FWC ITB 26.27-06 Addendum No.1.pdf
PDF 685 KB Posted
- Attached to
- BWWMA Fence Supply Project
- Solicitation number
- ITB-16577
- Issued by
- Leon County, Florida
About this file
This is Addendum No. 1 to an Invitation to Bid (ITB) issued by the Florida Fish and Wildlife Conservation Commission for the BWWMA Fence Supply Project. The addendum addresses clarifications regarding subcontracting, material suppliers, and bid submission procedures for fencing supplies to the Babcock/Webb Wildlife Management Area in Punta Gorda. The project requires delivery of 3,200 wooden fence posts (6' 4-5"), 200 wooden posts (8' 6"), 1,360 galvanized steel T-posts, 400 rolls of barbed wire, 40 rolls of brace wire, galvanized steel spikes, and fence staples. All sealed bids must be received by mail no later than 3:30 PM ET on Friday, August 14, 2026, with anticipated award on August 19, 2026. Public bid opening will occur on August 14, 2026 via in-person attendance or teleconference. The contract will be effective for one year upon issuance of the Purchase Order, with all fencing supplies required to be delivered by February 1, 2027, within three months of Purchase Order issuance.
The estimated budget for this project is $95,000. Price quotes must exclude federal and state sales or use taxes and include all delivery fees and necessary items to complete the project. Subcontracting is not permitted for this project; however, material suppliers are not legally considered subcontractors and may be utilized, provided they do not deliver supplies on the awarded vendor's behalf. Bidders must be registered in MyFloridaMarketPlace (MFMP) and SunBiz prior to bid opening and must submit a minimum of three references for similar completed projects. All items must be bid or the bid will be rejected. The award will go to the responsive, responsible bidder submitting the lowest total price. Failure to meet the February 1, 2027 completion date will trigger liquidated damages of $100 per calendar day of delay. A Subcontractor Minority Status Report must be submitted with each invoice for payment, with vendors indicating "N/A" given the prohibition on subcontracting.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC ITB 26.27-06 Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners Rodney Barreto Chairman Coral Gables
Steven Hudson Vice Chairman Fort Lauderdale
Preston Farrior Tampa
Joshua Kellam Palm Beach Gardens
Gary Lester Oxford
Albert Maury Coral Gables
Sonya Rood St. Augustine
Office of the Executive Director Roger A. Young Executive Director
Charles “Rett” Boyd Assistant Executive Director
George Warthen Chief Conservation Officer
Jessica Crawford Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street Tallahassee, Florida 32399-1600 Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T) 800-955-8770 (V)
MyFWC.com
DATE: AUGUST 7, 2026
ADDENDUM NO.: 1
BID NO.: FWC 26/27-06
BID TITLE: BWWMA FENCE SUPPLY PROJECT
UPDATE: QUESTIONS AND ANSWERS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s (FWC) Solicitation No. FWC 26/27-01, “BWWMA Fence Supply Project”.
All responses to the subject solicitation must be received no later than 3:30 PM (ET) on Friday, August 14, 2026.
A response received after the exact time specified will not be considered. Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes.
Written notices, formal requests and proceedings must conform with the requirements set forth in Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875 Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Adrian Wiggins FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
BEGIN ADDENDUM
QUESTION #1
Can you please specify your interpretation of a subcontractor?
ANSWER #1
Subcontracting will not be allowed for this ITB. The Subcontractor Minority Status Report (Attachment C) will need to be submitted with each invoice, the contractor should in indicate “N/A” since the project does not allow subcontractors. A subcontractor is a person or company hired by the awarded contractor to perform the service that is being bid.
QUESTION #2
Do you consider a material supplier as a subcontractor?
ANSWER #2
Under Florida Law, a material supplier is not legally considered a subcontractor. The material supplier used cannot deliver the fencing supplies on the awarded vendor’s behalf.
QUESTION #3
Can bid be submitted by email, or do the completed bids need to be sealed and mailed in?
ANSWER #3
All bids pertaining to this ITB will need to be submitted by mail and sealed.