This is an Invitation to Bid (ITB) issued by the Florida Fish and Wildlife Conservation Commission (FWC) for Chassahowitzka Wildlife Management Area (WMA) Road Maintenance, solicitation number FWC 25/26-12. The project involves maintaining approximately 27.44 miles of roads within the Chassahowitzka WMA, with work to be conducted during two 2-month periods: September-October (Period A) and April-May (Period B). The contractor will be responsible for providing equipment, labor, and road materials to grade roads during Period A and add road material, grade, and compact during Period B. The bid is advertised on August 8, 2025, with sealed bids due by August 26, 2025, at 3:00 PM ET. A mandatory site visit is required for bidders, and the contract will be effective for one year upon issuance of the purchase order, with potential renewal options for up to three additional years.
The estimated budget for the project is $200,000, with bidders required to provide pricing per 0.5-mile of road maintenance. The contract will be awarded to the responsive, responsible bidder submitting the lowest total bid price, with the FWC reserving the right to increase or decrease the project scope based on budgetary constraints. Bidders must be registered in the MyFloridaMarketPlace (MFMP) and Sunbiz systems, and certified minority-owned, woman-owned, and service-disabled veteran business enterprises are encouraged to participate. The contractor must use DOT-certified lime rock road base, provide all necessary equipment including a motor grader, compactor, and water truck, and comply with various state and federal regulations regarding employment verification, labor practices, and commodity sourcing.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION
1875 ORANGE AVE E
TALLAHASSEE, FL 32311-6160
(850) 488-6551
CHASSAHOWITZKA WMA ROAD MAINTENANCE
FWC 25/26-12
INVITATION TO BID
ITB BIDDER ACKNOWLEDGEMENT FORM
Purpose: The intent of this bid is to obtain competitive pricing for To procure price per 0.5-mile quotations for maintaining roads within Chassahowitzka Wildlife Management Area. Prices to be quoted per each maintenance period (A & B)., per the specifications contained herein. Only responsive and responsible Contractors will be considered for award of this Invitation to Bid (ITB).
Responsive: To be responsive, a bid must constitute a definite, firm, unqualified and unconditional offer to meet all of the material terms of this ITB. Material terms are those that could affect the price, quantity, quality, or delivery. Also included as material terms are those which are clearly identified in this ITB and which, for reasons of policy, must be complied with at risk of bid rejection for non-responsiveness.
Non-Responsive: Any submission that does not comply with this ITB in any way, does not contain all the properly signed forms, supplements or deviates from the Bid requirements or has an incomplete Price Sheet may be considered nonresponsive at the discretion of the Procurement Manager.
Responsible Vendors: The Commission shall only consider responsible vendors. Responsible vendors are those that have, in the sole judgment of the Commission, the financial ability, experience, resources, skills, capability, reliability and business integrity necessary to perform the requirements of the contract. The Commission may also consider references and quality to determine the responsibility of the bid. The Commission reserves the right to use any information, whether supplied through the Bidder’s submission or otherwise obtained, in determining responsibility.
Sealed Bid: In response to an Invitation to Bid (ITB), a sealed bid is the final submission of a bid from a vendor prior to the bid deadline, after which no further submissions will be considered.
Rejection of Bids: The Commission reserves the right to reject any and all bids and to waive any minor irregularity in the submissions received in response to this ITB. The Commission reserves the right to consider all information, whether submitted or otherwise, to determine responsiveness and responsibility and to reject bids accordingly.
Name of Business: ____________________________________________________________________________________________________
Contact Person Name: _________________________________________________________________________________________________
Business Address: ____________________________________________________________________________________________________
City: ____________________________ State: _____________________________ Zip code: ______________________________________
Phone: ___________________________ Fax: _______________________________ Email: ______________________________________
Federal Employer Identification Number: ____________________ Contractor’s License Number: _______________________________
The undersigned attest to the following:
“We understand all of the terms, conditions and the specifications contained herein and agree to abide by all of the terms, conditions and the specifications in their entirety. We have examined the site in reference to the specifications contained within this ITB and have familiarized ourselves with the entire site and have examined carefully the extent of the work that is needed.”
Authorized Signature (Manual): ________________________________________________________________________________________
Authorized Signature Name (Typed) and Title: __________________________________________________________________________
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 3 of 65
CALENDAR OF EVENTS
FWC 25/26-12
SCHEDULE DUE DATE METHOD
Bid Advertised August 8, 2025 Posted on the Vendor Information Portal
(VIP)
Deadline for Questions
Must be received
PRIOR to:
August 14, 2025
@ 5:00 PM ET
See Solicitation Questions Clause
Anticipated date for Responses to Written Questions August 20, 2025 Posted on the Vendor Information Portal
SEALED BIDS DUE
(REMEMBER: The bid number should be clearly marked on envelope)
Must be received
PRIOR to:
August 26, 2025
@ 3:00 PM ET
Mailing Address:
Florida Fish & Wildlife Conservation
Commission
Attn: Purchasing
1875 Orange Ave E
Tallahassee, Florida 32311-6160
Submissions are due BEFORE the date and time of the public opening.
Public Bid Opening August 26, 2025
@ 3:00 PM ET
Public Opening Options for Attendance:
-In Person-
1875 Orange Ave E
Tallahassee, FL 32311-6160
-Teleconference-
Conference call phone number:
1.888.585.9008
Conference room number: 218-721-199
Anticipated Date of Intended
Award September 2, 2025 Posted on the Vendor Information Portal https://vendor.myfloridamarketplace.com/
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 4 of 65
GENERAL CONDITIONS
FWC 25/26-12
The Florida Fish and Wildlife Conservation Commission’s (FWC or Commission) mission is to manage fish and wildlife resources for their long-term well-being and the benefit of people. The Commission administers six (6) major programs including habitat and species conservation, freshwater fisheries management, law enforcement, marine fisheries management, hunting and game management and fish and wildlife research.
A Bidder submitting a bid shall be registered in the MyFloridaMarketPlace (MFMP) system and where required, the Sunbiz system prior to the bid opening. Business entities which must be on file with Sunbiz include the following foreign and domestic entities: Corporations for and not for profit, Limited Liability
Companies (LLC), Limited Partnerships (LP) including Limited Liability Limited Partnerships (LLLP), and organizations doing business under a fictitious name (DBA). A Bidder may not be considered for an award, if not registered in the MFMP and Sunbiz system. The Bidder’s registration address and federal employer identification (FEID) number should match the Bidder’s address and FEID number listed on the
Bidder Acknowledgment form (page 2).
Certified Minority-owned, Woman-owned and Service-Disabled Veteran Business Enterprises, as certified by the State of Florida Office of Supplier Development, are encouraged by the Commission to participate in the bidding process.
Bids from Bidders shall include all necessary equipment to complete the job. The bidder is required to supply all specified documentation when submitting a bid for this project.
Please note:
• The terms “Contract,” “Agreement” and “Purchase Order” are used interchangeably in the document.
• The terms “Commodities” and “Goods” are used interchangeably in the document.
TERMS AND CONDITIONS
PUR 1000 and PUR1001 are hereby incorporated by reference. PUR1000 and PUR1001 can be found at the
Department of Management Services website at the following link:
https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purc hasing_pur_forms
The following terms and conditions take precedence over the PUR1001 and PUR1000 forms where applicable. The Commission objects to and shall not consider any additional terms or conditions submitted by a Bidder or Contractor, including any appearing in documents attached as part of a Bidder’s response.
In signing and submitting its bid, a Bidder agrees that any additional terms or conditions, whether submitted intentionally or inadvertently, shall have no force or effect. Failure to comply with terms and conditions, including those specifying information that must be submitted with a bid, shall be grounds for rejecting a bid.
The terms and conditions of Attachment A, Purchase Order Terms and Conditions, are hereby incorporated into this solicitation. Any contract resulting from this solicitation will include the terms and conditions of this solicitation and the terms and conditions contained in Attachment A.
https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purchasing_pur_forms https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purchasing_pur_forms
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 5 of 65
PROCUREMENT MANAGER
Randy Golightly
Randolph.golightly@myfwc.com
ESTIMATED BUDGET
The Commission has an estimated budget for this project of $200,000.
TERM
The contract will be effective one year upon issuance of Purchase Order.
If circumstances constituting Force Majeure have occurred, or if anything occurs beyond the Contractor’s control, the Contractor shall submit an extension request in writing. The Project Manager and Contract
Manager will review the extension request and if they determine it is justified, will forward to the Bid
Request Inbox (bidrequest@myfwc.com) for procurement review and approval/disapproval.
RENEWAL
The Commission has the option to renew this Contract on a yearly basis for a period up to three (3) years after the initial Contract period upon the same terms and conditions contained herein. Pursuant to Sections
287.057(1)(a)2., and 287.057(1)(a)3., Florida Statutes (F.S.), each Bidder shall supply a price for each year that a contract may be renewed. Evaluation of bids shall include consideration of the total cost of the contract, including the total cost for each renewal year, as submitted by the Bidder.
Exercise of the renewal option is at the Commission’s sole discretion and shall be conditioned, at a minimum, on the Contractor’s satisfactory performance of this Contract and is subject to the availability of funds. The Contractor if it desires to exercise this renewal option will provide written notice to the
Commission no later than thirty (30) days prior to the Contract expiration date. The renewal term shall require written approval from the Commission’s Procurement Manager.
SUBCONTRACTS
Subcontracting IS NOT permitted pursuant to the Terms and Conditions of the Contract. The
Subcontractor Minority Status Report (Composite Exhibit I) shall be submitted with each invoice for payment.
DIVERSITY
The Commission is committed to supporting Florida’s diverse business industry and population through ensuring participation by minority, women, and veteran-owned business enterprises in the economic life of the state. The State of Florida Mentor Protégé Program connects minority, women, and veteran-owned business enterprises with private corporations for business development mentoring. We strongly encourage contractors doing business with the State of Florida to consider this initiative. For more information on the
Mentor Protégé Program, please contact the Office of Supplier Development at (850) 487-0915 or osdinfo@dms.myflorida.com.
FWC encourages diversity in its procurement program and requests that all subcontracting opportunities afforded by this solicitation enthusiastically embrace diversity. The award of subcontracts should reflect the vast array of citizens in the State of Florida. Bidders can visit the Office of Supplier Development website for information on certified business enterprises that may be considered for subcontracting opportunities. However, pursuant to Section 287.05701 F.S., the Commission may not request documentation of or consider a vendor’s social, political, or ideological interests when determining if the mailto:bidrequest@myfwc.com?subject=Extension%20Request https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program mailto:osdinfo@dms.myflorida.com https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 6 of 65 vendor is a responsible vendor, nor give preference to a vendor based on the vendor’s social, political, or ideological interests.
MANDATORY BIDDER SITE VISIT
It is mandatory that prospective bidders inspect the project sites prior to submitting a bid. This will enable bidders to familiarize themselves with the scope of work. Bidders shall visit the sites on their own. The Site
Visit Mandatory Attestation-Individual Bidder Attendance form (Attachment B) must be completed by the
Contractor and submitted with the bid package. FWC will only issue an official written response to verbal questions subsequently submitted in writing in accordance with the Deadline for Questions clause below.
The Chassahowitzka Wildlife Management Area (CWMA) main entrance is located in Hernando County, FL approximately 0.2 miles north of the US 19 and Centralia Rd. intersection. However other entrances may be used depending on project locations. (See Figure 1 for general location)
Project Access Point(s):
• The main entrance is located at 13243 Commercial Way, Weeki Wachee, FL 34614.
VERBAL INSTRUCTION PROCEDURE
Bidders may not consider any verbal instructions as binding upon the Commission. No negotiations, discussions, or actions shall be initiated or executed by the Bidder as a result of any discussion with any
Commission employee. Only those communications from the Commission that are in writing, may be considered as a duly authorized expression on behalf of the Commission.
SOLICITATION QUESTIONS
Any questions from Bidders that require an official FWC answer concerning this project shall be submitted in writing to the Procurement Manager. This includes specification inquiries, such as questions or requests for additional or altered terms and conditions. Questions to the Procurement Manager shall not constitute formal protest of the specifications or of the solicitation. Questions must be received no later than the date and time specified in the Calendar of Events (Page 3). Questions may be sent via email with the solicitation number in the subject line. It is the responsibility of the bidder to confirm receipt of questions if needed.
If questions are received, an addendum will be issued and shall be posted on the Vendor Information Portal
(https://vendor.myfloridamarketplace.com).
LIMITATION ON BIDDER CONTACT DURING SOLICITATION PERIOD
Bidders to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the Commission posting the notice of intended award, (i.e., the 72-hour posting period excludes Saturdays, Sundays, and state holidays) any employee or officer of the executive or legislative branch concerning any aspect of this solicitation, except in writing to the Procurement Manager or as provided in the solicitation documents. Violation of this provision may be grounds for rejecting a response.
BIDDER SPECIFICATION CHALLENGE
Any protest concerning the specifications of this solicitation shall be made in accordance with PUR1001, paragraph 20, “Protests”. A notice of protest of the solicitation documents shall be made within seventy-two hours after the posting of the solicitation. Failure to file a protest within the time prescribed in Section
120.57(3)(b), F.S., shall constitute a waiver of proceedings under Chapter 120, F.S.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 7 of 65
ADDENDUMS
If the Commission finds it necessary to supplement, modify or interpret any portion of the specifications or documents or answer any Bidder questions during the ITB period an addendum shall be posted on the
Vendor Information Portal internet site. Each Bidder is responsible for monitoring the Vendor Information
Portal website (https://vendor.myfloridamarketplace.com) for new or changing information relative to this procurement. The Commission bears no responsibility for any delays, or resulting impacts, associated with a
Bidder’s failure to obtain the information made available through the Vendor Information Portal.
BIDDER ACKNOWLEDGMENT
In order for this bid to be valid, the bid must be completed in its entirety, signed by the Bidder and returned, as part of the bid or the bid will be rejected. By affixing your signature to the ITB Bidder Acknowledgement
Form (page 2), the Bidder hereby states that the Bidder has read all bid specifications and conditions and agrees to all terms, conditions, provisions, specifications, and is currently licensed to do business within the
State of Florida, if required by State or Federal Law, for the services or commodities the Bidder will provide the Commission under these bid specifications.
REFERENCES
Each prospective Bidder shall provide a minimum of three (3) references for similar projects completed.
Current contact names and phone numbers shall be included with the bid package. See the attached references form for more detail.
EQUAL BIDS
In the event that there is no multiple award contemplated in the ITB, and the Commission receives equal bids eligible for award, the Commission will comply with the following, as applicable: sections 287.057(12), 287.082, 287.087,287.092, 295.187(4)(a), and 295.187(4)(b), F.S. In order to clarify the Bidders’ status with regard to the applicable statutory preference requirements, the Commission may request information from
Bidders with equal bids. A Bidder will not be permitted to amend or supplement its Bid in response to such request for clarification. If the tie has not been broken by application of the aforementioned statutes, the
Commission will proceed with a random selection to decide the award.
SUPPORTING/SUPPLEMENTAL INFORMATION
The Commission requires that bidders submit all required technical, specification, and other supporting information with their bid, so that a detailed analysis and determination can be made, by the Contract
Manager that the product/service offered meets this ITB’s specifications and that other requirements of this ITB have been met. However, provided a bid meets the requirements for a definite, firm, unqualified, and unconditional offer, the Commission reserves the right to request supplemental information from the bidder after the bids have been opened to ensure that the products/services offered completely meet this
ITB’s requirements. The requirement for such supplemental information will be at the reasonable discretion of the Commission and may include the requirement that a bidder will provide a sample product(s) so that the Commission can make a first-hand examination and determination.
A bidder's failure to provide this supplemental information or the product sample(s), within the time set by the Commission, will cause the Commission to consider the Contractor non-responsive and reject the
Contractor’s bid.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 8 of 65
CONFIDENTIALITY/PUBLIC RECORDS LAW
Bidders are cautioned that Florida law generously defines what constitutes a public record and grants broad rights of public access to those records; see, for example, section 119.07, F.S. If a Bidder believes that its response contains information that is confidential or exempt from disclosure under Florida Law, the Bidder shall clearly segregate and mark that information (for example, stamp each page "Confidential" and place it in an envelope marked "Confidential") and briefly describe in writing the grounds and specific legal citations for claiming exemption from the public records law. If after the notice of intended decision or thirty
(30) days after bid opening, whichever is earlier, the Commission receives a public record request related to the solicitation, the Commission will provide copies of public records that are not exempt to the requester.
The Commission will endeavor to provide notice to the Bidder of all public records requests received related to documents provided by the Bidder that were marked pursuant to this paragraph. In no event shall the
Bidder hold the Commission or any of its employees or agents liable for disclosing, or otherwise failing to protect the confidentiality of, information submitted in response to this solicitation.
MAILING INSTRUCTIONS
All bids shall be submitted in a SEALED ENVELOPE addressed to:
Florida Fish and Wildlife Conservation Commission
Attn: Purchasing
1875 Orange Ave E
Tallahassee, Florida 32311-6160.
The envelope shall be plainly marked on the outside with: BID NUMBER, DATE AND TIME OF THE BID
OPENING.
THE COMMISSION IS NOT RESPONSIBLE FOR THE OPENING OF ANY ENVELOPES THAT ARE NOT PROPERLY
MARKED.
PLEASE NOTE: The Commission’s official business hours of operation are 8:00 AM–5:00 PM ET, exclusive of Saturdays, Sundays and state holidays. Selecting delivery services, such as next day first delivery, may result in attempted delivery prior to opening or closing, and the Commission will not be available to accept those deliveries. THE COMMISSION IS NOT RESPONSIBLE FOR LATE SUBMISSIONS DUE TO COMPLICATIONS
RELATED TO SELECTED DELIVERY SERVICES. DIGITAL SUBMISSIONS SHALL BE DEEMED NON-RESPONSIVE
AND SHALL NOT BE ACCEPTED.
SOLICITATION PUBLIC OPENING
The public opening of this bid will be conducted at the date, time and method specified on the Calendar of
Events (Page 3). BIDS RECEIVED AFTER THE SPECIFIED DATE AND TIME WILL BE REJECTED.
Any person with a qualified disability shall not be denied equal access and effective communication regarding any bid/proposal documents or the attendance at any related meeting or bid/proposal opening. If accommodations are needed because of a disability, please contact the Purchasing Section at (850) 488-6551 at least three (3) workdays prior to the opening.
AWARDED BID/INSPECTION
The Commission will award the bid to the responsive, responsible bidder who submits the lowest bid price.
If deemed necessary, an interview with the bidder by the Contract Manager may be required before the bid is awarded.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 9 of 65
The Commission reserves the right to inspect the prospective Contractor’s materials and background record prior to making an award of the Contract. If the Contract Manager determines the lowest bidder does not have sufficient experience, equipment, etc. to meet the specifications of this ITB, the Commission reserves the right to reject the bidder and evaluate the next lowest bidder.
POSTING OF BID TABS
Bid Tabulations with Contractors identified as awarded bidders will be posted electronically as Agency
Decisions on the Department of Management Services Vendor Information Portal as a Public Notice. The
Agency Decision may be viewed at https://vendor.myfloridamarketplace.com, and will remain posted for a period of 72 hours. Failure to file a protest within the time prescribed in Section 120.57(3)(b), F.S., shall constitute a waiver of proceedings under Chapter 120, F.S.
Awarded Bidders are instructed not to proceed until a Purchase Order, Formal Written Contract, Lease, Notice to Proceed, or some other form of written notice is given to the Contractor by the Commission. A company or person who proceeds prior to receiving a Purchase Order, Formal Written Contract, Lease, Notice to Proceed, or some other form of written notice from the Commission does so without a contract and at their own risk.
Sealed bids, proposals, or replies received by an agency pursuant to a competitive solicitation are exempt from s. 119.07(1) and s. 24(a), Art. I of the State Constitution until such time as the agency provides notice of an intended decision or until thirty (30) days after opening the bids, proposals, or final replies, whichever is earlier.
SCOPE CHANGES AFTER CONTRACT EXECUTION
The Commission shall provide written notice to the successful bidder thirty (30) days in advance of any
Commission required changes to the technical specifications and/or scope of service that affect the successful bidder’s ability to provide the service as specified herein. Any changes that are other than purely administrative changes will require a formal contract amendment.
FWC CONTRACT MANAGER
The FWC employee identified as the Contract Manager shall perform the following on behalf of the FWC:
• review, verify, and approve receipt of services/deliverables from the Contractor;
• submit requests for change orders/amendments/renewals, if applicable;
• review, verify, and approve invoices from the Contractor; and, if applicable, complete the
Certificate of Contract Completion form; and
• maintain an official record of all correspondence between the Commission and the Contractor and forward the original correspondence to the Procurement Manager for the official file.
DELIVERABLES
The following services or service tasks are identified as deliverables for the purposes of the subsequent
Contract:
a. Performance of all services set forth in the Scope of Work.
b. Submission of all invoicing, supporting documentation, Corrective Action Plans and reports.
https://vendor.myfloridamarketplace.com/ http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0100-0199/0119/Sections/0119.07.html
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 10 of 65
CERTIFICATE OF CONTRACT COMPLETION
The Contract Manager shall conduct a final inspection of the work to determine if completion has occurred.
Upon satisfactory completion of the work, the Contractor shall send the Contract Manager a notarized
Certificate of Contract Completion (Attachment D) and the contract shall be deemed completed upon the issuance date of such Certificate.
LIQUIDATED DAMAGES
If the Contractor fails to complete the work or the conditions of the Contract and/or Amendments by the completion date, the Commission shall have the right to deduct liquidated damages from any amount due and payable to the Contractor. Liquidated damages shall be assessed in the amount of $200 per calendar day of delay. Exceptions to this provision may be made if a delay is attributable to circumstances that are clearly beyond the control of the Contractor. The burden of proof of unavoidable delay shall rest with the
Contractor and shall be supplied in a written form and submitted to the Contract Manager.
WARRANTIES/DAMAGED ITEMS/DELIVERY
The Contractor shall assume full responsibility for providing or ensuring warranty coverage and/or warranty service on any and all items including goods, materials, or equipment provided to the Commission.
If Contractor is not the Manufacturer, all Manufacturer warranties must be passed through to the
Commission.
Delivery shall be made no later than the specified Delivery Date. The Contractor shall pay all costs associated with delivery and shall assume full responsibility for all item(s) damaged prior to the F.O.B.
destination delivery and agree to hold harmless the Commission of all responsibility for prosecuting damage claims.
The Contractor shall assume full responsibility for replacement of all defective or damaged goods within thirty (30) days of notice by the Commission of such defect or damage.
GUARANTEE
If products do not comply with the specifications contained herein, the Contractor shall replace the product(s), or the purchase price shall be refunded. The refund or the delivery of the replacement product(s) shall be made within thirty (30) days following the Contract Manager’s notification to the Contractor that the original product(s) was non-compliant. Costs of returning the original product(s) will be the sole responsibility of the Contractor.
MATERIAL AND EQUIPMENT ON COMMISSION PROPERTY
If the Commission allows the Contractor to have project materials or equipment delivered to and/or stored upon the Commission-managed or owned property before, during, or after the term of the project, the
Contractor will be fully and solely responsible for all expenses and liability incurred as a result of the delivery or storage. Should the Commission, in its sole discretion, determine that any project materials or equipment stored on its property must be moved in response to an emergency, the Contractor shall hold harmless, indemnify, defend, and may be responsible for costs of any reasonably necessary actions taken by the Commission.
AUTHORIZED COMPENSATION
It is understood and agreed that all compensation under this ITB is specifically limited to the Contractor’s bid price accepted by the Commission, and to the specific procedure for payment established in this ITB and the Contract executed pursuant to it. The Commission is not liable for any costs, fees, expenses or any
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 11 of 65 other compensation whatsoever incurred or charged by the Contractor, other than the bid price paid for the work specifically described in the Scope of Work, which work is actually accomplished and invoiced by the
Contractor subsequent to the Commission’s notice to proceed (or other notice to begin work). Thus, the
Commission is not liable for any costs incurred or charged by the Contractor in anticipation of responding to, or performing work described in, this ITB including, but not limited to, equipment or personnel procured by the Contractor in anticipation of such work. The Commission is not responsible to the Contractor for any loss or damages resulting from circumstances unforeseen at the time of publication of this ITB including, but not limited to, those resulting from a “force majeure”.
ADDITIONAL LEGAL REQUIREMENT
All corporations seeking to do business with the State shall, at the time of submitting a bid, be on file with the Department of State in accordance with provisions of Chapter 607, F.S.; similarly, partnerships seeking to do business with the State shall, at the time of submitting such bid, have complied with the applicable provisions of Chapter 620, F.S. For further information on required filing and forms, please go to the following sites: http://sunbiz.org or http://dos.myflorida.com.
USE OF CONTRACT BY OTHER STATE AGENCIES AND ELIGIBLE USERS
As provided in Chapter 60A-1.045, Florida Administrative Code (F.A.C.), and Section 287.042(16), F.S., other State of Florida agencies may purchase from the resulting contract of this ITB, provided that the
Department of Management Services has determined the contract’s use is cost effective and in the best interest of the State, and with the Contractor’s consent.
Other State of Florida governmental entities and eligible users may also request of the Contractor to be able to use this contract. If the Contractor agrees to other entities to utilize this ITB contract, such agencies shall coordinate their use of this contract with the Florida Fish and Wildlife Conservation Commission in order to reduce scheduling conflicts.
CONDITIONS AND SPECIFICATIONS
The bidder is required to examine carefully the conditions and specifications of this bid and to be thoroughly informed regarding any and all requirements of the conditions and specifications.
http://www.sunbiz.org/ http://dos.myflorida.com/
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 12 of 65
SCOPE OF WORK
FWC 25/26-12
CHASSAHOWITZKA WMA ROAD MAINTENANCE
PURPOSE
The intent of this Invitation to Bid is to obtain bids for maintaining roads within Chassahowitzka Wildlife
Management Area (Figure 1). The awarded Bidder (Contractor) shall provide the road material, equipment, and labor. The Contractor shall only grade the roads during Period A and during Period B shall add road material grade, and compact, within each state fiscal year (see Schedule and Payment section below) in accordance with the procedures outlined in this Invitation to Bid. Each occasion of maintenance activity is hereafter referred to as a “maintenance event”.
1.0 GENERAL CONTRACTOR RESPONSIBILITIES
1.1 The Contractor shall provide all labor, services, equipment, materials, tools, mobilization/demobilization costs and insurance necessary to complete the work as outlined herein.
The project consists of approximately 27.44 miles of road. If available budget limits project, priority will go to the primary roads first (Figure 1). No labor or equipment shall be furnished by the FWC.
1.2 All maintenance activities shall be limited to the Chassahowitzka WMA on the roads designated in
Figure 1.
1.3 All maintenance activities shall be scheduled with the FWC’s Project Manager to ensure public access is being maintained. Roads to be maintained are open to the public 7 days a week and maintenance activities should not preclude public use of these roads. Should major maintenance activity be required that would preclude public use of the site, the Contractor shall notify the FWC Project
Manager. In addition, the FWC Project Manager shall share with the Contractor information about hunting, logging, work projects, and other activities that may be taking place on the area during maintenance events.
1.4 The Contractor shall use every precaution necessary to prevent pollution of lakes and streams by fuel, oils, chemicals or other harmful materials. All waterways will be kept free of Contractor-generated debris.
1.5 The Contractor shall remove all extraneous materials, equipment and litter associated with the maintenance activities area before partial or final payment is made.
1.6 Equipment shall be thoroughly cleaned of all vegetative debris before entering or reentering the area to reduce the spread of invasive exotic vegetation. The FWC reserves the right to inspect equipment prior to its use on the area.
1.7 Stop Work Clause – The FWC’s Contract Manager or their designated representative has the right to stop work if the work is not being completed as specified; if the Contractor damages existing state or country property (i.e., roads, culverts, low water crossings, fences, gates, signs, trees or other natural resources); if the Contractor generates numerous public complaints; or if the Contractor does not maintain adequate communication with FWC’ Contract Manager or designated representative. Work shall not resume until the deficiency or deficiencies are corrected. Ongoing problems with the
Contractor’s performance could result in cancellation of the contract.
2.0 PROJECT SPECIFICATIONS FOR ROAD MAINTENANCE
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 13 of 65
2.1 Roads
2.1.1 The entire roadway (15 to 20 ft.) will be graded to smooth the surface and crowned with a
2%-4% slope with all existing depressions filled and grass and debris removed. Vegetation within the roadway shall be chemically treated with the appropriate herbicide to prevent regrowth. The vendor will supply the appropriate herbicide and applications shall be consistent with herbicide labels. Crown should be offset from center on curves in the grade. The
Contractor will obtain instructions from the FWC Project Manager on where to deposit excess material, if any.
2.1.2 Prior to grading roadways, areas that are rutted or have potholes, mud holes, or washouts, will be smoothed and leveled.
2.1.3 The Contractor will use DOT certified lime rock road base to patch rutted roadways, potholes, washouts, and mud holes.
2.1.4 If required, washouts, potholes or mud holes will be filled by the Contractor with DOT certified lime rock road base and spread, contoured, and blended into the finished grade of the roadbed.
2.1.5 Washouts, potholes or mud holes that are holding water will be drained by cutting weeps in the roadbed to drain water off the roadway prior to repairs.
2.1.6 All crushed lime rock will be used to cap/maintain WMA roads, not as a base to be covered with pavement. Flat tires due to boulders or shards of flint rock within the road material have been a problem in the past. To maintain a safe experience for visitors and WMA equipment integrity, the road material specifications described herein are extremely important. Crushed lime rock must be Florida Department of Transportation (DOT) certified. Contractor must provide a copy of DOT certification upon, or prior to, the first delivery. The material shall not contain flint rock, boulders, lumps of clay, organic matter, cherty or other extremely hard materials of such nature or in sufficient quantity to prevent the Commission from obtaining a smooth road surface free from pits, pockets, and sharp objects. Material that does not meet specifications will not be accepted and may be cause for purchase order cancellation.
2.1.7 Contractor will not be responsible for adding any road material to low water crossings. The
Contractor shall only place limerock road base up to the edges of the low water crossings. The
FWC Project Manager will work with the Contractor to delineate the low water crossings prior the start of work.
2.1.8 The final roadways will be finished graded and compacted using a vibratory roller. All work should result in a smooth road surface free of ruts, grass, and potholes; and suitable for passage by two-wheel drive vehicles.
3.0 GENERAL REQUIREMENTS
3.1 The Contractor shall be responsible for actions and damages caused by their personnel while on state-owned land. The Contractor shall also be responsible for damage or destruction to state or county property, or equipment caused by the Contractor’s employees or subcontractors and not within the scope of this project. This shall include damage to existing roads, culverts, fences, gates, signs, trees, and other natural resources.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 14 of 65
3.2 Any portion of a public roadway that sustains excessive construction-related damage, in the opinion of applicable agencies or county, shall be repaired at the Contractor’s expense in a manner specified by that particular agency.
3.3 The safeguarding of all Contractor equipment left at the job sites (overnight or weekends) shall be the sole responsibility of the Contractor, including theft of supplies or equipment and damages. The FWC does not take any responsibility for damage to the Contractor’s equipment left at job sites.
3.4 The Contractor shall not provide access to parties other than those performing activities associated with this project.
4.0 QUALITY CONTROL
4.1 Maintenance activities within this Scope of Work shall be completed as determined by the FWC
Project Manager.
4.2 The Contractor shall advise the FWC Project Manager when each mile of roadway is ready for inspection. The FWC Project Manager will inspect the road to ensure road specifications have been met.
5.0 MINIMUM EQUIPMENT REQUIRED
5.1 At a minimum, a Caterpillar 120 Motor Grader (or other brand with equivalent power) with a 10-f oo t blade is required for grading. A Caterpillar CCS7 Smooth Drum Vibratory Combination
Compactor (or other brand with equivalent power, single front drum, and rubber rear tires) and water truck equipped with a 16-foot boom sprayer or larger, is required for each maintenance event. A tractor/loader with bucket and dump truck is required to move material needed during each maintenance event.
5.2 Equipment used in the performance of the work shall be of the proper type and size and in such mechanical condition to accomplish the required work outlined herein. All equipment used shall be in good repair, and be in compliance with all federal, state, and local regulations. All equipment shall meet all safety standards as established for that piece of equipment. All equipment shall be operated and maintained in accordance with the manufacturer’s recommendations. All equipment shall be equipped with all appropriate safety guards, as specified by the manufacturer. Bidders must have the capability to provide replacement equipment within 48 hours in the event of equipment breakdowns.
The FWC reserves the right to request replacement of equipment or personnel if deemed to be unsafe or operating in an unsafe manner.
6.0 SCHEDULE AND PAYMENT
6.1 Work is expected to occur during two, 2-month periods – Period A: September and October and Period
B: April and May. The FWC may, at its sole discretion, modify starting and completion dates within the term of the purchase order.
6.2 Road maintenance cannot occur during the quota periods for Archery, Muzzleloader, General Gun, Wild Hog-Dog, and Spring Turkey. The 25/26 FY hunt quota period dates are September 13-21, October 18-20, November 1-9, January 9-11, 16-18, March 14-15, 27-29, and April 10-12, 24-26.
6.3 Generally, one purchase order will be issued for e ac h maintenance event (Period A and Period B) each year. A maintenance event is defined as the completion maintenance activity as described under
2.0: Payment may be made upon satisfactory completion of each maintenance event and inspection/approval by the FWC Project Manager.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 15 of 65
6.4 Maintenance activities within this Scope of Work shall be completed as determined by the FWC
Project Manager.
7.0 FINANCIAL CONSEQUENCES
If maintenance services are not completed per the terms of the purchase order and this ITB or are not completed to the satisfaction of the FWC, payment will be withheld until the services are satisfactorily completed as specified in this Scope of Work.
8.0 BID AWARD
The Bidder shall provide prices per 0.5 mile of road for each period of work (A & B) in accordance with the specifications contained herein. The contract will be awarded to the responsive, responsible Bidder with the lowest total bid price. The FWC reserves the right to increase or decrease the size of the project based on budgetary constraints and bids received. The FWC reserves the right to decide which sections of road will be chosen for maintenance.
REMAINDER OF PAGE INTENTIONALLY LEFT BLANK
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 16 of 65
Figure 1: Location of roads and access gates for road maintenance project Chassahowitzka WMA, H e r n a n d o County, FY 25-26.
28.6795, -82.5661 – NORTH ENTRANCE (RETRIEVER RD.)
28.6580, -82.5526 – HERNANDO SPORTSMAN CLUB ENTRANCE
28.5919, -82.5567 – ATLANTA SUV ROAD ENTRANCE
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 17 of 65
PRICE SHEET EXAMPLE #2
FWC 25/26-12
CONTRACTOR SHALL NOT ALTER THE PRICE SHEET IN ANY WAY.
Price quoted shall not contain any Federal or State sales or use taxes. The bidder recognizes that the State of Florida, by virtue of its sovereignty, is not required to pay taxes on services, goods and/or equipment purchased incident to such service. Quoted price shall include all necessary items to complete the project.
ALL ITEMS SHALL BE BID OR THE BID WILL BE REJECTED. THE BID WILL BE AWARDED TO
THE RESPONSIVE, RESPONSIBLE BIDDER THAT SUBMITS THE LOWEST TOTAL PRICE. NO
AMOUNT OF WORK IS GUARANTEED, AND THE COMMISSION RESERVES THE RIGHT TO
INCREASE OR DECREASE THE MILEAGE AS NEEDED.
Period’s Price Unit Price
A
Provide all Equipment and Labor for Road
Grading Price Per 0.5 Mile Supplied and Delivered $__________ /Per 0.5 Miles
B
Provide all Equipment, Labor, and Road
Material for Grading and Compacting Price Per 0.5 Mile Supplied and Delivered $_____________/Per 0.5 Miles
TOTAL BID PRICE (Add Period A Price + Period B Price) $________________________
BY SIGNING BELOW, I ATTEST THAT I HAVE READ THE ENTIRE BID AND AGREE TO FURNISH
THE SERVICE AT THE PRICE QUOTED ABOVE. I HEREBY AFFIRM I HAVE NOT BEEN IN ANY
AGREEMENT OR COLLUSION AMONG BIDDERS IN RESTRAINT OF FREEDOM OF COMPETITION.
Contractor: _______________________________
Address: _________________________________
Signed: ___________________________________
Print Name: ______________________________
Title: ____________________________________
City/State/Zip: ____________________________
Phone: ___________________________________
Fax: _____________________________________
REFERENCES
A minimum of three (3) separate and verifiable references, from persons or firms for whom the bidder has performed similar jobs as per the bid specifications shall be supplied with the bid. The same client may not be listed for more than one (1) reference, and no more than one (1) of the submitted references shall be related to a past project where staff necessary for the current project were unaffiliated with the bidder and/or employed by a different company. If providing an unaffiliated reference, enter the information in
Reference 4 - Collective Experience. The firms and/or contact persons should be available between the hours of 8:00 AM and 5:00 PM, Eastern Time, Monday through Friday. FWC staff will attempt to contact each selected reference by phone up to three (3) times. If any reference is not available as stated above, this may be cause for rejection of the Bidder’s bid. Provide a description (scope of work) of each job.
REFERENCE #1
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 19 of 65
REFERENCE #2
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 20 of 65
REFERENCE #3
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 21 of 65
REFERENCE #4 – COLLECTIVE EXPERIENCE
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Collective Experience Employee
First Name: __________________________________ Last Name: ___________________________________
Previous Employer’s Name: _______________________________________________________________________
Previous Position Title: ___________________________________________________________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
SAMPLE REFERENCE QUESTIONNAIRE
REFERENCE:
Reference Organization Name: ___________________________________________
Reference Contact: ______________________________________________________
Reference Phone Number: _______________________________________________
For Agency use ONLY, to be completed following the bid opening:
The following questions will be asked of the client reference, as chosen at the discretion of the Agency.
1. Did the vendor stay within the approved timeline/budget?
Excellent Above Satisfactory Satisfactory Fair Poor
Comments:
2. Did the vendor maintain clear communication?
3. How satisfied was your organization with the vendor's skill, knowledge, cooperativeness, and professional manner?
4. How satisfied was your organization with the timeliness of the vendor’s delivery of products or performance of services under the contract?
FWC Staff Signature: __________________________________
Date: ___________________
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-12, Page 23 of 65
ATTACHMENT A
FWC 25/26-12
FLORIDA FISH & WILDLIFE CONSERVATION COMMISSION
PURCHASE ORDER TERMS & CONDITIONS
Last Updated: April 29, 2025
Section 1. PURCHASE ORDER
A. Composition and Priority The Contractor agrees to provide commodities or contractual services to the Commission within the manner and at the location specified in the Purchase Order, and any attachments to the Purchase
Order. These Purchase Order Terms and Conditions, whether generic or specific, shall take precedence over any inconsistent or conflicting provision in the State of Florida, General Contract Conditions, PUR
1000. Additionally, the terms of the Purchase Order supersede the terms of any and all prior agreements with respect to this purchase.
B. Initial Term Unless otherwise specified, the Purchase Order begins on the date of issuance. Contractual services or commodities to be provided by the Contractor shall be completed by the date specified on the
Purchase Order end date.
Section 2. PERFORMANCE
A. Performance Standards The Contractor agrees to perform all tasks and provide deliverables as set forth in the Statement of
Work and attachments to the Purchase Order. The Commission shall be entitled at all times, upon request, to be advised as to the status of work being done by the Contractor and of the details thereof.
Coordination shall be maintained by the Contractor with representatives of the Commission, or of other agencies involved in the project on behalf of the Commission.
B. Performance Deficiency If the Commission determines that the performance of the Contractor is unsatisfactory, the Commission may notify the Contractor of the deficiency to be corrected, which correction shall be made within a timeframe specified by the Commission.