the PA. Project planned for FY22, but P&S development in FY21. | Galveston Harbor and Channel | PA Improvement | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 2/28/22 | 3/29/22 | 5/4/22 | 6/13/22 | 6/13/23 | N/A | Between $5,000,000 and $10,000,000 | N/A | Upland Confined | |
| FY23 | GIWW Corpus to Port Isabel/Channel to Harlingen Dredging | Maintenance Dredging of GIWW CC Bay to Port Isabel reach with Channel to Harlingen hot spot dredging | GIWW | Maintenance dredging | 237990 | JONES, SETH | Tate, Danelle- danelle.m.tate@usace.army.mil | 7/13/23 | 8/13/23 | 9/13/23 | 10/22/23 | 4/29/24 | 1,000,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Upland Confined,/ BU/ Open Water | |
| FY23 | GIWW Freeport to Upper Matagorda Bay with Channel to Palacios | GIWW | Maintenance dredging | 237990 | JONES, SETH | Sewell, Teakeishia- Teakeishia.M.Sewell@usace.army.mil | 2/4/22 | 3/7/22 | 3/25/22 | 4/14/22 | 9/9/22 | 1,000,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Upland Confined,/ BU/ Open Water | ||
| FY23 | GIWW PA 118A Improvements (Matagorda Bay to Corpus Christi) | Maintenance Dredging of GIWW Matagorda Bay to Corpus Christi | GIWW | Maintenance Dredging | 237990 | JONES, SETH | Smith, Lucille- lucille.r.smith@usace.army.mil | 11/28/22 | 12/28/22 | 1/30/23 | 2/21/23 | 5/30/23 | TBD | Between $5,000,000 and $10,000,000 | TBD | Upland | |
| FY23 | GIWW Matagorda Bay to Corpus Christi Bay Maintenance Dredging | GIWW | Maintenance Dredging | 237990 | JONES, SETH | Tate, Danelle- danelle.m.tate@usace.army.mil | |||||||||||
| FY23 | GIWW Rollover to Causeway and Chocolate Bayou Pipeline Dredging | GIWW | Maintenance Dredging | 237990 | JONES, SETH | Tate, Danelle- danelle.m.tate@usace.army.mil | 7/18/22 | 8/17/22 | 9/14/2022 | 10/18/22 | 3/18/23 | 800,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Upland and Open Water | ||
| FY23 | GIWW-West Galveston Bay Barrieer Island Reconstruction | Maintenance Dredging | GIWW | Maintenance Dredging | 237990 | JONES, SETH | Tate, Danelle- danelle.m.tate@usace.army.mil | 11/29/22 | 12/29/22 | 1/31/23 | 2/22/23 | 8/7/24 | TBD | Between $10,000,000 and $25,000,000 | Pipeline | N/A | |
| FY23 | HSC- Alexander PA Dewatering | PA improvements | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 7/10/23 | 8/8/23 | 9/15/23 | 10/30/23 | 3/4/24 | N/A | Between $1,000,000 and $5,000,000 | N/A | Upland Confined | |
| FY22 | HSC Carpenters to Greens | Maintenance dredging HSC Carpenters to Greens | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Smith, Lucille- lucille.r.smith@usace.army.mil | 1/05/22 | 2/04/22 | 3/11/22 | 11/9/22 | 500,000 CY | Between $5,000,000 and $10,000,000 | Mechanical Pipeline | Upland Confined | ||
| FY23 | HSC Morgans to Exxon & Barbours Cut | Dredging of the Houston Ship Channel generally between Morgan's Point | |||||||||||||||
| and the NW Corner of Alexander Island, near the Exxon Facility. Material will go to Alexander Island Placement Area. | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Sewell, Teakeishia- Teakeishia.M.Sewell@usace.army.mil | 8/22/22 | 10/10/22 | 11/25/22 | 12/22/22 | 9/9/23 | 2,500,000 CY | More than $10,000,000 | Pipeline,Mechanical, Hopper | Upland Confined | |||
| FY23 | HSC PA 14 Dewatering | Dewatering of PA14, an upland site along the Houston Ship Channel | |||||||||||||||
| located on the east side of the Houston Ship Channel, directly across from the entrance to the Bayport Ship Channel. Work will consist of a varying amount of dewatering ditches to dry material and facilitating interior drainage. | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 7/11/22 | 8/9/22 | 9/15/22 | 10/26/22 | 4/27/23 | N/A | Between $1,000,000 and $5,000,000 | N/A | Upland Confined | |||
| FY23 | HSC - Peggy Lake PA Improvements | PA improvements | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Yocum, Jaclyn- Jaclyn.C.yocum@usace.army.mil | 5/24/23 | 6/26/23 | 8/3/23 | 9/17/23 | 9/30/24 | N/A | Between $1,000,000 and $5,000,000 | N/A | Upland Confined | |
| FY23 | NEW WORK: HSC -(ECIP) Segment 3, Barbours Cut Channel, Spilman Island & Morgans Point Bulkhead Walls | New Work Dredging | Houston Ship Channel | New Work | 237990 | COOK, ANDREW | Yocum, Jaclyn- Jaclyn.C.yocum@usace.army.mil | 1/12/23 | 2/14/23 | 6/19/23 | 7/20/23 | 8/15/25 | 2,800,000 CY | Over $25,000,000 | Pipeline | BU Confined | |
| FY23 | HSC- Rosa Allen PA Improvements | PA improvements | Houston Ship Channel | PA Improvement | 237990 | COOK, ANDREW | Tate, Danelle- danelle.m.tate@usace.army.mil | 5/14/23 | 6/13/23 | 7/20/23 | 8/31/23 | 9/1/24 | N/A | Between $5,000,000 and $10,000,000 | N/A | Upland Confined | |
| FY23 | HSC Sims to TB & Light Draft Channel | Maintenance Dredging | Houston Ship Channel | Maintenance Dredging | 237990 | COOK, ANDREW | Slater, Christy- christy.l.slater@usace.army.mil | 12/4/22 | 1/4/23 | 2/13/23 | 3/9/23 | 12/11/23 | 800,000 CY | Between $5,000,000 and $10,000,000 | Mechanical, Pipeline | Upland Confined | |
| FY22 | HSC-TX City-GHC Complex -Hopper MATOC Task Order | Maintenance Dredging | Houston Ship Channel | Maintenance Dredging | 237990 | COOK, ANDREW | Slater, Christy- christy.l.slater@usace.army.mil | 1/18/22 | 2/15/22 | 3/15/22 | 4/15/22 | 8/15/22 | 1,200,000 CY | Between $5,000,000 and $10,000,001 | Hopper | TBD | |
| FY22 | Jadwin 3rd Floor Lighting FY22 | Maintenance Dredging | Jadwin | Maintenance Dredging | 237990 | TBD | Slater, Christy- christy.l.slater@usace.army.mil | TBD | TBD | TBD | TBD | TBD | N/A | Between $5,000,000 and $10,000,002 | N/A | N/A | |
| FY23 | Jadwin Chiller #2 Replacement | Maintenance Dredging | Jadwin | Maintenance Dredging | 237990 | Slater, Christy- christy.l.slater@usace.army.mil | 10/27/22 | 12/26/22 | 12/28/22 | Between $5,000,000 and $10,000,003 | |||||||
| FY22 | Jadwin Exterior Windows FY22 | Maintenance Dredging | Jadwin | Maintenance Dredging | 237990 | TBD | Slater, Christy- christy.l.slater@usace.army.mil | TBD | TBD | TBD | TBD | TBD | N/A | Between $5,000,000 and $10,000,004 | N/A | N/A | |
| FY23 | Mouth of Colorado- Entrance/ Jetty Channel and Detention Basin Dredging | Maintenance Dredging | Mouth of Colorado | Maintenance Dredging | 237990 | JONES, SETH | Slater, Christy- christy.l.slater@usace.army.mil | 5/11/23 | 6/12/23 | 7/13/23 | 8/12/23 | 3/5/24 | 1,000,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Near Shore/ Beach | |
| FY22 | Placement Area Improvement MATOC | Maintenance Dredging | Matagorda Ship Channel | Maintenance Dredging | 237990 | COOK, ANDREW | McCue, Jo- jo.a.mccue@usace.army.mil | 12/10/21 | 1/22/22 | 2/23/22 | TBD | TBD | TBD | Between $25,000,000 and $100,000,000 | Pipeline | N/A | |
| FY23 | Pipeline MATOC Task Order 2- Matagorda Ship Channel, Peninsula to Point Comfort | Maintenance Dredging | Matagorda Ship Channel | Maintenance Dredging | 237990 | EDWARDS, ARON | SWG-CT-Execution-Proposals@usace.army.mil | 12/14/22 | 1/26/22 | 2/23/23 | 3/24/23 | 3/24/24 | 3,000,000 CY | Between $5,000,000 and $10,000,000 | Pipeline | Open Water/ BU | |
| FY23 | SNWW Maintenance Dredging | Maintenance Dredging of the Sabine-Neches Waterway | Sabine-Neches Waterway | Maintenance Dredging | 237990 | SHERMAN, SCOTT | Sewell, Teakeishia- Teakeishia.M.Sewell@usace.army.mil | 1/23/23 | 2/23/23 | 3/24/23 | 4/20/23 | 11/7/23 | 1,300,000 CY | Between $1,000,000 and $5,000,000 | Pipeline | Upland Confined | |
| FY23 | NEW WORK: SNWW- Channel Improvement Project (Contract #6A- Full Depth - Sabine Entracne Channel) | New Work Dredging | Sabine-Neches Waterway | New Work | 237990 | NEALY, FRANCHELLE | SWG-CT-Execution-Proposals@usace.army.mil | 7/5/23 | 8/20/23 | 9/26/23 | 10/25/23 | 7/10/25 | 13,489,000 CY | TBD | HOPPER | ODMDS | |
| FY23 | NEW WORK: SNWW Sabine Bank Channel to Sabine Pass Channel Half Depth (Contract #2B) | New Work Dredging | Sabine-Neches Waterway | New Work | 237990 | SHERMAN, SCOTT | SWG-CT-Execution-Proposals@usace.army.mil | 11/14/22 | 1/4/23 | 3/24/23 | 2/23/23 | 10/23/24 | TBD | TBD | HOPPER | ODMDS | |
| FY22 | Sabine-Neches Waterway - Outer Bar & Bank | Maintenance Dredging of the Sabine-Neches Waterway Outer Bar & Bank | Sabine-Neches Waterway | Maintenance Dredging | 237990 | KINMAN, BELYNDA | Tate, Danelle- danelle.m.tate@usace.army.mil | 4/26/22 | 5/26/22 | 6/27/22 | 7/28/22 | 12/21/22 | 3,000,000 CY | TBD | Hopper or Pipeline | BU Confined | |
| FY23 | NEW WORK: SNWW PA8 Improvements | Project is for work on outfall structures and levee along the road side of PA11 | Sabine-Neches Waterway | PA Improvement | 237990 | NEALY, FRANCHELLE | Tate, Danelle- danelle.m.tate@usace.army.mil | 06/28/23 | 08/06/23 | 08/29/23 | 12/07/23 | 12/30/24 | N/A | TBD | N/A | N/A | |
| FY23 | NEW WORK: SNWW PA11 Improvements | PA improvements | Sabine-Neches Waterway | PA Improvement | 237990 | NEALY, FRANCHELLE | Tate, Danelle- danelle.m.tate@usace.army.mil | 07/28/23 | 08/06/23 | 08/29/23 | 12/07/23 | 11/23/24 | N/A | TBD | N/A | N/A | |
| FY22 | Texas City Ship Channel - Main Channel & Turning Basin | Maintenance Dredging of the Texas City Channel with possible dewatering of PA 5/6 | Texas City Ship Channel | Maintenance Dredging | 237990 | KINMAN, BELYNDA | Tate, Danelle- danelle.m.tate@usace.army.mil | 5/20/2022 | 6/20/22 | 7/22/22 | 8/22/22 | 2/22/23 | 1,500,000 CY | TBD | Pipeline | BU Confined | |
| FY23 | Wallisville Construct North Boat Ramp (BIL) | Tennessee Valley Authority | STANGELAND, GARY | ||||||||||||||
| FY23 | Wallisville Sheetpile Wall Repair | STANGELAND, GARY | |||||||||||||||
| FY23 | Wallisville Sector Gate Rehab (BIL) | Tenness Valley Authority | STANGELAND, GARY |
mailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.milmailto:SWG-CT-Execution-Proposals@usace.army.mil