Summary of FWC 25/26-73 Invitation to Bid
This is an Invitation to Bid (ITB) issued by the Florida Fish and Wildlife Conservation Commission (FWC) for the supply and delivery of road materials to the Babcock/Webb Wildlife Management Area in Charlotte County, Florida. The project requires bidders to supply approximately 9,600 tons of bank run shell material meeting FDOT 913-3 specifications and 1,214 tons of crushed concrete (minus, free of all metal) to designated dumping areas accessible via Jones Loop Road and Bermont Road. Bidders must be registered in MyFloridaMarketPlace and SunBiz prior to bid opening. Written questions must be submitted by December 23, 2025, at 5:00 PM ET, with responses posted by December 31, 2025. Sealed bids are due January 7, 2026, at 3:00 PM ET, with a public opening scheduled for the same date and time at the FWC Purchasing office in Tallahassee or via teleconference. The anticipated award date is January 12, 2026. Work must commence only after issuance of a Purchase Order and Notice to Proceed and must be completed by June 1, 2026. A mandatory site visit with the awarded vendor and any subcontractors is required prior to Notice to Proceed issuance. The contract term is one year from Purchase Order issuance.
Bidders shall provide pricing per ton for each material type, with the total bid price determining the award to the lowest responsive and responsible bidder. The estimated budget is $200,000, and all quoted prices must include labor, materials, equipment, supplies, vehicles, delivery, and miscellaneous items necessary to complete the project. The contract does not specify set-asides for disadvantaged enterprises, though certified minority-owned, women-owned, and service-disabled veteran business enterprises are encouraged to participate and subcontracting is permitted. A Performance Bond equal to 100 percent of the total contract price must be submitted within ten days of Purchase Order issuance. The Contractor shall maintain workers' compensation insurance with minimum employers' liability limits of $100,000 per accident, general liability insurance, and shall be responsible for all safety, site cleanup, environmental compliance, and damage repair. A ten percent financial penalty will be applied to payment if deliverables are not completed within specified timeframes. No federal funds are explicitly mentioned as supporting this procurement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FWC 25.26-73 ITB.Final.pdf | ||
| Questions & Answers Addendum.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FLORIDA FISH AND WILDLIFE CONSERVATION COMMISSION
1875 ORANGE AVE E
TALLAHASSEE, FL 32311-6160
(850) 488-6551
BABCOCK/WEBB WMA ROAD MATERIAL
FWC 25/26-73
INVITATION TO BID
ITB BIDDER ACKNOWLEDGEMENT FORM
BABCOCK/WEBB WMA ROAD MATERIAL
Purpose: The intent of this bid is to obtain competitive pricing for the supply/delivery of bank run shell and crushed concrete materials to the Babcock/Webb WMA., per the specifications contained herein. Only responsive and responsible Contractors will be considered for award of this Invitation to Bid (ITB).
Responsive: To be responsive, a bid must constitute a definite, firm, unqualified and unconditional offer to meet all of the material terms of this ITB. Material terms are those that could affect the price, quantity, quality, or delivery. Also included as material terms are those which are clearly identified in this ITB and which, for reasons of policy, must be complied with at risk of bid rejection for non-responsiveness.
Non-Responsive: Any submission that does not comply with this ITB in any way, does not contain all the properly signed forms, supplements or deviates from the Bid requirements or has an incomplete Price Sheet may be considered nonresponsive at the discretion of the Procurement Manager.
Responsible Vendors: The Commission shall only consider responsible vendors. Responsible vendors are those that have, in the sole judgment of the Commission, the financial ability, experience, resources, skills, capability, reliability and business integrity necessary to perform the requirements of the contract. The Commission may also consider references and quality to determine the responsibility of the bid. The Commission reserves the right to use any information, whether supplied through the Bidder’s submission or otherwise obtained, in determining responsibility.
Sealed Bid: In response to an Invitation to Bid (ITB), a sealed bid is the final submission of a bid from a vendor prior to the bid deadline, after which no further submissions will be considered.
Rejection of Bids: The Commission reserves the right to reject any and all bids and to waive any minor irregularity in the submissions received in response to this ITB. The Commission reserves the right to consider all information, whether submitted or otherwise, to determine responsiveness and responsibility and to reject bids accordingly.
Name of Business: ____________________________________________________________________________________________________
Contact Person Name: _________________________________________________________________________________________________
Business Address: ____________________________________________________________________________________________________
City: ____________________________ State: _____________________________ Zip code: ______________________________________
Phone: ___________________________ Fax: _______________________________ Email: ______________________________________
Federal Employer Identification Number: ____________________
The undersigned attest to the following:
“We understand all of the terms, conditions and the specifications contained herein and agree to abide by all of the terms, conditions and the specifications in their entirety.
Authorized Signature (Manual): ________________________________________________________________________________________
Authorized Signature Name (Typed) and Title: __________________________________________________________________________
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 3 of 64
CALENDAR OF EVENTS
FWC 25/26-73
SCHEDULE DUE DATE METHOD
Bid Advertised December 16, 2025 Posted on the Vendor Information Portal
(VIP)
Deadline for Questions
Must be received
PRIOR to:
December 23, 2025
@ 5:00 PM ET
See Solicitation Questions Clause
Anticipated date for Responses to Written Questions December 31, 2025 Posted on the Vendor Information Portal
SEALED BIDS DUE
(REMEMBER: The bid number should be clearly marked on envelope)
Must be received
PRIOR to:
January 7, 2026
@ 3:00 PM ET
Mailing Address:
Florida Fish & Wildlife Conservation
Commission
Attn: Purchasing
1875 Orange Ave E
Tallahassee, Florida 32311-6160
Submissions are due BEFORE the date and time of the public opening.
Public Bid Opening January 7, 2026
@ 3:00 PM ET
Public Opening Options for Attendance:
-In Person-
1875 Orange Ave E
Tallahassee, FL 32311-6160
-Teleconference-
Conference call phone number:
1.888.585.9008
Conference room number: 218-721-199
Anticipated Date of Intended
Award January 12, 2026 Posted on the Vendor Information Portal https://vendor.myfloridamarketplace.com/
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 4 of 64
GENERAL CONDITIONS
FWC 25/26-73
The Florida Fish and Wildlife Conservation Commission’s (FWC or Commission) mission is to manage fish and wildlife resources for their long-term well-being and the benefit of people. The Commission administers six (6) major programs including habitat and species conservation, freshwater fisheries management, law enforcement, marine fisheries management, hunting and game management and fish and wildlife research.
A Bidder submitting a bid shall be registered in the MyFloridaMarketPlace (MFMP) system and where required, the Sunbiz system prior to the bid opening. Business entities which must be on file with Sunbiz include the following foreign and domestic entities: Corporations for and not for profit, Limited Liability
Companies (LLC), Limited Partnerships (LP) including Limited Liability Limited Partnerships (LLLP), and organizations doing business under a fictitious name (DBA). A Bidder may not be considered for an award, if not registered in the MFMP and Sunbiz system. The Bidder’s registration address and federal employer identification (FEID) number should match the Bidder’s address and FEID number listed on the
Bidder Acknowledgment form (page 1).
Certified Minority-owned, Woman-owned and Service-Disabled Veteran Business Enterprises, as certified by the State of Florida Office of Supplier Development, are encouraged by the Commission to participate in the bidding process.
Bids from Bidders shall include all necessary equipment to complete the job. The bidder is required to supply all specified documentation when submitting a bid for this project.
Please note:
• The terms “Contract,” “Agreement” and “Purchase Order” are used interchangeably in the document.
• The terms “Commodities” and “Goods” are used interchangeably in the document.
TERMS AND CONDITIONS
PUR 1000 and PUR1001 are hereby incorporated by reference. PUR1000 and PUR1001 can be found at the
Department of Management Services website at the following link:
https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purc hasing_pur_forms
The following terms and conditions take precedence over the PUR1001 and PUR1000 forms where applicable. The Commission objects to and shall not consider any additional terms or conditions submitted by a Bidder or Contractor, including any appearing in documents attached as part of a Bidder’s response.
In signing and submitting its bid, a Bidder agrees that any additional terms or conditions, whether submitted intentionally or inadvertently, shall have no force or effect. Failure to comply with terms and conditions, including those specifying information that must be submitted with a bid, shall be grounds for rejecting a bid.
The terms and conditions of Attachment A, Purchase Order Terms and Conditions, are hereby incorporated into this solicitation. Any contract resulting from this solicitation will include the terms and conditions of this solicitation and the terms and conditions contained in Attachment A.
https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purchasing_pur_forms https://www.dms.myflorida.com/business_operations/state_purchasing/state_agency_resources/state_purchasing_pur_forms
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 5 of 64
PROCUREMENT MANAGER
Randy Golightly
Randolph.Golightly@myfwc.com
ESTIMATED BUDGET
The Commission has an estimated budget for this project of $200,000.
TERM
The contract will be effective one year upon issuance of Purchase Order.
If circumstances constituting Force Majeure have occurred, or if anything occurs beyond the Contractor’s control, the Contractor shall submit an extension request in writing. The Project Manager and Contract
Manager will review the extension request and if they determine it is justified, will forward to the Bid
Request Inbox (bidrequest@myfwc.com) for procurement review and approval/disapproval.
SUBCONTRACTS
Subcontracting IS permitted pursuant to the Terms and Conditions of the Purchase Order. The
Subcontractor Minority Status Report (Composite Exhibit I) shall be submitted with each invoice for payment. The List of Subcontractors (Composite Exhibit I) shall be included with bid submission.
DIVERSITY
The Commission is committed to supporting Florida’s diverse business industry and population through ensuring participation by minority, women, and veteran-owned business enterprises in the economic life of the state. The State of Florida Mentor Protégé Program connects minority, women, and veteran-owned business enterprises with private corporations for business development mentoring. We strongly encourage contractors doing business with the State of Florida to consider this initiative. For more information on the
Mentor Protégé Program, please contact the Office of Supplier Development at (850) 487-0915 or osdinfo@dms.myflorida.com.
FWC encourages diversity in its procurement program and requests that all subcontracting opportunities afforded by this solicitation enthusiastically embrace diversity. The award of subcontracts should reflect the vast array of citizens in the State of Florida. Bidders can visit the Office of Supplier Development website for information on certified business enterprises that may be considered for subcontracting opportunities. However, pursuant to Section 287.05701 F.S., the Commission may not request documentation of or consider a vendor’s social, political, or ideological interests when determining if the vendor is a responsible vendor, nor give preference to a vendor based on the vendor’s social, political, or ideological interests.
VERBAL INSTRUCTION PROCEDURE
Bidders may not consider any verbal instructions as binding upon the Commission. No negotiations, discussions, or actions shall be initiated or executed by the Bidder as a result of any discussion with any
Commission employee. Only those communications from the Commission that are in writing, may be considered as a duly authorized expression on behalf of the Commission.
SOLICITATION QUESTIONS
Any questions from Bidders that require an official FWC answer concerning this project shall be submitted in writing to the Procurement Manager. This includes specification inquiries, such as questions or requests mailto:bidrequest@myfwc.com?subject=Extension%20Request https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program mailto:osdinfo@dms.myflorida.com https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program https://www.dms.myflorida.com/agency_administration/office_of_supplier_diversity_osd/mentor_protege_program
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 6 of 64 for additional or altered terms and conditions. Questions to the Procurement Manager shall not constitute formal protest of the specifications or of the solicitation. Questions must be received no later than the date and time specified in the Calendar of Events (Page 3). Questions may be sent via email with the solicitation number in the subject line. It is the responsibility of the bidder to confirm receipt of questions if needed.
If questions are received, an addendum will be issued and shall be posted on the Vendor Information Portal
(https://vendor.myfloridamarketplace.com).
LIMITATION ON BIDDER CONTACT DURING SOLICITATION PERIOD
Bidders to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the Commission posting the notice of intended award, (i.e., the 72-hour posting period excludes Saturdays, Sundays, and state holidays) any employee or officer of the executive or legislative branch concerning any aspect of this solicitation, except in writing to the Procurement Manager or as provided in the solicitation documents. Violation of this provision may be grounds for rejecting a response.
BIDDER SPECIFICATION CHALLENGE
Any protest concerning the specifications of this solicitation shall be made in accordance with PUR1001, paragraph 20, “Protests”. A notice of protest of the solicitation documents shall be made within seventy-two hours after the posting of the solicitation. Failure to file a protest within the time prescribed in Section
120.57(3)(b), F.S., shall constitute a waiver of proceedings under Chapter 120, F.S.
ADDENDUMS
If the Commission finds it necessary to supplement, modify or interpret any portion of the specifications or documents or answer any Bidder questions during the ITB period an addendum shall be posted on the
Vendor Information Portal internet site. Each Bidder is responsible for monitoring the Vendor Information
Portal website (https://vendor.myfloridamarketplace.com) for new or changing information relative to this procurement. The Commission bears no responsibility for any delays, or resulting impacts, associated with a
Bidder’s failure to obtain the information made available through the Vendor Information Portal.
BIDDER ACKNOWLEDGMENT
In order for this bid to be valid, the bid must be completed in its entirety, signed by the Bidder and returned, as part of the bid or the bid will be rejected. By affixing your signature to the ITB Bidder Acknowledgement
Form (page 2), the Bidder hereby states that the Bidder has read all bid specifications and conditions and agrees to all terms, conditions, provisions, specifications, and is currently licensed to do business within the
State of Florida, if required by State or Federal Law, for the services or commodities the Bidder will provide the Commission under these bid specifications.
REFERENCES
Each prospective Bidder shall provide a minimum of three (3) references for similar projects completed.
Current contact names and phone numbers shall be included with the bid package. See the attached references form for more detail.
EQUAL BIDS
In the event that there is no multiple award contemplated in the ITB, and the Commission receives equal bids eligible for award, the Commission will comply with the following, as applicable: sections 287.057(12), 287.082, 287.087,287.092, 295.187(4)(a), and 295.187(4)(b), F.S. In order to clarify the Bidders’ status with regard to the applicable statutory preference requirements, the Commission may request information from
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 7 of 64
Bidders with equal bids. A Bidder will not be permitted to amend or supplement its Bid in response to such request for clarification. If the tie has not been broken by application of the aforementioned statutes, the
Commission will proceed with a random selection to decide the award.
SUPPORTING/SUPPLEMENTAL INFORMATION
The Commission requires that bidders submit all required technical, specification, and other supporting information with their bid, so that a detailed analysis and determination can be made, by the Contract
Manager that the product/service offered meets this ITB’s specifications and that other requirements of this ITB have been met. However, provided a bid meets the requirements for a definite, firm, unqualified, and unconditional offer, the Commission reserves the right to request supplemental information from the bidder after the bids have been opened to ensure that the products/services offered completely meet this
ITB’s requirements. The requirement for such supplemental information will be at the reasonable discretion of the Commission and may include the requirement that a bidder will provide a sample product(s) so that the Commission can make a first-hand examination and determination.
A bidder's failure to provide this supplemental information or the product sample(s), within the time set by the Commission, will cause the Commission to consider the Contractor non-responsive and reject the
Contractor’s bid.
CONFIDENTIALITY/PUBLIC RECORDS LAW
Bidders are cautioned that Florida law generously defines what constitutes a public record and grants broad rights of public access to those records; see, for example, section 119.07, F.S. If a Bidder believes that its response contains information that is confidential or exempt from disclosure under Florida Law, the Bidder shall clearly segregate and mark that information (for example, stamp each page "Confidential" and place it in an envelope marked "Confidential") and briefly describe in writing the grounds and specific legal citations for claiming exemption from the public records law. If after the notice of intended decision or thirty
(30) days after bid opening, whichever is earlier, the Commission receives a public record request related to the solicitation, the Commission will provide copies of public records that are not exempt to the requester.
The Commission will endeavor to provide notice to the Bidder of all public records requests received related to documents provided by the Bidder that were marked pursuant to this paragraph. In no event shall the
Bidder hold the Commission or any of its employees or agents liable for disclosing, or otherwise failing to protect the confidentiality of, information submitted in response to this solicitation.
MAILING INSTRUCTIONS
All bids shall be submitted in a SEALED ENVELOPE addressed to:
Florida Fish and Wildlife Conservation Commission
Attn: Purchasing
1875 Orange Ave E
Tallahassee, Florida 32311-6160.
The envelope shall be plainly marked on the outside with: BID NUMBER, DATE AND TIME OF THE BID
OPENING.
THE COMMISSION IS NOT RESPONSIBLE FOR THE OPENING OF ANY ENVELOPES THAT ARE NOT PROPERLY
MARKED.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 8 of 64
PLEASE NOTE: The Commission’s official business hours of operation are 8:00 AM–5:00 PM ET, exclusive of Saturdays, Sundays and state holidays. Selecting delivery services, such as next day first delivery, may result in attempted delivery prior to opening or closing, and the Commission will not be available to accept those deliveries. THE COMMISSION IS NOT RESPONSIBLE FOR LATE SUBMISSIONS DUE TO COMPLICATIONS
RELATED TO SELECTED DELIVERY SERVICES. DIGITAL SUBMISSIONS SHALL BE DEEMED NON-RESPONSIVE
AND SHALL NOT BE ACCEPTED.
SOLICITATION PUBLIC OPENING
The public opening of this bid will be conducted at the date, time and method specified on the Calendar of
Events (Page 2). BIDS RECEIVED AFTER THE SPECIFIED DATE AND TIME WILL BE REJECTED.
Any person with a qualified disability shall not be denied equal access and effective communication regarding any bid/proposal documents or the attendance at any related meeting or bid/proposal opening. If accommodations are needed because of a disability, please contact the Purchasing Section at (850) 488-6551 at least three (3) workdays prior to the opening.
AWARDED BID/INSPECTION
The Commission will award the bid to the responsive, responsible bidder who submits the lowest bid price.
If deemed necessary, an interview with the bidder by the Contract Manager may be required before the bid is awarded.
The Commission reserves the right to inspect the prospective Contractor’s materials and background record prior to making an award of the Contract. If the Contract Manager determines the lowest bidder does not have sufficient experience, equipment, etc. to meet the specifications of this ITB, the Commission reserves the right to reject the bidder and evaluate the next lowest bidder.
POSTING OF BID TABS
Bid Tabulations with Contractors identified as awarded bidders will be posted electronically as Agency
Decisions on the Department of Management Services Vendor Information Portal as a Public Notice. The
Agency Decision may be viewed at https://vendor.myfloridamarketplace.com, and will remain posted for a period of 72 hours. Failure to file a protest within the time prescribed in Section 120.57(3)(b), F.S., shall constitute a waiver of proceedings under Chapter 120, F.S.
Awarded Bidders are instructed not to proceed until a Purchase Order, Formal Written Contract, Lease, Notice to Proceed, or some other form of written notice is given to the Contractor by the Commission. A company or person who proceeds prior to receiving a Purchase Order, Formal Written Contract, Lease, Notice to Proceed, or some other form of written notice from the Commission does so without a contract and at their own risk.
Sealed bids, proposals, or replies received by an agency pursuant to a competitive solicitation are exempt from s. 119.07(1) and s. 24(a), Art. I of the State Constitution until such time as the agency provides notice of an intended decision or until thirty (30) days after opening the bids, proposals, or final replies, whichever is earlier.
SCOPE CHANGES AFTER CONTRACT EXECUTION
The Commission shall provide written notice to the successful bidder thirty (30) days in advance of any
Commission required changes to the technical specifications and/or scope of service that affect the successful bidder’s ability to provide the service as specified herein. Any changes that are other than purely administrative changes will require a change order.
https://vendor.myfloridamarketplace.com/ http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&Search_String=&URL=0100-0199/0119/Sections/0119.07.html
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 9 of 64
FWC CONTRACT MANAGER
The FWC employee identified as the Contract Manager shall perform the following on behalf of the FWC:
• review, verify, and approve receipt of services/deliverables from the Contractor;
• submit requests for change orders/amendments/renewals, if applicable;
• review, verify, and approve invoices from the Contractor; and, if applicable, complete the
Certificate of Contract Completion form; and
• maintain an official record of all correspondence between the Commission and the Contractor and forward the original correspondence to the Procurement Manager for the official file.
DELIVERABLES
The following services or service tasks are identified as deliverables for the purposes of the subsequent
Contract:
a. Performance of all services set forth in the Scope of Work.
b. Submission of all invoicing, supporting documentation, Corrective Action Plans and reports.
NOTICE TO PROCEED
The awarded Bidder shall not initiate work under this contract until the required Performance Bond and
Insurance documentation have been received by the Commission. The Contractor may begin work once it has received an official written Notice to Proceed (Attachment B) from the Contract Manager.
CERTIFICATE OF CONTRACT COMPLETION
The Contract Manager shall conduct a final inspection of the work to determine if completion has occurred.
Upon satisfactory completion of the work, the Contractor shall send the Contract Manager a notarized
Certificate of Contract Completion (Attachment C) and the contract shall be deemed completed upon the issuance date of such Certificate.
WARRANTIES/DAMAGED ITEMS/DELIVERY
The Contractor shall assume full responsibility for providing or ensuring warranty coverage and/or warranty service on any and all items including goods, materials, or equipment provided to the Commission.
If Contractor is not the Manufacturer, all Manufacturer warranties must be passed through to the
Commission.
Delivery shall be made no later than the specified Delivery Date. The Contractor shall pay all costs associated with delivery and shall assume full responsibility for all item(s) damaged prior to the F.O.B.
destination delivery and agree to hold harmless the Commission of all responsibility for prosecuting damage claims.
The Contractor shall assume full responsibility for replacement of all defective or damaged goods within thirty (30) days of notice by the Commission of such defect or damage.
GUARANTEE
If products do not comply with the specifications contained herein, the Contractor shall replace the product(s), or the purchase price shall be refunded. The refund or the delivery of the replacement product(s) shall be made within thirty (30) days following the Contract Manager’s notification to the Contractor that
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 10 of 64 the original product(s) was non-compliant. Costs of returning the original product(s) will be the sole responsibility of the Contractor.
MATERIAL AND EQUIPMENT ON COMMISSION PROPERTY
If the Commission allows the Contractor to have project materials or equipment delivered to and/or stored upon the Commission-managed or owned property before, during, or after the term of the project, the
Contractor will be fully and solely responsible for all expenses and liability incurred as a result of the delivery or storage. Should the Commission, in its sole discretion, determine that any project materials or equipment stored on its property must be moved in response to an emergency, the Contractor shall hold harmless, indemnify, defend, and may be responsible for costs of any reasonably necessary actions taken by the Commission.
PERFORMANCE BOND
A Performance Bond shall be required from the Contractor by the Commission for this project. Prior to commencing any work, and within ten (10) days after issuance of a Purchase Order, the Contractor shall furnish a Performance Bond in the amount of one hundred percent (100%) of the total contract price to ensure full and complete performance of the contract to the attention of the Contract Manager. The bond must state on its front page: the name, principal business address, and phone number of the Contractor, the Surety, the Commission’s full name, the Purchase Order assigned to the project by the Commission, and a description of the property being improved with a general description of the project. Please note: A
Notice to Proceed will not be issued until after the required bond has been received.
The Bond shall be issued from a reliable Surety Company acceptable to the Commission, licensed to do business in the State of Florida and signed by a Florida Licensed Resident Agent. Such a bond shall be accompanied by a duly authenticated power of attorney evidencing that the person executing the bonds on behalf of the Surety had the authority to do so on the date of the bond. The cost of the Performance Bond shall be borne by the Contractor.
In lieu of a Performance Bond, The Commission may prior approve an alternate form of security in the form of a Cashier’s check, Official bank check or Money order in the amount of the bond. The alternative form of security shall be for the same purpose and be subject to the same conditions as those applicable to the
Performance Bond.
Work shall not begin before the Commission receives the Performance Bond. Failure to provide a
Performance Bond may be grounds to find the Contractor in default, which could include cancellation of the contract, and/or the Contractor’s removal from the State’s approved Contractor list for future solicitations.
AUTHORIZED COMPENSATION
It is understood and agreed that all compensation under this ITB is specifically limited to the Contractor’s bid price accepted by the Commission, and to the specific procedure for payment established in this ITB and the Purchase Order executed pursuant to it. The Commission is not liable for any costs, fees, expenses or any other compensation whatsoever incurred or charged by the Contractor, other than the bid price paid for the work specifically described in the Scope of Work, which work is actually accomplished and invoiced by the Contractor subsequent to the Commission’s notice to proceed (or other notice to begin work). Thus, the Commission is not liable for any costs incurred or charged by the Contractor in anticipation of responding to, or performing work described in, this ITB including, but not limited to, equipment or personnel procured by the Contractor in anticipation of such work. The Commission is not responsible to the Contractor for any loss or damages resulting from circumstances unforeseen at the time of publication of this ITB including, but not limited to, those resulting from a “force majeure”.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 11 of 64
ADDITIONAL LEGAL REQUIREMENT
All corporations seeking to do business with the State shall, at the time of submitting a bid, be on file with the Department of State in accordance with provisions of Chapter 607, F.S.; similarly, partnerships seeking to do business with the State shall, at the time of submitting such bid, have complied with the applicable provisions of Chapter 620, F.S. For further information on required filing and forms, please go to the following sites: http://sunbiz.org or http://dos.myflorida.com.
USE OF CONTRACT BY OTHER STATE AGENCIES AND ELIGIBLE USERS
As provided in Chapter 60A-1.045, Florida Administrative Code (F.A.C.), and Section 287.042(16), F.S., other State of Florida agencies may purchase from the resulting contract of this ITB, provided that the
Department of Management Services has determined the contract’s use is cost effective and in the best interest of the State, and with the Contractor’s consent.
Other State of Florida governmental entities and eligible users may also request of the Contractor to be able to use this contract. If the Contractor agrees to other entities to utilize this ITB contract, such agencies shall coordinate their use of this contract with the Florida Fish and Wildlife Conservation Commission in order to reduce scheduling conflicts.
CONDITIONS AND SPECIFICATIONS
The bidder is required to examine carefully the conditions and specifications of this bid and to be thoroughly informed regarding any and all requirements of the conditions and specifications.
http://www.sunbiz.org/ http://dos.myflorida.com/
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 12 of 64
SCOPE OF WORK
FWC 25/26-73
BABCOCK/WEBB WMA ROAD MATERIAL
PURPOSE
The Florida Fish and Wildlife Conservation Commission (FWC) seeks to obtain competitive pricing for the supply/delivery of bank run shell and crushed concrete materials.
Bidders shall provide a price per ton for bank run shell and crushed concrete materials. The FWC reserves the right to increase or decrease the project based on need and budget.
PROJECT AREA
Babcock/Webb WMA, Charlotte County, Florida, Map 1.
START/COMPLETION DATE
Work will not begin until the issuance of the Purchase Order and a notice to proceed is issued by Contract Manager.
Services for this project must be completed by June 1, 2026. Site Visit with the awarded vendor and Subs, if used, is required before issuance of Notice to Proceed.
FINANCIAL CONSEQUENCES
Should the Contractor fail to produce deliverables within the time frame specified by the Scope of Work, the budget amount allocated for that deliverable will be reduced by ten percent (10%) from Contractor’s payment, per Agency Terms and Conditions.
1. GENERAL DESCRIPTION OF WORK
1.1. The supply and delivery of bank run shell material is for the Babcock/Webb WMA located in
Charlotte County, FL Office address: 29200 Tuckers Grade, Punts Gorda, FL 33955.
1.2. The Contractor shall supply and deliver approximately 9,600 tons of bank run shell to the designated dumping area outlined in Maps 2 and 3.
1.3. The Contractor shall supply and deliver approximately 1,214 tons of crushed concrete to the designated dumping area outlined in Maps 2 and 3.
1.4. The route for dump trucks is as follows: enter off Jones Loop Road, travel approximately 7.3 miles total through area, exit onto Bermont Road.
1.5. The southern end of the road site is 26.9027862, -81.9211622, the northern end of the road site is
26.9465073, -81.9308853
2. TECHNICAL SPECIFICATIONS
2.1. Material Definitions:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 13 of 64
a. Bank Run Shell: FDOT - 913-3 Bank-Run Shell. 913-3.1 Definition: Bank-Run Shell shall be defined as those shell materials meeting the requirements of 913-1 which are presently found as "dry land" deposits. 913-3.2
Gradation Requirements: Materials classified as Bank-Run Shell shall meet the following gradation requirements:
Passing 3 1/2 inch [90 mm] sieve 97% (maximum dimension not to exceed 6 inches [150 mm]) Passing No. 4
[4.75 mm] sieve maximum 80% Passing No. 200 [75 mm] sieve maximum 20% (washed)
b. Crushed Concrete: ½” Minus (must be free of all metal)
3. GENERAL SPECIFICATIONS
3.1. The Contractor shall provide all labor, materials, equipment, supplies, vehicles, and such miscellaneous items as necessary to complete all supply and delivery operations in accordance with the specifications contained herein.
3.2. The FWC Project Manager will consult, at least one month prior to the desired work performed period, with the Contractor to schedule supply and delivery of bank run shell and crushed concrete materials.
3.3. During the delivery phase of the project, FWC personnel will be located at site entrances or exits for the purpose of signing and collecting load tickets. It is the responsibility of the Contractor to ensure that truck drivers get load tickets signed and give copies to FWC ground personnel.
3.4. The Contractor shall be responsible for knowing and complying with federal, state, and local guidelines pertaining to project activities, especially concerning the disturbance of wetlands.
3.5. Disturbance of non-target vegetation must be avoided. If excessive ground disturbance seems necessary to complete the job, the Contractors should confer with the FWC Project Manager or designee before proceeding.
3.6. The equipment operator is required to have the ability to converse with the FWC Project Manager or designee to understand and follow very specific instructions regarding various strategies for this project.
3.7. Once the project is initiated, it must continue to completion in a systematic and contiguous manner, unless unavoidable delays (as determined by FWC) are encountered.
3.8. The Contractor and Contractor’s employees shall abide by all rules and general area regulations of the Babcock/Webb WMA other than the work they are performing.
3.9. In performing work under this ITB, all safety on site shall be the sole responsibility of the
Contractor. The Contractor shall be solely responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with work. The Contractor shall be responsible for protecting and safeguarding the public in connection with the work and project sites.
3.10. It shall be the responsibility of the Contractor to remove all extraneous materials, equipment, debris and trash associated with the project from the area before final payment will be awarded. It is the responsibility of the Contractor to see that the area is cleaned upon completion of the project.
3.11. Secondary impacts on roads, trails, and natural areas shall be minimized as much as practical. Any damage to existing state property (i.e. culverts, fences, trees, or other natural resources) caused by the Contractor, and not within the scope of work of this ITB, will be the responsibility of the
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 14 of 64
Contractor. The Contractor shall be responsible for the conduct of hired personnel at all times within
Babcock/Webb WMA.
3.12. No equipment shall be operated in a manner that significantly damages natural resources or infrastructure on the Babcock/Webb WMA. This includes damage to existing roadways, culvers, gates, utility structures, trees, native vegetation, wildlife and other natural resources and equipment. The Contractor shall be responsible for and repair/replace, to the satisfaction of FWC
Project Manager, all Contractor induced damage.
3.13. For the purposes of prescribed burning, hunts or other FWC operations, the Contractor may be required with short notice to stop work at a particular project area and/or relocate to another project area.
4. RESOURCE PROTECTION
4.1. Every effort shall be made by the Contractor to avoid damage to threatened and endangered plants and wildlife.
4.2. Contractor will avoid any flagged areas. Flagged areas in this project will include federally/state listed plant species, which will be designated in color by the FWC Project Manager or designee.
4.3. Contractor shall use every precaution necessary to prevent environmental pollution by fuel, oil, chemicals, silt, or other harmful materials. All bodies of water, including ditches, will be kept free of Contractor generated debris or soils.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 15 of 64
Map 1
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 16 of 64
PRICE SHEET
FWC 25/26-73
CONTRACTOR SHALL NOT ALTER THE PRICE SHEET IN ANY WAY.
Price quoted shall not contain any Federal or State sales or use taxes. The bidder recognizes that the State of Florida, by virtue of its sovereignty, is not required to pay taxes on services, goods and/or equipment purchased incident to such service. Quoted price shall include all necessary items to complete the project.
ALL ITEMS SHALL BE BID OR THE BID WILL BE REJECTED. THE BID WILL BE AWARDED TO
THE RESPONSIVE, RESPONSIBLE BIDDER THAT SUBMITS THE LOWEST TOTAL PRICE.
Task Price Unit Price
1.
Supply and Deliver Approximately 9600 Tons of Bank Run Shell to the Designated Dumping
Location
Price Per Ton of Bank Run Shell Supplied and Delivered $____________/Per Ton
2.
Supply and Deliver Approximately 1214 Tons of Crushed Concrete to the Designated
Dumping Location
Price Per Ton of Crushed Concrete
Supplied and Delivered $____________/Per Ton
TOTAL BID PRICE (Add Task 1 price + Task 2 Price) $_____________________
BY SIGNING BELOW, I ATTEST THAT I HAVE READ THE ENTIRE BID AND AGREE TO FURNISH
THE SERVICE AT THE PRICE QUOTED ABOVE. I HEREBY AFFIRM I HAVE NOT BEEN IN ANY
AGREEMENT OR COLLUSION AMONG BIDDERS IN RESTRAINT OF FREEDOM OF COMPETITION.
Contractor: _______________________________
Address: _________________________________
Signed: ___________________________________
Print Name: ______________________________
Title: ____________________________________
City/State/Zip: ____________________________
Phone: ___________________________________
Fax: _____________________________________
REFERENCES
A minimum of three (3) separate and verifiable references, from persons or firms for whom the bidder has performed similar jobs as per the bid specifications shall be supplied with the bid. The same client may not be listed for more than one (1) reference, and no more than one (1) of the submitted references shall be related to a past project where staff necessary for the current project were unaffiliated with the bidder and/or employed by a different company. If providing an unaffiliated reference, enter the information in
Reference 4 - Collective Experience. The firms and/or contact persons should be available between the hours of 8:00 AM and 5:00 PM, Eastern Time, Monday through Friday. FWC staff will attempt to contact each selected reference by phone up to three (3) times. If any reference is not available as stated above, this may be cause for rejection of the Bidder’s bid. Provide a description (scope of work) of each job.
REFERENCE #1
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 18 of 64
REFERENCE #2
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 19 of 64
REFERENCE #3
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 20 of 64
REFERENCE #4 – COLLECTIVE EXPERIENCE
Name: __________________________________________________________________________________________
Address: ________________________________________________________________________________________
Contact Person: ____________________________________ Telephone Number: _________________________
Collective Experience Employee
First Name: __________________________________ Last Name: ___________________________________
Previous Employer’s Name: _______________________________________________________________________
Previous Position Title: ___________________________________________________________________________
Project Dates for Work Performed (MM/YYYY): _________________________ to _________________________
Project Location: _________________________________________________________________________________
Brief description of the services performed for the project:
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 21 of 64
SAMPLE REFERENCE QUESTIONNAIRE
FWC 25/26-73
REFERENCE:
Reference Organization Name: ___________________________________________
Reference Contact: ______________________________________________________
Reference Phone Number: _______________________________________________
For Agency use ONLY, to be completed following the bid opening:
The following questions will be asked of the client reference, as chosen at the discretion of the Agency.
1. What type of work did the vendor perform for your organization?
2. When did the vendor perform this work?
3. How well did the vendor stay within the approved timeline and budget?
(5-Excellent, 4-Above Satisfactory, 3-Satisfactory, 2-Fair, 1-Poor)
Comments:
4. How well did the vendor maintain clear communication?
5. How satisfied was your organization with the vendor's skill, knowledge, cooperativeness, and professional manner?
6. How satisfied was your organization with the timeliness of the vendor’s delivery of products or performance of services under the contract?
7. Do you have any additional comments to make regarding the vendor and the work they performed?
FWC Staff Signature: __________________________________
Date: ___________________
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 22 of 64
ATTACHMENT A
FLORIDA FISH & WILDLIFE CONSERVATION COMMISSION
PURCHASE ORDER TERMS & CONDITIONS
Last Updated: April 29, 2025
Section 1. PURCHASE ORDER
A. Composition and Priority The Contractor agrees to provide commodities or contractual services to the Commission within the manner and at the location specified in the Purchase Order, and any attachments to the Purchase
Order. These Purchase Order Terms and Conditions, whether generic or specific, shall take precedence over any inconsistent or conflicting provision in the State of Florida, General Contract Conditions, PUR
1000. Additionally, the terms of the Purchase Order supersede the terms of any and all prior agreements with respect to this purchase.
B. Initial Term Unless otherwise specified, the Purchase Order begins on the date of issuance. Contractual services or commodities to be provided by the Contractor shall be completed by the date specified on the
Purchase Order end date.
Section 2. PERFORMANCE
A. Performance Standards The Contractor agrees to perform all tasks and provide deliverables as set forth in the Statement of
Work and attachments to the Purchase Order. The Commission shall be entitled at all times, upon request, to be advised as to the status of work being done by the Contractor and of the details thereof.
Coordination shall be maintained by the Contractor with representatives of the Commission, or of other agencies involved in the project on behalf of the Commission.
B. Performance Deficiency If the Commission determines that the performance of the Contractor is unsatisfactory, the Commission may notify the Contractor of the deficiency to be corrected, which correction shall be made within a timeframe specified by the Commission. The Contractor shall provide the Commission with a corrective action plan describing how the Contractor will address all issues of Purchase Order non‐performance, unacceptable performance, and failure to meet the minimum performance levels, deliverable deficiencies, or Purchase Order non‐compliance. If the corrective action plan is unacceptable to the
Commission, the Contractor will be assessed a non‐performance retainage equivalent to ten (10) percent of the total invoice amount or as specified in the contractual documents. The retainage will be applied to the invoice for the then‐current billing period. The retainage will be withheld until the Contractor resolves the deficiency. If the deficiency is subsequently resolved, the Contractor may invoice the
Commission for the retained amount during the next billing period. If the Contractor is unable to resolve the deficiency, the funds retained will be forfeited.
Ch. 287 Invitation to Bid – Revised 3.12.2025 FWC 25/26-73, Page 23 of 64
C. Contractor Responsibilities The Contractor agrees that all Contractor employees, subcontractors, or agents performing work under the Purchase Order shall be properly trained technicians who meet or exceed any specified training qualifications. Upon request, the Contractor shall furnish a copy of technical certification or other proof of qualification. All employees, subcontractors, or agents performing work under the Purchase Order must comply with all security and administrative requirements of the Commission. The Commission may conduct, and the Contractor shall cooperate in, a security background check or otherwise assess any employee, subcontractor, or agent furnished by the Contractor. The Commission may refuse access to, or require replacement of, any personnel for cause, including, but not limited to, technical or training qualifications, quality of work, change in security status, or non-compliance with the Commission’s security or other requirements. Such refusal shall not relieve the Contractor of its obligation to perform all work in compliance with the Purchase Order. The Commission may reject and bar from any facility for cause any of the Contractor’s employees, subcontractors, or agents.
D. Assignment The Contractor shall not sell, assign or transfer any of its rights, duties or obligations under the
Purchase Order without the prior written consent of the Commission. In the event of any assignment, the Contractor remains secondarily liable for performance of the Purchase Order, unless the
Commission expressly waives such secondary liability. The Commission may assign the Purchase Order with prior written notice to the Contractor.
E. Damages to State Property Any damages to state property (e.g., structures, roads, culverts, fences, trees, or other natural resources) caused by the Contractor while working on this project shall be the responsibility of the Contractor to remedy, as determined by the Commission. The Contractor shall be responsible for the conduct of all
Contractor personnel at all times while on the job site.
Should any historical or cultural artifacts be uncovered, the Contractor shall immediately halt work and notify the Commission’s Contract Manager. Please note: The State Archaeologist has the power to halt work if they have reason to believe artifacts are being disturbed.
F. Subcontractor Minority Status Report.
Contractor shall provide a Subcontractor Minority Status Report (Composite Exhibit I) to the
Commission’s Contract Manager, summarizing the participation of certified and non-certified woman-
, veteran- and/or minority-owned business enterprise subcontractors/material suppliers for this
Contract. The report shall be completed in its entirety and submitted with each invoice. The
Contractor shall indicate “N/A” if the project does not utilize subcontractors. The Office of Supplier
Development can assist in furnishing names of qualified woman-, veteran- and/or minority-owned business enterprises. Contact the Commission’s Minority Coordinator at (850) 488-6551 with any questions.
G. Independent Contractor The Contractor shall perform as an independent contractor and not as an agent, representative, or employee of the Commission. The Contractor covenants that it presently has no interest and shall not acquire any interest that would conflict in any manner or degree with the performance of services required. Each party hereto covenants that there is no conflict of interest or any other prohibited relationship between the Contractor and the Commission.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .