FWC 26.27.27 Question & Answers.pdf
PDF 351 KB Posted
- Solicitation number
- ITB-17019
- Issued by
- Leon County, Florida
About this file
This is an Addendum No. 2 to a competitive sealed bid solicitation issued by the Florida Fish and Wildlife Conservation Commission (FWC) for Dinner Island Ranch Wildlife Management Area Canal Cleaning and Maintenance services. The solicitation requests bids for three service categories: removal of aquatic vegetation and sediment from canals, vegetation clearing of canal rights-of-way to establish maintenance access corridors, and chemical spraying of aquatic vegetation using EPA-registered herbicides across over 50 miles of drainage canals. Contractors must submit pricing on a per-tenth-mile unit rate basis for each service category. The original bid due date was October 14, 2026, at 3:00 PM ET; however, Addendum No. 2, issued October 9, 2026, extends the deadline to October 16, 2026, at 3:00 PM ET. The mandatory pre-bid conference and site visit was scheduled for September 29, 2026, at 11:00 AM ET. The anticipated award date is October 19, 2026. The contract term is three years from Purchase Order issuance, with possible extension requests for circumstances beyond the contractor's control. The award will be made to the lowest responsive, responsible bidder on combined total price.
Key clarifications in Addendum No. 2 address critical bid preparation questions. No engineer's estimate exists for this project. Subcontracting is not permitted for any portion of the work; all services must be completed by the awarded contractor with 100 percent self-performance required. The Subcontractor Minority Status Report (Attachment C) must still be signed and returned as a completed form, even though subcontracting is prohibited. The FWC's budget for the current fiscal year is $150,000, with future budget requests to be adjusted based on bid prices and actual needs. The actual quantities treated annually will depend on bid prices, annual budget availability, area conditions, and current canal conditions. Contractors must obtain all required permits and maintain current Florida Pesticide Applicator licenses for aquatic pest control (FDACS Category 5A) when applying herbicides. Liquidated damages of $150 per calendar day apply for failure to meet completion dates, except for delays outside the contractor's control. Contractors must maintain commercial general liability insurance and workers' compensation insurance with minimum limits of $100,000 per accident and $500,000 policy aggregate, and must be registered in MyFloridaMarketPlace and with SunBiz prior to bid opening.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWc 26.27.27 COE Addendum.pdf | ||
| FWC 26.27.27 ITB Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Fish and Wildlife Conservation Commission
Commissioners
Rodney Barreto
Chairman
Coral Gables
Steven Hudson
Vice Chairman
Fort Lauderdale
Preston Farrior
Tampa
Joshua Kellam
Palm Beach Gardens
Gary Lester
Oxford
Albert Maury
Coral Gables
Sonya Rood
St. Augustine
Office of the
Executive Director
Roger A. Young
Executive Director
Charles “Rett” Boyd
Assistant Executive Director
George Warthen
Chief Conservation Officer
Jessica Crawford
Chief of Staff
850-487-3796
850-921-5786 FAX
Managing fish and wildlife resources for their long-term well-being and the benefit of people.
620 South Meridian Street
Tallahassee, Florida
32399-1600
Voice: 850-488-4676
Hearing/speech-impaired:
800-955-8771 (T)
800-955-8770 (V)
MyFWC.com
DATE: OCTOBER 9, 2026
ADDENDUM NO.: 2
BID NO.: FWC 26/27-27
BID TITLE: Dinner Island Ranch WMA Canal Clearing and Maintenance
UPDATE: QUESTIONS
The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s (FWC) Solicitation
No. FWC 26/27-27, “Dinner Island Ranch WMA Canal Clearing and Maintenance”.
All responses to the subject solicitation must be received no later than 3:00 PM (ET) on
Friday, October 16, 2026.
A response received after the exact time specified will not be considered. Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes.
Written notices, formal requests and proceedings must conform with the requirements set forth in Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875 Orange
Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section
120.57(3), F.S. and Chapter 28-110, F.A.C.
Sincerely, Randy Golightly
FWC Procurement Manager
FWC SOLICITATION ADDENDUM 2
BEGIN ADDENDUM
QUESTION #1
What is the engineers’ estimate for the Dinner Island Ranch Project? Thank you
ANSWER #1
An engineer’s estimate does not exist for this project.
QUESTION #2
The contract documents state:
Subcontracting IS NOT permitted pursuant to the Terms and Conditions of the Purchase Order. The
Subcontractor Minority Status Report (Attachment C) shall be submitted with each invoice for payment.
Could you please clarify what is meant by this clause? We are interested in submitting a proposal for this job, but we would have to subcontract the chemical spraying to a licensed applicator. Are any portions of the scope allowed to be subcontracted, or is there a 100% self-performance requirement?
ANSWER #2
Subcontracting is not permitted for any portion of this ITB. All services must be completed by the awarded
Contractor.
QUESTION #3
Please confirm the Sample Reference Questionnaire is a sample document that does not need to be included in our bid submittal.
ANSWER #3
Yes, it is a sample form to show you what questions will be asked to your references.
QUESTION #4
Please confirm if Attachment C is Not Applicable as subcontracting is not permitted per P.5 of the ITB
ANSWER #4
Yes, if Subcontracting is not allowed the form must sill be signed and returned.
QUESTION #5
Please confirm Attachment D is a post award document that does not need to be included in our bid submittal.
FWC SOLICITATION ADDENDUM 3
ANSWER #5
Attachment D is not a requirement for responsiveness. You may fill out and send back with your submission.
QUESTION #6
Please confirm Composite Exhibit I is a post award document that does not need to be included in our bid submittal
ANSWER #6
Yes, it is a post award document. You must sign the form but you do not have to fill it out for responsiveness.
QUESTION #7
Are any copies required in addition to our original bid submittal? If so, how many?
ANSWER #7
No, You must mail your response to the address provided in the COE.
QUESTION #8
Do any of the canals requiring cleaning run through multiple prescribed burn units? If right-of-way clearing is required along those sections, would we be permitted to pile the cleared vegetation or spread it within the adjacent burn units for future burning?
ANSWER #8
Yes. Materials must not be left in consolidated piles, or where it can float or wash back into the canal during rain events. The FWC Project Manager will assist the Contractor in determining where to spread mulch and/or removed materials.
QUESTION #9
Can FWC provide the GIS data associated with the canals anticipated for work under this contract, preferably in KML/KMZ format or another GIS-compatible format? If GIS linework is not available, can
FWC provide a georeferenced PDF or Avenza-compatible map identifying the canals anticipated for treatment?
ANSWER #9
The intent of this project is for ongoing maintenance for all canals within the WMA. Please refer to Figure
1 for the location of the canals. GIS/georeferenced maps will be provided to the awarded Contractor prior to beginning work.
FWC SOLICITATION ADDENDUM 4
QUESTION #10
To estimate cost is it accurate to say 100% of canals will be cleaned, 100% of ROW cleared, and herbicide used as maintenance after the clearing in canals has occurred or herbicide treat 100% of canals as well?
ANSWER #10
No, the actual needs for each portion of the canals will vary based on their current condition before work begins. The actual amounts will be dependent on the awarded bid prices, annual budget appropriation, current condition and needs within each portion of the canals, etc.
QUESTION #11
Please provide FWC’s estimated quantity, in tenths of a mile, anticipated for each Price Sheet service during the contract term: (1) Canal Cleaning, (2) Canal ROW Vegetation Clearing, and (3) Chemical Spraying.”
ANSWER #11
This is an ongoing maintenance project of the canals within Dinner Island Ranch WMA. The amount treated each year will be dependent on bid price, annual budget availability, area conditions, etc. The budget for this fiscal year is $150,000. Future budget requests will be adjusted based on bid prices and needs.
QUESTION #12
When FWC orders Canal ROW Vegetation Clearing for a canal segment that already has an existing 12-foot vehicle corridor and requires only minimal vegetation clearing, will the full bid unit price per tenth mile apply to that segment?
ANSWER #12
Yes.
QUESTION #13
If advantageous to FWC, would maceration within the canal be permitted, provided that any remaining viable/workable material is removed upon completion?
ANSWER #13
As long as all targeted vegetative material is removed from the canal and no negative impacts occur to the canal system, the Contractor may use maceration.
END ADDENDUM
| Question #1 |
| Answer #1 |
| Question #2 |
| Answer #2 |
| Question #3 |
| Answer #3 |
| Question #4 |
| Answer #4 |
| Question #5 |
| Answer #5 |
| Question #6 |
| Answer #6 |
| Question #7 |
| Answer #7 |
| Question #8 |
| Answer #8 |
| Question #9 |
| Answer #9 |
| Question #10 |
| Answer #10 |
| Question #11 |
| Answer #11 |
| Question #12 |
| Answer #12 |
| Question #13 |
| Answer #13 |