This Statement of Work (SOW) details architect-engineering services for developing a Unidirectional Flushing Program (UDFP) at Eielson Air Force Base in Alaska. The six-month project, with a July 2025 date, requires the contractor to develop a comprehensive water distribution system flushing plan using advanced mapping and hydraulic modeling techniques. Key tasks include reviewing existing documents, creating a GIS-integrated hydraulics model in WaterGEMS, conducting field investigations, and developing systematic flushing sequences that optimize water quality and system efficiency.
The project involves three primary tasks: (1) Investigation of existing water infrastructure components, (2) Hydraulics Model Configuration and Calibration using current and future water consumption data, and (3) Unidirectional Flushing (UDF) Planning. Deliverables include an Investigation Report, GIS-based Hydraulics Model, Calibration Report, color-coded flushing sequence maps, step-by-step field instructions, and monitoring forms. The contractor must comply with multiple standards including AWWA, EPA guidelines, and DoD Unified Facilities Criteria. Travel requirements include seven days of on-site work for three personnel, with some remote work permitted for data processing and reporting.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
ARCHITECT-ENGINEERING (A-E) SERVICES
TO PROVIDE
Planning Study Documents
FOR
FLUSHING PROGRAM PLAN DEVELOPMENT
AT
EIELSON AIR FORCE BASE (AFB), ALASKA (AK)
Project No: FTQW241400
16 JULY 2025
Flushing Program Plan Development - Statement of Work (16 July 2025) Eielson AFB, Alaska
2 of 7 Controlled Unclassified Information (CUI)
1.0 INTRODUCTION
Water distribution systems require regular flushing to maintain water quality and system efficiency by removing accumulated deposits from pipe walls. Two primary methods used are conventional flushing and unidirectional flushing. Conventional flushing involves opening hydrants to allow water to flow freely, but it requires significant water usage and is less effective at clearing deposits.
Unidirectional flushing, a more targeted approach, forces water through selected pipes at higher velocity by closing specific valves, thus improving cleaning efficiency while using less water. It also helps identify faulty valves and hydrants and enhances overall system reliability.
This Statement of Work (SOW) defines the requirements for the development and implementation of a Unidirectional Flushing Program (UDFP) at Eielson Air Force Base (AFB), AK. The purpose of this effort is to ensure accurate GIS representation, optimize water system performance, and establish a systematic approach for flushing procedures.
2.0 DESCRIPTION OF SERVICES
The Contractor shall review existing documents, assess hydraulic conditions, configure a GIS-based hydraulics model, develop a flushing sequence, and conduct condition assessments. The Contractor shall ensure compatibility with Eielson AFB’s GIS feature layers and standards.
3.0 SCOPE OF WORK
The scope of work encompasses data review/entry, hydraulics modeling, and UDFP development.
The period of performance for this work is six months after Notice to Proceed.
3.1 TASK 1 – Investigation
3.1.1 The Contractor shall review all available documents, including but not limited to as-builts, water quality reports (from BEE sampling), Lead Service Line inventory and key infrastructure components such as:
• Critical valves
• Hydrants
• Storage tanks
• Pump stations
3.1.2 The collected information shall be consolidated into a centralized project database for all water distribution system assets at Eielson AFB.
3.1.3 The Contractor shall ensure compatibility with existing GIS feature layers and standards.
3.1.4 The Contractor shall update and validate the current water system data to reflect existing condition accurately, ensuring reliability for operational and planning needs.
Contractor Deliverable: Investigation Report.
3.2 TASK 2 – Hydraulics Model Configuration and Calibration
The Contractor shall:
3 of 7 Controlled Unclassified Information (CUI)
• Develop a GIS-integrated hydraulics model using current and future water consumption data that supports future modeling and system optimization.
• Incorporate pipe characteristics, demand nodes, pump curves, and storage tank data.
• Conduct flow/pressure test at designated hydrants for model calibration.
• Adjust hydraulic model parameters to reflect actual system behaviors under normal and peak flow conditions.
Contract Deliverable: GIS-based Hydraulics Model and Calibration Report.
3.3 TASK 3 – UDF Planning
The overall goal is to establish a comprehensive UDFP that operations can consistently rely on for effective system maintenance and water quality management.
The Contractor shall:
• Identify and map out flushing sequences to systematically isolate each main segment.
• Establish recommended flushing velocities and document the step-by-step sequence for valve and hydrant operations.
• Specify which valves to close, which hydrants to open, and the sequence for each flushing section.
• Provide step-by-step field instructions, maps, and data collection forms for monitoring and documentation.
Contract Deliverable:
UDFP documents, including:
• Step-by-step flushing instructions
• Recommended velocity/flow requirements
• Color-coded flushing sequence maps
• Monitoring and recordkeeping forms
4.0 SUBMITTALS AND DELIVERABLES
The Contractor is required to provide documentation and reports at various stages of the project to ensure accountability, transparency, and adherence to the scope of work. Deliverables shall be submitted in electronic format (e.g., PDF, Word, Excel, GIS files) via the designated document management system.
4.1 Task 1 – Investigation
4.1.1 Post-award Kick-Off Teleconference Call: A post-award kick-off meeting with Government will be held within fifteen (15) working days of NTP. The post-award kick-off meeting will include all key team members.
4.1.2 Project Coordination Teleconferences and Status Updates: Coordination meetings with the Government shall be conducted as needed to discuss progress and any roadblocks.
4.1.3 Meeting Minutes: Meeting minutes will include meeting attendees, decisions made, action items per the POC. The document must be in MS Word (current version) or Adobe PDF
4 of 7 Controlled Unclassified Information (CUI)
(current version) and be sent to the 354 CES Project Manager (PM) and 354 CONS Contracting Officer (CO) by the Contractor in digital form via email.
4.1.4 Progress Reporting (Required): The Contractor shall submit monthly progress reports detailing the status of the investigation phase, challenges encountered, and preliminary findings.
4.1.5 Quality Control: The Contractor shall document quality control checks, including verification of data accuracy and completeness.
4.2 Task 2 and 3 – Hydraulics Model & UDF Plan
4.2.1 Draft Submittal: The Contractor shall submit a draft report for Government review, including the initial hydraulics model and flushing plan. Hydraulics modeling shall be provided in WaterGEMS. The Government will procure a license for the software to view contractor submittal.
4.2.2 Review meeting: A review meeting with Government will be held for the draft submittal.
4.2.3 Meeting Minutes: Meeting minutes will include meeting attendees, decisions made, action items per the POC. The document must be in MS Word (current version) or Adobe PDF (current version) and be sent to the 354 CES Project Manager (PM) and 354 CONS Contracting Officer (CO) by the Contractor in digital form via email.
4.2.4 Progress Reporting (Required): The Contractor shall submit monthly progress reports detailing the status of the project phase and challenges encountered.
4.2.5 Final Submittal: After addressing Government comments, the final deliverables shall be submitted, including the GIS-based hydraulics model (in WaterGEMS format), calibration report, flushing sequence documentation, and field instruction manual.
5.0 CONTRACT REQUIREMENTS
The Contractor shall provide all deliverables in draft form for Government review prior to final submission. The Government will review, provide comments, and request necessary revisions to ensure compliance with project requirements.
5.1 Government Review and Comment Resolution
• The Government will have a 21 calendar day review period for all draft deliverables.
• The Contractor shall provide a comment resolution matrix (CRM) tracking all Government comments, Reponses, and incorporated changes.
• Revised deliverables shall be submitted within 30 calendar days after receiving Government
NTP.
• Any significant disputes regarding review comments shall be escalated to the 354 CES Project
Manager and resolved through mutual discussions.
5.2 CADD and GIS Development, Performance, and Recording
• The Contractor shall ensure that all WaterGEMS and CADD deliverables are compatible with Eielson AFB’s existing systems and formats.
• GIS modeling shall be developed to align with base-wide GIS feature layers and attributable standards.
5 of 7 Controlled Unclassified Information (CUI)
• Deliverables shall include:
o Updated GIS database files with water system components and flushing sequences.
o CADD drawings representing the flushing plan and infrastructure modifications.
o Metadata and documentation for GIS and CADD files, ensuring future usability by base personnel.
• The Contractor shall provide a demonstration and training session for Government personnel on using and updating GIS and CADD files, and training on the WaterGEMS system.
6.0 GENERAL REQUIREMENTS
6.1 Information Management Support
6.1.1 Automated Data Processing (ADP) Systems: Contractor personnel shall possess the expertise and capability to provide support in conducting analysis on infrastructure using data from AF and DoD enterprise systems and others as necessary.
6.1.2 Data Repository: The Contractor shall store, transmit, evaluate and/or present data generated in the designated format.
6.1.3 Data Collection: The Contractor shall perform data collection in support of the services outlined in this SOW. The Contractor shall integrate field data with the GIS database.
6.1.4 Design and Production of Visual Media Products: The data that the Contractor produces shall be done in the style that supports the AF mission. The Contractor shall create reports, tables, graphs, and charts and consult with graphic illustrators on development of artwork and coordinate with staff or contracted photographers to acquire needed photographic images.
6.2 Project Management Support
6.2.1 Technical Expertise: The Contractor shall assist in providing technical expertise to the Government at meetings. The Contractor shall assist in delivering technical presentations, providing agendas and meeting minutes, facilitate meetings.
6.2.2 Technical Reviews: The Contractor shall perform and deliver technical reviews of data, model and flushing program deliverables submitted to the Government for validation. Reviews shall assess functional and technical accuracy/completeness, compliance with applicable regulations, and feasibility.
6.2.3 Documentation: The Contractor shall assist in documenting program files, organizing files and providing administrative support.
6.3 Quality Assurance/Quality Control (QA/QC)
6.3.1 Oversite: The Contractor shall provide QA/QC Oversight of field activities and implement QA/QC measures to verify data accuracy and ensure procedural adherence.
6.3.2 Data and Analysis Support: The Contractor shall assist in the technical review of work products, including site data, analytical data, and reports. The Contractor shall analyze field data and adjust the flushing model accordingly.
6.5 Work Site Coordination
6 of 7 Controlled Unclassified Information (CUI)
6.5.1 Work Site Activities: The Contractor shall coordinate work site activities to ensure the protection of human health and the environment; the prevention of damage to property, utilities, materials, supplies, and equipment; and the avoidance of work interruptions. The Contractor shall provide physical security to the work area with security equipment and personnel as specified in this SOW. The Contractor shall conduct field investigation, flushing tests, and data collection as required.
6.5.2 Compliance: The Contractor must comply with Occupational Safety and Health Administration (OSHA) safety and health regulations and local safety office requirements. The Contractor is required to provide the CO copies of any OSHA report(s) submitted during the duration of the SOW.
7.0 TRAVEL REQUIREMENTS
The Contractor shall estimate travel costs based on the following anticipated requirements for this government order:
7.1 Data acquisition/Field investigation: Assumes three (3) personnel for seven (7) days.
7.2 Follow up site visit: Assumes seven (7) days +/- (days can be negotiated up or down) of travel for three (3) personnel.
8.0 APPLICABLE DOCUMENTS
The Contractor shall ensure compliance with all applicable standards, including but not limited to:
• W192BV-10-D-2006 Unidirectional Flushing (UDF) Guide for Water Distribution Systems
• RDC/CERL TR-20-1, January 2020, Guidelines for Minimizing Potable Water Loss Due to Water Distribution System Flushing (attached)
• American Warter Works Association (AWWA) M32 – Water Distribution System Operation and Maintenance
• Environmental Protection Agency (EPA guidelines for water distribution system maintenance
• Base-specific GIS and data management standards
• Department of Defense (DoD) Unified Facilities Criteria (UFC) for Water Supply Systems
• Occupational Safety and Health Administration (OSHA) regulations for water infrastructure work
9.0 PLACE OF PERFORMANCE
• Eielson AFB, Alaska
• Remote work may be conducted for certain tasks, such as data processing, report writing, and GIS modeling.
10.0 SECURITY REQUIREMENTS
No access to classified material is expected to be required. The Contractor must be eligible to obtain Access to base IAW base access guidelines.
7 of 7 Controlled Unclassified Information (CUI)
Some hydrants and valves required are located within restricted areas on the installation. Contractor personnel will require government escorts to access these locations. The Contractor shall coordinate with the Government at least seven days in advance to schedule access to any restricted areas necessary to perform flushing activities.
11.0 GOVERNMENT POINTS OF CONTACT
Contracting Officer:
Kimberly Graham
(907) 337-7482 kimberly.graham.3@af.mil
354 CES Project Manager:
Yaun Yaun Zhao
(907) 377-4251 yaunyaun.zhao.ctr@us.af.mil
354 CES Interim Engineering Flight Chief:
Jason Colquhoun
(907) 377-1736 jason.colquhoun@us.af.mil
END OF STATEMENT OF WORK
ATTACHMENTS:
1. W192BV-10-D-2006 Unidirectional Flushing (UDF) Guide for Water Distribution Systems
2. RDC/CERL TR-20-1, January 2020, Guidelines for Minimizing Potable Water Loss Due to Water
Distribution System Flushing mailto:kimberly.graham.3@af.mil mailto:yaunyaun.zhao.ctr@us.af.mil mailto:jason.colquhoun@us.af.mil
File details come from the government source that posted it. Updated .