This is a Performance Work Statement (PWS) for the installation of a second-level storage cage system at Building 3245, USASOC, Fort Belvoir, Virginia, under contract PR&C# W802Y962228645.

The contractor must furnish all labor, supervision, tools, equipment, lifting devices, and incidental materials to inventory, assemble, install, and place into service approximately 85 second-level storage cages above the existing first-level mezzanine cage system. Key tasks include: pre-construction site verification and review of Government-furnished design drawings; material assessment involving unloading and inventorying components from two CONEX containers; secure installation of all framing, panels, doors, and hardware with proper adjustment for operational functionality; and project closeout including debris removal, area cleaning, and provision of a one-year workmanship warranty. The Government provides the storage cage materials, design drawings, CAD backgrounds for as-built drawings, and building access. The contractor must complete all work within 90 calendar days of receiving the Notice to Proceed and submit weekly progress updates. Work shall be performed during normal duty hours (0630-1500) with possible after-hours work requiring Government escorts. The contractor must comply with OSHA requirements, EM 385-1-1 safety standards, National Electric Code, and ADA accessibility requirements. All employees require security vetting including E-Verify pre-screening, Notice of Visit forms submitted three business days in advance, and appropriate background investigations per local security policy. The contractor must submit a comprehensive safety plan within 10 working days of award identifying hazards, control measures, emergency procedures, and personnel qualifications. Work acceptance occurs when all cages are installed and operational, the work area is cleaned, and all punch list items are corrected. The technical point of contact is Michael Johnson (703-428-9172, Building 2593), and the contracting office is HECSA Contracting Office (703-428-7153).

View the file

Other files

File Type Posted
Contractor Question Responses.pdf PDF
CSS_Cages Installation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USASOC BLDG 3245

PERFORMANCE WORK STATEMENT

STORAGE CAGE SYSTEM INSTALLATION

PR&C# W802Y962228645

General Overview:

1.0 Background

The US Army Corps of Engineers has a customer requirement to add to the existing first-level storage cage system located within the warehouse mezzanine of Bldg 3245. The Government has previously procured the materials necessary to construct a second level of storage cages. These materials are currently stored in two (2) Government-owned CONEX containers located adjacent to the building.

The Government requires a Contractor to furnish all labor, supervision, tools, equipment, and incidental materials necessary to inventory, assemble, install, and place into service the second-level storage cage system in accordance with Government-furnished design drawings, located in the building 3245 at Davison Army Airfield (DAAF), Fort Belvoir, Virginia.

2.0 Scope of Work

The Contractor will furnish all labor, supervision, tools, equipment, lifting devices, transportation, and incidental materials necessary to complete the work described herein.

The Contractor will perform the following tasks:

2.1 Pre-Construction

• Attend a site visit with the Government.

• Verify field conditions and dimensions.

• Review Government-furnished drawings.

• Notify the Contracting Officer's Representative (COR) of any discrepancies prior to beginning work.

• Verify that existing conditions are suitable for installation.

2.2 Material Assessment

The Contractor will:

• Unload all Government-furnished storage cage materials from two (2) CONEX containers.

• Inventory and sort all components.

• Verify that all required materials are available for installation.

• Notify the Government immediately of any missing or damaged materials.

• Stage materials in a government-approved laydown area.

2.3 Storage Cage Installation

• Assemble and install approximately eighty-five (85) second-level storage cages above the existing mezzanine.

• Integrate the new cage system with the existing first-level cages.

• Ensure all framing, panels, doors, and hardware are securely installed, plumb, level, and fully operational.

• Adjust all doors and hardware to ensure proper operation.

2.4 Project Closeout

Upon completion, the Contractor will:

• Remove all construction debris and unused materials.

• Clean the work area.

• Provide a one-year warranty on workmanship.

3.0 Government-Furnished Property

The Government will provide:

• Storage cage materials.

• Design drawings.

• CAD backgrounds for as-built drawings.

• Access to Building 3245 and designated work areas.

4.0 Contractor Responsibilities

• Coordinate work with the COR.

• Protect existing Government property.

• Comply with OSHA safety requirements and EM 385-1-1.

• Repair any damage caused by construction activities at no additional cost to the

Government.

• Maintain a clean and safe work area throughout the project.

5.0 Acceptance

The work will be accepted when:

• All storage cages are installed and operational.

• The work area has been cleaned.

• All punch list items have been corrected.

6.0 Period of Performance

The Contractor will complete all work within 90 calendar days after receipt of the Notice to Proceed.

The contractor will also provide weekly progress updates to the government Project Manager throughout the duration of this requirement.

Α.8 The contractor will perform testing and a final serviceability inspection, training to the HEC security office and end user.

Technical point of contact for questions or project visit (recommended) is Michael Johnson, 703-428-9172, room 2D10 in building 2593. Contractual POC is HECSA Contracting Office, 703-428-7153; FAX 703-428-8181.

Performance of Work:

B.1. The contractor will perform this service IAW EM 385-1-1, US Army Corps of Engineers Safety and Health Requirements Manual, National Electric Code (NEC) and, 28 CFR Part 36 and Public Law 101-336 -Americans with Disabilities Act (ADA).

B.2. The contractor will furnish the government with a warranty for a minimum of one year for parts and service (at no additional cost to the government), including all labor and service calls if needed. Contractor will also submit Manufacturers extended warranties on equipment to the POC.

B.3 The contractor will not leave any areas in an unsafe manner and will remove debris from the complex daily. The government will provide the location at the facility for dumpster placement.

B.4 The contractor will verify measurements and site conditions prior to any work starting. Contractor will also provide submittals (and be approved by the POC) for all equipment and materials prior to purchase.

B.5. Any Government property damaged by contractor will be repaired to a condition acceptable to the Government at no additional cost to the Government.

B.6. All work will be performed during normal duty hours, 0630 to 1500, and will be coordinated with the P.O.C. Parts of this work may be required to be done after hours or weekends and the government will provide escorts for contractor personnel to perform work.

B.7. The contractor will be responsible for obtaining all information on manufacture requirements and will install all materials and equipment in accordance with manufacturer's specifications.

B.8. All work will be done in a professional workman like manner.

B.9. All material used for this project will be new, and any requests to use equivalent parts and materials must be made and approved by the POC prior to purchase/installation of materials.

B.10. All work performed will not be accepted until 100 % complete and operational to the satisfaction of the POC (Michael Johnson).

General Security Requirements:

C.1. All contractor and all associated sub-contractor’s employees will comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor will also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

C.2 All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

C.3 The Contractor must pre-screen Candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates must be provided to the COR no later than 3 business days after the initial contract award. *When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative.

This Form will be provided to the Contracting Officer and will become part of the official contract file.

Local Security Policy:

D.1 All contractor employees who require physical access to government-controlled facilities or logical access to government information and or information systems are subject to a fitness determination and appropriate vetting. To assist in the vetting process, the contractor must submit a notice of visit form for each employee who will perform work on the contract, including at the minimum, the name, social security number and date of birth of each employee performing work on the contract that need physical and or logical access.

D.2 Documents containing personally identifiable information may only be submitted via encrypted email, by first class mail or it may be hand carried to the security office. Notice of visits must be submitted through the government contracting officer representative (COR) or technical representative who will deliver them to the security office. All notice of visits must be received three business days in advance of the contractor reporting for work.

D.3 The contractor will work through the COR or technical representative for the contract who will serve as the liaison between the security office and the contractor. Contractor employees who are not sponsored by a government employee will not be granted access to any facilities under HECSA control nor will HECSA security approve logical access to information systems if a notice of visit containing either the DOD ID number or the social security number is not provided to the security office.

D.4 Contractor personnel who do not require a common access card may be granted physical access based on favorable results of an NCIC III records check. Contractors who need a common access card must have the minimum of a favorably adjudicated NACI. If no investigation is on file, the CAC will not be issued until a favorable FBI fingerprints check is received by the security office and the NACI has been initiated in PSIP. HECSA Security will initiate all NACI investigations. Contractors who require access to classified information must be performing work on a classified contract and the contract company is responsible for initiating all required investigations for the appropriate security clearance.

D.5 If an employee has been the subject of a previous favorably adjudicated investigation, it may be reciprocally accepted if there has not been a two-year break in service and there is no presence of new and potentially unfavorable information that casts doubt about the subject’s suitability. When a background check is reciprocally accepted but is more than 5 years old, the security office may initiate an NCIC III check to ensure no new unfavorable information exists.

D.6 Contractor employees whose access to classified information has been suspended or revoked will not be authorized logical access to government information systems IAW

AR 25-2 paragraph 4-14 b (2) until that investigation is favorably adjudicated. These personnel will also not be allowed unescorted access to government facilities until the investigation has been favorably adjudicated by the Command Security Manager. OPM Final Credentialing Standards allow agencies to deny a CAC or PIV card to any individual who has had their access to classified information denied or revoked. Further due process is not required in these situations. The contractor must provide employees who can be cleared to perform work and must immediately provide replacement employees for those who cannot be cleared.

Accident Prevention and Requirements:

E.1 In performing this contract, the contractor will provide for protecting the lives and health of employees and other persons; preventing damage to property, materials, supplies and equipment; and avoiding work interruptions. For these purposes, the Contractor will:

(1) Comply with all pertinent provisions of the most recent version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation and available at:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_3 85-1-1_2008Sep_Consolidated_2011Aug.pdf ;

(2) Provide appropriate safety personal protection equipment (steel toe safety boots, eye protection, hearing protection, reflective vests, etc.) as required by the Position Hazard Analysis.

(2) Comply with the standards issued by the Secretary of Labor in 29 CFR Part 1910 and or 29 CFR Part 1926.

(3) Safeguard the public and Government personnel, property, materials, supplies, and

(4) equipment exposed to Contractor operations and activities.

(5) Avoid interruptions of Government operations and delays in project completion dates, and.

(6) Control costs in the performance of this contract.

E.2 Additionally, for these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor will also --

(1) Provide appropriate safety barricades, signs, and signal lights, and.

(2) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1_2008Sep_Consolidated_2011Aug.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1_2008Sep_Consolidated_2011Aug.pdf

E.3 Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer will notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor’s representative at the work site, will be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor will immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor will not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any Stop-Work Order issued under this clause.

E.4 The Contractor will require any/all subcontractors to comply with these safety requirements.

E.5 After receipt of a notice of award, the Contractor will:

(1) Submit in writing (within 10 working days) a proposal for effectuating this provision for accident prevention. The plan will include an analysis of the significant hazards to life, limb, and property inherent in the contract work performance and a plan for controlling these hazards.

(2) The plan, which will be reviewed by the Humphreys Engineer Center Support Activity, Safety and Occupational Health Office will include but not be limited to the following:

(a) Identification and signature of on-site contractor safety officer.

(b) Identification and telephone numbers of medical emergency facilities.

(c) Medical emergency response procedures (what to do in a medical emergency).

(d) Plans for initial safety indoctrination and continuing safety training for employees.

(e) Hazard analysis and abatement.

(f) Personal protective equipment.

(g) Procedures to be used for accident reporting and investigating.

(h) Criteria for reprimand due to willful negligence towards safety standards.

(3) Meet in conference with representatives of the Contracting Officer to discuss and develop mutual understanding relative to administration of the overall safety program.

File details come from the government source that posted it. Updated .