Swing Bridge Repair at SW 11th Avenue – Bridge #865748
This is an Invitation to Bid (ITB) package issued by the City of Fort Lauderdale, Florida Parks and Recreation Department for construction services related to swing bridge repair and rehabilitation. The project involves comprehensive repair of the SW 11th Avenue Swing Bridge (Bridge #865748), including mobilization and demobilization, installation and maintenance of floating turbidity barriers, repair and adjustment of the elevator wheel assembly, replacement of the center pivot bearing, removal and replacement of the manual drive shaft bronze journal, reinforcement of the balance wheel track and support ring affected by corrosion, removal and replacement of the machinery platform around the center pivot pier, sidewalk joint seal repairs, concrete sidewalk restoration, guardrail and hardware repairs, vegetation and debris removal, operational testing, alignment verification, final inspections, and complete closeout documentation including as-built drawings and warranty documents. Sealed electronic bids are due August 20, 2026, at 2:00 p.m. local time. A pre-bid conference is scheduled for July 29, 2026, at 10:00 a.m. at Fort Lauderdale Fleet Maintenance Services (220 SW 14th Avenue, Building 2), followed immediately by a mandatory site visit at 11:00 a.m. at the SW 11th Avenue Swing Bridge. Substantial completion is required within 120 calendar days of the Notice to Proceed, with final completion within 150 calendar days. The contract is awarded on a lump sum basis with no change orders permitted unless owner-driven and initiated by the City.
The bid amount includes all labor, materials, equipment, permits, bonds, overhead, and profit necessary to complete the project. A bid security of 10 percent of the bid amount must accompany each offer. The project includes allowances totaling $30,000 comprising a $5,000 permit fee allowance and $25,000 owner's contingency. Contractor compensation will be made via the City's P-Card Program (Visa or MasterCard). Contractors must possess a Florida Certified General Contractor License or equivalent and provide proof of applicable subcontractor licenses for marine, mechanical, electrical, and structural bridge repair work. Bidders must demonstrate a minimum of five years of successful experience in movable bridge construction and repair within Florida and completion of at least three similar projects within the last ten years. Comprehensive insurance coverage is required, including Commercial General Liability ($2,000,000 each occurrence), Business Automobile Liability ($1,000,000 combined single limit), Protection and Indemnity/Watercraft Liability ($1,000,000 per occurrence), and Workers' Compensation. A performance and payment bond equal to 100 percent of the contract price is mandatory. Liquidated damages are assessed at $250 per calendar day for delays beyond the specified completion date. Procurement Specialist Santrecia Harden manages the solicitation and can be contacted at (954) 828-5169 or saharden@fortlauderdale.gov.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF FORT LAUDERDALE
CONTRACT AND SPECIFICATIONS PACKAGE
BID/EVENT NO. 635
PROJECT NO. P12912
SWING BRIDGE REPAIR AT 11TH
AVENUE – BRIDGE #865748
Santrecia Harden Senior Procurement Specialist
E-mail: saharden@fortlauderdale.gov Telephone: (954) 828-5169
TOC-1
TABLE OF CONTENTS
Description Pages
I. BID INFORMATION
Invitation to Bid ............................................................................................................. ITB-1 Instruction to Bidders ...................................................................................................... IB-1 General Conditions ....................................................................................................... GC-1 Special Conditions ......................................................................................................... SC-1 Construction Agreement (Sample) ................................................................................... C-1
II. SCOPE OF SERVICES .................................................................... INFOR ATTACHMENT
III. 11TH AVENUE BRIDGE HIGH WATER RISK STUDY .................... INFOR ATTACHMENT
III. FDOT POINT REPORT - 865748 ...................................................... INFOR ATTACHMENT
Note: The following documents are available electronically for completion and must be returned with your bid along with your bid security, proof of insurance, and proof of required licenses/certifications.
Affidavit of Compliance with Foreign Entity Laws CITB Questionnaire Sheet City of Fort Lauderdale Bid/Proposal Bid Certification Contract Payment Method Disadvantaged Business Enterprise Preference Certification E-Verify Affirmation Statement Local Business Preference Certification Non-Collusion Statement
Non-Discrimination Certification Drug Free Workplace Certification City of Fort Lauderdale Reference Form
ITB-1
INVITATION TO BID
Sealed bids will be received electronically until 2:00 p.m., local time, on August 20, 2026, and opened online immediately thereafter for ITB EVENT NO. 635, PROJECT NO. P12912, Swing Bridge Repair at 11TH Avenue - Bridge #865748.
Please be advised that effective immediately, and until further notice, all Invitation to Bids, Request for Proposals, Request for Qualifications, and other solicitations led by the City of Fort Lauderdale will be opened electronically via the City’s on-line strategic sourcing platform at the date and time indicated on the solicitation. All openings will be held on the City’s on-line strategic sourcing platform.
In the event of any conflict or discrepancy between bid price(s) submitted by bidder electronically into the City’s online strategic sourcing platform Unit Price field(s), any other forms or attachments (whether part of the City’s solicitation documents or documents created and uploaded by the bidder, or another section/field of the System, the online unit price(s) inputted electronically into the System by the bidder shall govern.
Anyone requesting assistance or having further inquiry in this matter must contact the Procurement Specialist indicated in the solicitation, via the Question and Answer (Q&A) forum on the City’s online strategic sourcing platform before the Last Day for Questions indicated in the Solicitation.
The City of Fort Lauderdale, Florida (City) is seeking bids from qualified bidders, hereinafter referred to as the Contractor, with demonstrated experience in movable bridge maintenance, repair, and rehabilitation services to furnish all labor, supervision, materials, equipment, tools, detour coordination, marine traffic coordination, temporary bridge closure coordination, environmental protection measures, permits, testing, closeout documentation, and all incidentals necessary to complete the structural and mechanical repairs to the SW 11th Avenue Swing Bridge
- Bridge #865748.
The scope of work includes, but is not limited to, mobilization and demobilization, installation and maintenance of floating turbidity barriers necessary to support the corrective repairs associated with the deficiencies identified in the FDOT Point Inspection Report, repair and adjustment of the elevator wheel assembly, replacement of the center (pivot) bearing, removal and replacement of the manual drive shaft bronze journal, reinforcement of the balance wheel track and support ring affected by corrosion, and removal and replacement of the machinery platform around the center pivot pier.
The work shall further include sidewalk joint seal repairs, concrete sidewalk restoration, guardrail and hardware repairs, vegetation and debris removal, final verification and corrective resolution of the deficiencies identified in the FDOT Point Inspection Report, operational testing of the swing bridge, alignment verification, final inspections, and complete closeout documentation including as-built drawings and warranty documents.
The Contractor shall coordinate bridge closures and marine traffic, and furnish all labor, materials, and equipment necessary to complete the corrective repairs associated with the deficiencies identified in the FDOT Point Inspection Report, in accordance with applicable City, County, and State requirements.
ITB-2
The itemized lump sum prices shall include all labor, materials, equipment, and all other costs necessary to fully complete the project. The bid price shall also include all applicable insurance, permits, bonds, overhead, profit, and any other costs required to deliver a complete and operational project.
THE FOLLOWING IS APPLICABLE TO THIS SOLICITATION IF CHECKED:
☐ LUMP SUM BID - City shall pay awarded bidder the Contract Price for the performance of work described in this Invitation for Bid. Payment shall be at the lump sum price stated in this Invitation to Bid and/or resultant contract. This price shall be full compensation for all costs, including overhead and profit, associated with completion of all work in full conformity with the requirements as stated or shown, or both, in the contract documents. The cost of any item of work not covered in this solicitation shall still be provided and the cost borne by the contractor.
NO CHANGE ORDERS WILL BE ALLOWED UNLESS IT IS OWNER-DRIVEN AND INITIATED
BY THE CITY.
Drawing Plans: There are no drawing plans for this Project.
Licensing Requirements: Possession of a State of Florida Certified General Contractor License is required for this Project.
OR
Any other State or County License(s), Certification(s) or Registration(s) deemed legally permissible by the City to conduct the nature of the work required in this solicitation.
Any sub-contractors employed by the Proposer shall be licensed and insured in accordance with this solicitation. Additionally, it is the Proposer’s responsibility for ensuring that any sub-contractors’ work meets the requirements of this solicitation at all times.
Certification Requirements: Contractor shall provide proof of applicable subcontractor licenses/certifications for marine, mechanical, electrical, or structural bridge repair work as required, and FDOT MOT/TTC certification for any work within the public right-of-way.
NOTE: Payment on this contract will be made by Visa or MasterCard.
Pre-Bid Conference: A pre-bid conference will be held on:
Date: July 29, 2026
Time: 10:00 AM (E.S.T.)
Location: Fort Lauderdale Fleet Maintenance Services
220 SW 14th Avenue, Building 2 Fort Lauderdale, Florida 33312
ITB-3
Site Visit: A site visit will follow immediately after the pre-bid conference at:
Date: July 29, 2026
Time: 11:00 AM (E.S.T.)
Location: SW 11th Avenue Swing Bridge Fort Lauderdale, Florida 33312
While attendance is not mandatory, tours at other times might not be available. It is the sole responsibility of the Contractor to become familiar with the scope of the City’s requirements and systems prior to submitting a bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. It is strongly suggested that all Bidders attend the pre-bid meeting and/or site visit.
It will be the sole responsibility of the Bidder to attend the pre-bid/site visit to inspect the City's location(s) facilities systems prior to submitting a bid. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the Bidder has familiarized themselves with the nature and extent of the work, equipment, materials, and labor required.
If a person decides to appeal any decision made by the board, agency, or commission with respect to any matter considered at such meeting or hearing, he or she will need a record of the proceedings, and that, for such purpose, he or she may need to ensure that a verbatim record of the proceedings is made, which record includes the testimony and evidence upon which the appeal is to be based.
Bid Security: A certified check, cashier's check, bank officer's check or bid bond for TEN percent (10%) of the bid amount, made payable to the City of Fort Lauderdale, Florida, shall accompany each offer.
Bid Bonds:
Bidders can submit bid bonds four different ways.
1) Bidders may upload their original executed bid bond on the City’s online strategic sourcing platform to accompany their electronic bids and deliver the original, signed and sealed hard copy to the Procurement Services Department, 101 NE 3rd Avenue, Suite 200, Fort Lauderdale, Florida 33301-1016, within five (5) business days after bid opening, with the company name, bid number and title clearly indicated on the envelope.
2) Bidders may upload their original executed bid bond on the City’s online strategic sourcing platform to accompany their electronic bids and mail the original, signed and sealed hard copy to the Procurement Services Department, 101 NE 3rd Avenue, Suite 200, Fort Lauderdale, Florida 33301-1016, within five (5) business days after bid opening, with the company name, bid number and title clearly indicated on the envelope.
3) Bidders can hand deliver their original, signed and sealed bid bond in a sealed envelope to the Procurement Services Department, 101 NE 3rd
ITB-4
Avenue, Suite 200, Fort Lauderdale, Florida 33301-1016, before time of bid opening, with the company name, bid number and title clearly indicated on the envelope.
4) Bidders can mail their original, signed and sealed bid bond to the
Procurement Services Department, 101 NE 3rd Avenue, Suite 200, Fort Lauderdale, Florida 33301-1016, before time of bid opening, with the company name, bid number and title clearly indicated on the envelope.
NOTE: Bond must be received in Procurement and time stamped before bid opening.
It will be the sole responsibility of the bidder to ensure that its bid is submitted prior to the bid opening date and time listed. PAPER BID SUBMITTALS WILL NOT BE ACCEPTED. BIDS
MUST BE SUBMITTED ELECTRONICALLY VIA THE CITY’S ONLINE STRATEGIC
SOURCING PLATFORM.
Certified Checks, Cashier’s Checks and Bank Drafts:
These CANNOT be submitted via the City’s online strategic souring platform, nor are their images allowed to be uploaded and submitted with your electronic bid. These forms of securities, as well as hard copy bid bonds, must be received on or before the Invitation to Bid (ITB) opening date and time, at the Procurement Services Department, 101 NE 3rd Avenue, Suite 200, Fort Lauderdale, Florida 33301-1016, with the bid number and title clearly indicated on the envelope.
It is the bidder’s sole responsibility to ensure that its bid bond or other bid security is received by the Procurement Services Department before the time of bid opening. Failure to adhere to this requirement may be grounds to consider the bid as non-responsive.
The City of Fort Lauderdale reserves the right to waive any informality in any or all bids and to reject any or all bids.
For information concerning technical specifications, please utilize the Q&A platform provided on the City’s online strategic sourcing platform. Questions of a material nature must be received prior to the cut-off date specified in the solicitation. Material changes, if any, to the scope of services or bidding procedures, will only be transmitted by written addendum. Bidders please note: No part of your bid can be submitted via FAX. No variation in price or conditions shall be permitted based upon a claim of ignorance. Submission of a bid will be considered evidence that the bidder has familiarized himself with the nature and extent of the work, equipment, materials, and labor required. The entire bid response must be submitted in accordance with all specifications contained in this solicitation.
Information on bid results and projects currently out to bid can be obtained on the City’s website
– https://www.fortlauderdale.gov/Government/Departments/Procurement-Services. For general inquiries, please call (954) 828-5933.
-END OF SECTION-
IB-1
INSTRUCTIONS TO BIDDERS
The following instructions are given for the purpose of guiding bidders in properly preparing their bids or proposals. These directions have equal force and weight with the specifications, and strict compliance is required with all of these provisions.
QUALIFICATIONS OF BIDDERS – No bid will be accepted from, nor will any contract be awarded to, any person who is in arrears to the City of Fort Lauderdale, upon any debt or contract, or who has defaulted, as surety or otherwise, upon any obligation to the City, or who is deemed irresponsible or unreliable by the City Commission of Fort Lauderdale.
CONCERNING SUB-CONTRACTORS, SUPPLIERS, AND OTHERS – The amount of work that is sublet by the Bidder shall be limited by the condition that the Bidder shall, with his own organization, perform at least forty percent (40%) of the total dollar amount of the Work to be performed under the Agreement.
PERSONAL INVESTIGATION – Bidders shall satisfy themselves by personal investigation, and by such other means as they may think necessary or desirable, as to the conditions affecting the proposed work and the cost. No information derived from maps, plans, specifications, or from the Engineer or City staff shall relieve the Contractor from any risk or from fulfilling all terms of the contract.
INCONSISTENCIES – Any inconsistency between different provisions of the plans, specifications, bid or contract, or any point requiring explanation must be inquired by the bidder, in writing, at least ten (10) days prior to the time set for opening bids. After bids are opened, the bidders shall abide by the decision of the Engineer as to such interpretation.
ADDENDA AND INTERPRETATIONS – No interpretations of the meaning of the plans, specifications or other contract documents will be made orally to any bidder. Prospective bidders must request such interpretation in writing as instructed in the bid package. To be considered, such request must be received by the Questions and Answers deadline as indicated in the City’s online strategic sourcing platform. Material changes, if any, to the scope of services or bidding procedures will only be transmitted by written addendum. It is the bidder’s responsibility to verify if addenda have been issued in the City’s online strategic sourcing platform. Failure of any bidder to receive any such addenda or interpretation shall not relieve any bidder from any obligation under its bid as submitted. All addenda so issued shall become a part of the contract document. Bidder shall verify in the City’s online strategic sourcing platform that it has all addenda before submitting a bid.
LEGAL CONDITIONS – Bidders are notified to familiarize themselves with the provisions of the laws of the State of Florida relating to hours of labor on municipal work, and with the provisions of the laws of the State of Florida and the Charter and the ordinances of the City of Fort Lauderdale.
PUBLIC ENTITY CRIMES – A person or affiliate who has been placed on the convicted vendor list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to a public entity, may not submit a bid on a contract with a public entity for the construction or repair of a public building or public work, may not submit bids on leases of real property to a public entity, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with any public entity, and may not transact business with any public entity in excess of the threshold amount provided in Section 287.017, Florida Statutes, for Category Two for a period of thirty-six (36) months from the date of being placed on the convicted vendor list.
FORMS OF BIDS – Each bid and its accompanying statements MUST BE SUBMITTED ELECTRONICALLY, IN GOOD ORDER WITH ALL BLANKS COMPLETED, and must show the name of the bidder and a statement as to its contents. In the event of any conflict or discrepancy between bid price(s) submitted by bidder electronically into the City’s online strategic sourcing platform Unit Price
IB-2
field(s), any other forms or attachments (whether part of the City’s solicitation documents or documents created and uploaded by the bidder, or another section/field of the System, the online unit price(s) inputted electronically into the System by the bidder shall govern.
The bid must be signed by one duly authorized to do so, and in case signed by a deputy or subordinate, the principal's properly written authority to such deputy or subordinate must accompany the bid. No bid will be accepted, for any reason whatsoever, which is not submitted to the City as stated above, within the specified time.
INSURANCE – Contractor shall provide and shall require all of its sub-contractors to provide, pay for, and maintain in force at all times during the term of the Agreement, such insurance, including Property Insurance (Builder’s Risk), Commercial General Liability Insurance, Business Automobile Liability Insurance, Workers’ Compensation Insurance, Employer’s Liability Insurance, and Umbrella/Excess Liability, as stated below. Such policy or policies shall be issued by companies authorized to do business in the State of Florida and having agents upon whom service of process may be made in the State of Florida.
BID BOND – A certified check, cashier's check or bank officer's check made payable to the City of Fort Lauderdale, or a bid bond in favor of the City of Fort Lauderdale shall accompany each bid as evidence of the good faith and responsibility of the bidder. The amount of the check or bond shall be retained by the City as liquidated damages in the event the bidder whose bid is accepted refuses to or fails to enter into a contract for the execution of the work solicited in this Invitation to Bid.
The bid bond or check shall be a guarantee that the successful bidder will promptly execute a contract satisfactory to the City for the work solicited in this Invitation to Bid and furnish good and sufficient bonds.
Following the full execution of a contract for the work solicited in this Invitation to Bid and the successful bidder’s provision of good and sufficient bonds, in the event bid security was provided by check, the amount of the bid security accompanying the successful bidder’s bid will be refunded to the successful bidder, or in the event bid security was provided by a bond, the bond accompanying the successful bidder’s bid will be returned to the successful bidder. In the event the successful bidder fails to enter into, execute, and deliver a contract and furnish the required bonds within ten (10) days after the City provides notice to the successful bidder to deliver the executed contract and the required bonds, the bid bond shall immediately be payable to the City of Fort Lauderdale, or in the case of a check, the City shall retain the amount of the check, as liquidated damages. The City’s retention of such amount shall not be construed as a penalty or forfeiture.
FILLING IN BIDS – All prices must be electronically submitted in the bid pages, and bids must fully cover all items for which prices are asked and no other. Where more than one person is interested, it is required that all persons interested or their legal representative make all verification and subscribe to the bid. In the event of any conflict or discrepancy between bid price(s) submitted by bidder electronically into the City’s online strategic sourcing platform Unit Price field(s), any other forms or attachments (whether part of the City’s solicitation documents or documents created and uploaded by the bidder, or another section/field of the System, the online unit price(s) inputted electronically into the System by the bidder shall govern.
PRICES QUOTED – Deduct any discount offered and quote firm net unit prices. In the case of a discrepancy in computing the amount of the bid, the unit price quoted will govern. All prices quoted shall be F.O.B. destination, freight prepaid (Bidder pays and bears freight charges, Bidder owns goods in transit and files any claims), unless otherwise stated in Special Conditions. Each item must be bid separately. No attempt shall be made to tie any item or items contained in the ITB with any other business with the City.
IB-3
BIDS FIRM FOR ACCEPTANCE – Bidder warrants, by virtue of bidding, that his bid and the prices quoted in his bid will be firm for acceptance by the City for a period of one hundred and twenty (120) days from the date of bid opening unless otherwise stated in the ITB. The City shall award contract within this time period or shall request to the recommended awarded vendor an extension to hold pricing, until products/services have been awarded.
ADDITIONAL ITEMS OR SERVICES – The City may require additional items or services of a similar nature, but not specifically listed in the contract. The Contractor agrees to provide such items or services and shall provide the City prices on such additional items or services. If the price(s) offered are not acceptable to the City, and the situation cannot be resolved to the satisfaction of the City, the City reserves the right to procure those items or services from other vendors, or to cancel the contract upon giving the Contractor thirty (30) days written notice.
DELETION OR MODIFICATION OF SERVICES – The City reserves the right to delete any portion of the Contract at any time without cause, and if such right is exercised by the City, the total fee shall be reduced in the same ratio as the estimated cost of the work deleted bears to the estimated cost of the work originally planned. If work has already been accomplished on the portion of the Contract to be deleted, the Contractor shall be paid for the deleted portion on the basis of the estimated percentage of completion of such portion.
If the Contractor and the City agree on modifications or revisions to the task elements, after the City has approved work to begin on a particular task or project, and a budget has been established for that task or project, the Contractor will submit a revised cost to the City for approval prior to proceeding with the work.
TERMINATION FOR UNAPPROPRIATED FUNDS – The obligation of the City for payment to a Contractor is limited to the availability of funds appropriated in a current fiscal period, and continuation of the contract into a subsequent fiscal period is subject to appropriation of funds, unless otherwise authorized by law.
CAUSES FOR REJECTION – No bid will be canvassed, considered or accepted which, in the opinion of the City is informal or unbalanced, or contains inadequate or unreasonable prices for any items.
Each item must carry its own proportion of the cost as nearly as is practicable. Any alteration, erasure, interlineation, or failure to specify bids for all items called for in the schedule shall render the bid informal.
REJECTION OF BIDS – The City reserves the right to reject any bid if the evidence submitted by the bidder, or if the investigation of such bidder, fails to satisfy the City that such bidder is properly qualified to carry out the obligations and to complete the work contemplated. Any or all bids will be rejected, if there is reason to believe that collusion exists among bidders. A bid will be considered irregular and may be rejected, if it shows serious omissions, alterations in form, additions not called for, conditions or unauthorized alternates, or irregularities of any kind. The City reserves the right to reject any or all bids and to waive such technical errors as may be deemed best for the interests of the City.
BID PROTEST PROCEDURE – Any bidder who is not recommended for award of a contract and who alleges a failure by the City to follow the City’s procurement ordinance or any applicable law may protest to the Procurement Department - Chief Procurement Officer, by delivering a letter of protest within five
(5) days after a Notice of Intent to award is posted on the City’s website at the following link:
https://www.fortlauderdale.gov/Government/Departments/Procurement-Services/Notices-of-Intent-to- Award-Reject.
The complete protest ordinance may be found on the City’s website at the following link:
https://library.municode.com/fl/fort_lauderdale/codes/code_of_ordinances?nodeId=COOR_CH2AD_A
RTVFI_DIV2PR_S2-182DIREPRAWINAW.
IB-4
WITHDRAWALS – Any bidder may, without prejudice to himself, withdraw its bid at any time prior to the expiration of the time during which bids may be submitted. Such request for withdrawal must be in writing and signed in the same manner and by the same person who signed the bid. After expiration of the period for receiving bids, no bids can be withdrawn, modified, or explained.
CONTRACT – The bidder to whom award is made shall execute a written contract to do the work and maintain the same in good repair until final acceptance by the proper authorities and shall furnish good and sufficient bonds as specified within ten (10) days after receiving such contract for execution. If the bidder to whom the first award is made fails to enter into a contract as provided, the award may be annulled and the contract let to the next lowest bidder who is responsive and responsible, and that bidder shall fulfill every stipulation and obligation as if such bidder were the original party to whom award was made.
The contract shall provide that the Contractor agrees to correct any defective or faulty work or material, which may appear within one (1) year after completion of the work and receipt of final payment.
ENFORCEMENT OF SPECIFICATIONS – Copies of the specifications will be placed in the hands of all the assistants to the Engineer and Inspectors employed on the Work, who shall enforce each and every requirement of the contract. Such assistants shall have no authority to vary from such requirements.
DRAWING PLANS – There are no drawing plans for this Project.
SURETY BOND – The Contractor shall execute and record in the public records of Broward County, Florida, a payment and performance bond in an amount at least equal to the Contract Price with a surety insurer authorized to do business in the State of Florida as surety, (“Bond”), in accordance with Section 255.05, Florida Statutes (2025), as may be amended or revised, as security for the faithful performance and payment of all of the Contractor’s obligations under the Contract Documents.
The successful bidder shall furnish a performance and payment bond in compliance with Section 255.05, Florida Statutes (2025), written by a Corporate Surety company, holding a Certificate of Authority from the Secretary of the Treasury of the United States as acceptable sureties on federal bonds, in an amount equal to the total amount payable by the terms of the contract, executed and issued by a Resident Agent licensed by and having an office in the State of Florida, representing such Corporate Surety, conditioned for the due and faithful performance of the work, and providing in addition to all other conditions, that if the Contractor, or his or its subcontractors, fail to duly pay for any labor, materials, or other supplies used or consumed by such Contractor, or his or its subcontractor or subcontractors, in performance of the work contracted to be done, the Surety will pay the same in the amount not exceeding the sum provided in such bonds, together with interest at the rate of fifteen percent (15%) per annum, and that they shall indemnify and hold harmless the City of Fort Lauderdale to the extent of any and all payments in connection with carrying out of the contract, which the City may be required to make under the law.
The Contractor is required at all times to have a valid surety bond in force covering the work being performed. A failure to have such bond in force at any time shall constitute a default on the part of the Contractor. A bond written by a surety, which becomes disqualified to do business in the State of Florida, shall automatically constitute a failure on the part of the Contractor to meet the above requirements.
Such bond shall continue in effect for one (1) year after completion and acceptance of the work with liability equal to at least twenty-five percent (25%) of contract price, or an additional bond shall be conditioned that the Contractor will correct any defective or faulty work or material which appear within one (1) year after completion of the contract, upon notification by the City, except in contracts which are concerned solely with demolition work, in which cases twenty-five percent (25%) liability will not be applicable.
IB-5
AUDIT OF CONTRACTOR’S RECORDS – Upon execution of the Contract, the City reserves the right to conduct any necessary audit of the Contractor’s records. Such an audit, or audits, may be conducted by the City or its representatives at any time prior to final payment, or thereafter, for a period up to three
(3) years. The City may also require submittal of the records from either the Contractor, the Subcontractor, or both. For the purpose of this Section, records shall include all books of account, supporting documents and papers deemed necessary by the City to assure compliance with the contract provisions.
Failure of the Contractor or Subcontractor to comply with these requirements may result in disqualification or suspension from bidding for future contracts or disapproval as a Subcontractor at the option of the City.
The Contractor shall assure that each of its Subcontractors will provide access to its records pertaining to the project upon request by the City.
PERIODIC ESTIMATE FOR PARTIAL PAYMENT – After the Contractor has submitted a periodic estimate for partial payment, approved and certified by the Parks and Recreation Department, the City shall make payment in the manner provided in the Contract Documents and in accordance with Florida’s Prompt Payment Act, Section 218, Florida Statutes (2025).
RESERVATION FOR AWARD AND REJECTION OF BIDS – The City reserves the right to accept or reject any or all bids, part of bids, and to waive minor irregularities or variations to specifications contained in bids, and minor irregularities in the bidding process. The City also reserves the right to award the contract on a split order basis, lump sum basis, individual item basis, or such combination as shall best serve the interest of the City. The City reserves the right to make an award to the responsive and responsible bidder whose product or service meets the terms, conditions, and specifications of the ITB and whose bid is considered to best serve the City’s interest. In determining the responsiveness of the offer and the responsibility of the Bidder, the following shall be considered when applicable: the ability, capacity and skill of the Bidder to perform as required; whether the Bidder can perform promptly, or within the time specified, without delay or interference; the character, integrity, reputation, judgment, experience and efficiency of the Bidder; the quality of past performance by the Bidder; the previous and existing compliance by the Bidder with related laws and ordinances; the sufficiency of the Bidder’s financial resources; the availability, quality and adaptability of the Bidder’s supplies or services to the required use; the ability of the Bidder to provide future maintenance, service or parts; the number and scope of conditions attached to the bid.
LOCAL BUSINESS PREFERENCE – Section 2-186, Code of Ordinances of the City of Fort Lauderdale, provides for a local business preference. In order to be considered for a local business preference, a proposer must include the Local Business Preference Certification Statement of this ITB, as applicable to the local business preference class claimed at the time of Bid submittal:
Upon formal request of the City, based on the application of a Local Business Preference, the Proposer shall, within ten (10) calendar days, submit the following documentation to the Local Business Preference Class claimed:
a. Copy of City of Fort Lauderdale current year business tax receipt, or Broward County current year business tax receipt, and
b. List of the names of all employees of the proposer and evidence of employees’ residence within the geographic bounds of the City of Fort Lauderdale or Broward County, as the case may be, such as current Florida driver license, residential utility bill (water, electric, telephone, cable television), or other type of similar documentation acceptable to the City.
IB-6
Failure to comply at time of bid submittal shall result in the Proposer being found ineligible for the local business preference.
Definitions:
a. The term "Class A business" shall mean any business that has established and agrees to maintain a permanent place of business located in a non-residential zone, staffed with full-time employees within the limits of the city, and shall maintain a staffing level for the proposed work of at least fifty percent (50%) who are residents of the City of Fort Lauderdale.
b. The term "Class B business" shall mean any business that has established and agrees to maintain a permanent place of business located in a non-residential zone, staffed with full-time employees within the limits of the city, or shall maintain a staffing level for the proposed work of at least fifty percent (50%) who are residents of the City of Fort Lauderdale.
c. The term "Class C business" shall mean any business that has established and agrees to maintain a permanent place of business located in a non-residential zone, staffed with full-time employees within the limits of Broward County.
c. The term "Class D business" shall mean any business that does not qualify as a Class A, Class B, or Class C business.
The complete local business preference ordinance may be found on the City’s web site at the following link:
https://library.municode.com/fl/fort_lauderdale/codes/code_of_ordinances?nodeId=COOR_CH2AD_A
RTVFI_DIV2PR_S2-186LOBUPR.
DISADVANTAGED BUSINESS ENTERPRISE PREFERENCE – Section 2-185, Code of Ordinances of the City of Fort Lauderdale, provides for a disadvantaged business preference. In order to be considered for a disadvantaged business preference, a proposer must include a certification from a government agency, as applicable to the disadvantaged business preference class claimed at the time of Bid submittal:
Upon formal request of the City, based on the application of a Disadvantaged Business Preference the Proposer shall within ten (10) calendar days submit the following documentation to the Disadvantaged Business Enterprise Preference Class claimed:
a. Copy of City of Fort Lauderdale current year business tax receipt, or the Tri-County
(Broward, Dade, West Palm Beach) current year business tax receipt, or proof of active Sunbiz status and
b. List of the names of all employees of the proposer and evidence of employees’ residence within the geographic bounds of the City of Fort Lauderdale or the Tri- County, as the case may be, such as current Florida driver license, residential utility bill (water, electric, telephone, cable television), or other type of similar documentation acceptable to the City.
Failure to comply at time of bid submittal shall result in the Proposer being found ineligible for the Disadvantaged Business Enterprise Preference business preference.
The complete Disadvantaged Business Preference ordinance may be found on the City’s website at the following link:
RTVFI_DIV2PR_S2-185EQOPDIBUEN.
IB-7
DEBARRED OR SUSPENDED BIDDERS OR PROPOSERS – The bidder or proposer certifies, by submission of a response to this solicitation, that neither it nor its principals and subcontractors are presently debarred or suspended by any Federal department or agency.
LOBBYING ACTIVITIES – ALL CONTRACTORS PLEASE NOTE: Any contractor submitting a response to this solicitation must comply, if applicable, with City of Fort Lauderdale Ordinance No. C- 11-42 & Resolution No. 07-101, Lobbying Activities. Copies of Ordinance No., C-11-42, and Resolution No. 07-101, may be obtained from the City Clerk’s Office at 1 East Broward Boulevard, Suite 444, Fort Lauderdale, Florida 33301.
The Ordinance may also be viewed on the City's website at the following link:
RTVFI_DIV2PR.
GC-1
GENERAL CONDITIONS
Unless otherwise modified in the Project’s Special Conditions, the following General Conditions shall be part of the Contract:
GC - 01 - DEFINITIONS – The following words and expressions, or pronouns used in their stead, shall wherever they appear in the Contract and the Contract Documents, be construed as follows:
"Addendum" or "Addenda" – shall mean the additional Contract provisions issued in writing, by the Engineer, prior to the receipt of bids.
"Bid" – shall mean the offer or bid of the Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.
"Bidder" – shall mean any person, firm, company, corporation or entity submitting a bid for the Work.
"Bonds" – shall mean bid, performance and payment bonds and other instruments of security, furnished by Contractor and his surety in accordance with the Contract Documents.
“City” – shall mean the City of Fort Lauderdale, Florida, a Florida municipal corporation. In the event the City exercises its regulatory authority as a government body, the exercise of such regulatory authority and the enforcement of any rules, regulations, codes, laws and ordinances shall be deemed to have occurred pursuant to City’s authority as a governmental body and shall not be attributable in any manner to the City as a party to this Contract.
"Consultant" – shall mean a person, firm, company, corporation or other entity employed by the City to perform the professional services for the project.
“Contractor” – shall mean the successful Bidder who has been employed by the City to perform the construction and related services for the project.
“Contract Work” – shall mean everything expressed or implied to be required to be furnished and furnished by the Contractor by any one or more of the parts of the Contract Documents referred to in the Contract hereof. In the case of any inconsistency in or between any parts of this Contract, the Project Manager shall determine which shall prevail.
"Department Director" – shall mean the Director of the Parks and Recreation Department for the City of Fort Lauderdale.
“Design Documents” – shall mean the construction plans and specifications included as part of a Bid Solicitation prepared either by the City or by the Consultant under a separate Agreement with the City.
“Engineer” – shall include the terms “professional engineer” and “licensed engineer” and means a person who is licensed to engage in the practice of engineering under Florida Statute, Chapter 471.
An Engineer may be a City employee or a consultant hired by the City.
"Extra Work" – shall mean work other than that required by the Contract.
"Inspector" – shall mean an authorized representative of the City assigned to make necessary inspections of materials furnished by Contractor and of the Work performed by Contractor.
"Notice" – shall mean written notice sent by certified United States mail, return receipt requested, or sent by commercial express carrier with acknowledgement of delivery, or via fax or email, or by
GC-2
hand delivery with a request for a written receipt of acknowledgment of delivery and shall be served upon the Contractor either personally or to its place of business listed in the Bid.
“Owner” – shall mean the City of Fort Lauderdale.
“Project Manager” – shall mean a professional designated by the City to manage the Project under the supervision and direction of the Department Director or designee.
"Site" – shall mean the area upon or in which the Contractor's operations are carried out and such other areas adjacent thereto as may be designated as such by the Project Manager.
"Sub-contractor" – shall mean any person, firm, company, corporation or other entity, other than employees of the Contractor, who or which contracts with the contractor, to furnish, or actually furnishes labor and materials, or labor and equipment, or labor, materials and equipment at the site.
"Surety" – shall mean any corporation or entity that executes, as Surety, the Contractor's performance and payment bond securing the performance of this Contract.
GC - 02 - SITE INVESTIGATION AND REPRESENTATION – The Contractor acknowledges that it has satisfied itself as to the nature and location of the Work under the Contract Documents, the general and local conditions of the Site, particularly those bearing upon availability of transportation, disposal, handling and storage of materials, availability of labor, water, electric power, and roads, field conditions, the type of equipment and facilities needed preliminary to and during the prosecution of the Work and all other matters which can in any way affect the Work or the cost thereof under the Contract Documents.
The Contractor acknowledges that it has conducted extensive tests, examinations and investigations and represents and warrants a thorough familiarization with the nature and extent of the Contract Documents, the Work, locality, soil conditions, moisture conditions and all year-round local weather and climate conditions (past and present), and, in reliance on such tests, examination and investigations conducted by Contractor and the Contractor’s experts, has determined that no conditions exist that would in any manner affect the Bid Price and that the project can be completed for the Bid Price submitted.
Any failure by the Contractor to acquaint itself with all the Site conditions shall not relieve Contractor from responsibility for properly estimating the difficulty or cost thereof under the Contract Documents.
GC - 03 - SUBSTITUTIONS – If the Contractor desires to use materials and/or products of manufacturer's names different from those specified in the Contract Documents, the Bidder requesting the substitution shall make written application as described herein. The burden of proving the equality of the proposed substitution rests on the Contractor making the request. To be acceptable, the proposed substitution shall meet or exceed all expressed requirements of the Contract Documents and shall be submitted upon the Contractor's letterhead. The following requirements shall be met in order for the substitution to be considered:
1. Requests for substitution shall be accompanied by such technical data, as the party making the request desires to submit. The Project Manager will consider reports from reputable independent testing laboratories, verified experience records from previous users and other written information valid in the circumstances; and
2. Requests for substitution shall completely and clearly indicate in what respects the materials and/or products differ from those indicated in the Contract Documents; and
GC-3
3. Requests for substitution shall be accompanied by the manufacturer's printed recommendations clearly describing the installation, use and care, as applicable, of the proposed substitutions; and
4. Requests for substitution shall be accompanied by a complete schedule of changes in the Contract Documents, if any, which must be made to permit the use of the proposed substitution.
If a proposed substitution is approved by the Project Manager, an addendum will be issued to prospective bidders not less than three (3) working days prior to the date set for opening of bids.
Unless substitutions are received and approved as described above, the successful Bidder shall be responsible for furnishing materials and products in strict accordance with the Contract Documents.
GC- 04 - CONSTRUCTION RESOURCES – Contractor shall provide all labor and equipment necessary to complete the installation within a timely manner. Contractor shall provide details as to manpower and equipment to be dedicated to the project in its Work Plan. Contractor is responsible for making arrangements, obtaining and purchasing construction water services if required to complete the work.
GC - 05 - CONTROL OF THE WORK – The Project Manager shall have full control and direction of the Work in all respects. The Project Manager and/or his authorized designee(s) shall, at all times, have the right to inspect the Work and materials. The Contractor shall furnish all reasonable facilities for obtaining such information, as the Project Manager may desire respecting the quality of the Work and materials and the manner of conducting the Work. Should the Contractor be permitted to perform night Work, or to vary the period which work is ordinarily carried on in the daytime, he shall give ample notice to the Project Manager so that proper and adequate inspection may be provided.
Such Work shall be done only under such regulations as are furnished in writing by the Project Manager, and no extra compensation shall be allowed to the Contractor therefore. In the event of night work, the Contractor shall furnish such light, satisfactory to the Project Manager, as will ensure proper inspection. Nothing herein contained shall relieve the Contractor from compliance with any and all City ordinances relating to noise or Work during prohibited hours.
GC - 06 - SUB-CONTRACTOR – The Contractor shall not sublet, in whole or any part of the Work without the written consent and approval of the Project Manager. Within ten (10) days after official notification of starting date, the Contractor must submit in writing, to the Project Manager, a list of all Sub-contractors. No Work shall be done by any sub-contractor until such Sub-contractor has been officially approved by the Project Manager. A sub-contractor not appearing on the original list will not be approved without written request submitted to the Project Manager and approved by the Department Director. In all cases, the Contractor shall give his personal attention to the Work of the Sub-contractors and the Sub-contractor is liable to be discharged by the Contractor, at the direction of the Project Manager, for neglect of duty, incompetence or misconduct.
Acceptance of any sub-contractor, other person, or organization by the Project Manager shall not constitute a waiver of any right of Project Manager to reject defective Work or Work not in conformance with the Contract Documents.
Contractor shall be fully responsible for all acts and omissions of its Sub-contractors and of persons and organizations directly or indirectly employed by them and of persons and organizations for whose acts any of them may be liable to the same extent that he is responsible for the acts and omissions of persons directly employed by him. Nothing in the Contract Documents shall create any contractual relationship between City and any sub-contractor or other person or organization having a direct contract with Contractor, nor shall it create any obligation on the part of City to pay or to see to the payment of any moneys due to any sub-contractor or other person, or organization, except as may otherwise be required by law.
GC-4
GC - 07 - QUANTITIES – Contractor recognizes and agrees that the quantities shown on plans and Bid/Price Schedule are estimates only and may vary during actual construction. No change shall be made involving any departure from the general scheme of the Work and that no such change involving a material change in cost, either to the City or Contractor, shall be made, except upon written permission of the City. However, the Project Manager shall have the right to make minor alternations in the line, grade, plan, form or materials of the Work herein contemplated any time before the completion of the same. That if such alterations shall diminish the quantity of the Work to be done, such alterations shall not constitute a claim for damages or anticipated profits. That if such alterations increase the amount of the Work to be done, such increase shall be paid for according to the quantity actually performed and at the unit price or prices stipulated therefore in the Contract. The City shall, in all cases of dispute, determine the amount or quantity of the several kinds of Work which are to be paid for under this Contract, and shall decide all questions relative to the execution of the same, and such estimates and decisions shall be final and binding.
Any Work not herein specified, which might be fairly implied as included in the Contract, of which the City shall judge, shall be done by the Contractor without extra charge. However, such cost increases shall be authorized either by the Department Director or designee, or the City Commission based upon the purchasing threshold amounts provided for in Chapter 2 of the City of Fort Lauderdale’s Code of Ordinances.
GC - 08 - NO ORAL CHANGES – Except to the extent expressly set forth in the Contract, no change in, or modification, termination or discharge of the Contract in any form whatsoever, shall be valid or enforceable unless it is in writing and signed by the parties charged, therewith or their duly authorized representative.
GC - 09 - PERMITS AND PROTECTION OF PUBLIC – Permits on file with the City and/or those permits to be obtained by the Contractor, shall be considered directive in nature, and will be…