FSSS_MV Chugach.docx
DOCX document 97 KB Posted
- Attached to
- M/V Chugach Site Preparation Services Federal contract opportunity
- Solicitation number
- 12010920Q0096
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 001.pdf | ||
| 12010920Q0096.docx | DOCX document | |
| Statement of Work_Specifications.docx | DOCX document | |
| Service Wage Determination.pdf | ||
| MV Chugach Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
*Note – Change all references of construction to services, and all bids to quotes
Table of Contents
| Table of Contents | 1 |
| Preface | 4 |
| 101 - Terms, Format, and Definitions | 5 |
| 101.01 Meaning of Terms | 5 |
| 101.03 Abbreviations. | 5 |
| 101.04 Definitions. | 5 |
| 102 - Bid, Award, and Execution of Contract | 8 |
| 102 Bid, Award, and Execution of Contract | 8 |
| 103 - Scope of Work | 9 |
| Deletions | 9 |
| 104 - Control of Work | 10 |
| Deletions | 10 |
| 104.06 Use of Roads by Contractor | 10 |
| 105 - Control of Material | 11 |
| 105.02 Material Sources. | 11 |
| 105.02(a) Government-provided sources. | 11 |
| 105.05 Use of Material Found in the Work. | 11 |
| 106 - Acceptance of Work | 12 |
| 106.01 Conformity with Contract Requirements. | 12 |
| 106.07 Delete | 14 |
| 107 - Legal Relations and Responsibility to the Public | 15 |
| 107.05 Responsibility for Damage Claims. | 15 |
| 107.06 Contractor’s Responsibility for Work. | 15 |
| 107.09 Legal Relationship of the Parties. | 15 |
| 107.10 Environmental Protection. | 15 |
| 108 - Prosecution and Progress | 17 |
| 108 Delete. | 17 |
| 109 - Measurement and Payment | 18 |
| 109 Deletions | 18 |
| 109.02 Measurement Terms and Definitions. | 18 |
| 153 - Contractor Quality Control | 19 |
| 153.04 Records. | 19 |
| 155 - Schedules for Construction Contracts | 20 |
| 155 Delete. | 20 |
| 156 - Public Traffic | 21 |
| 157 - Soil Erosion Control | 24 |
| 157.03 General | 24 |
| 204 - Excavation and Embankment | 25 |
| 204.09 Preparing Foundation for Embankment Construction. | 25 |
| 204.10 Embankment Construction. | 25 |
| 204.11 Compaction. | 26 |
| 204.13 Sloping, Shaping, and Finishing. | 26 |
| 204.13 Sloping, Shaping, and Finishing. | 26 |
| Table 204-2 Construction tolerances. | 27 |
| 204.14 Disposal of Unsuitable or Excess Material. | 27 |
| 204.14 Disposal of Unsuitable or Excess Material. | 28 |
| 204.15 Acceptance | 28 |
| Table 204-1 Sampling and Testing Requirements. | 28 |
| 205 - Rock Blasting | 30 |
| 208.04 General. | 30 |
| 252 - Special Rock Embankment and Rock Buttress | 31 |
| 252.02 Material. | 31 |
| 252.03 Placing Rock. | 31 |
| 301 - Untreated Aggregate Courses | 32 |
| 301 Title Change. | 32 |
| 301.01 Work. | 32 |
| 301.02 Material. | 32 |
| 301.03 General. | 32 |
| 301.04 Mixing and Spreading. | 33 |
| 301.05 Compacting | 33 |
| 301.06 Surface Tolerance. | 34 |
| 301.08(b) Plasticity Index. | 34 |
| Table 301-1 Field Density Requirements. | 36 |
| Table 301-1—Acceptance Sampling and Testing Requirements. | 37 |
| 301.09 Measurement. | 38 |
| 303 - Road Reconditioning | 39 |
| 303.01 Work | 39 |
| 303.06 Aggregate Surface Reconditioning. | 39 |
| 303.06 Asphalt and Aggregate Surface Reconditioning | 39 |
| Table 303-1 Sampling and Testing Requirements | 40 |
| 303.07 Roadway Reconditioning | 41 |
| 303.10 Measurement | 41 |
| 303.10 Measurement | 41 |
| 625 - Turf Establishment | 42 |
| 625.03 General. | 42 |
| 625.04 Preparing Seedbed. | 44 |
| 625.11 Measurement. | 44 |
| 635 - Temporary Traffic Control | 45 |
| 635.03 General. | 45 |
| 651 - Development of Pits & Quarries | 46 |
| 703 - Aggregate | 47 |
| 703.05 Subbase, Base, Surface Course, and Screened Aggregate. | 47 |
| Table 703-2 Correction. | 49 |
| Table 703-3 Correction. | 50 |
| Table 703-16 Add. | 51 |
| Table 703-2 Correction. | 51 |
| 703.10(e) Flakiness Index. | 51 |
| 703.10(i) Adherent Coating. | 51 |
| 718 - Traffic Signing and Marking Material | 52 |
| 718.02 Reserved. | 52 |
| 718.02 Protective Overlay Film and Edge Film. | 52 |
| 718.05 Aluminum Panels | 52 |
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006 Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.01_nat_us_01_17_2013
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
153 - Contractor Quality Control 153.04_nat_us_10_24_2007
153.04 Records.
Delete all but the first sentence
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic 156.00_nat_us_04_17_2007 Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
| Construction sign panels | 633 | |
| Retro-reflective sheeting | 718.01 | |
| Temporary concrete barrier | 618 | |
| Temporary plastic fence | 710.11 | |
| Temporary traffic control devices | 718.22 |
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 2 hours at any one time followed by an open period of no less than 30 minutes.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.
Table 156-1 Temporary Road Closures
| Road Number |
| At Milepost |
| Maximum Consecutive Days of Closure |
| Minimum Consecutive Days Open |
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
157 - Soil Erosion Control 157.03_nat_us_02_24_2005
157.03 General
Delete the entire subsection and replace with the following:
Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.
Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.
When erosion control measures are not functioning as intended, immediately take corrective action.
204 – Excavation and Embankment
204.05 Conserved Topsoil
Delete the entire paragraph.
204.06_nat_us_03_02_2005
204.06 Roadway Excavation
(a) General.
Add the following:
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
204.09_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Add the following:
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
(a) Sloping.
Add the following:
Slope rounding is not required on tolerance class D though M roads.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class(a)
| A |
| B |
| C |
| D |
| E |
| F |
| G |
| H |
| I |
| J |
| K |
| L |
| M |
| Roadbed width (ft) |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.5 |
| +1.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
Subgrade elevation (ft)
| +0.1 |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.5 |
| +2.0 |
| +3.0 |
| +2.0 |
| +3.0 |
| (c) |
| Centerline alignment (ft) |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| `+1.5 |
| +1.5 |
| +2.0 |
| +3.0 |
| +3.0 |
| +5.0 |
| (c) |
| Slopes, excavation, and embankment (% slope(b) |
| +3 |
| +5 |
| +5 |
| +5 |
| +5 |
| +5 |
| +10 |
| +10 |
| +10 |
| +10 |
| +20 |
| +20 |
| +20 |
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.14_nat_us_03_02_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
204.14_1005_us_01_18_2005
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites or legally off of the project.
Add the following:
End haul consists of the direct loading, hauling, and placement of excess or unsuitable excavation including clearing and grubbing debris from within areas shown on drawings to designated disposal location(s). End Haul also includes all work required to prepare designated disposal location(s) prior to placement of end hauled material. Shape and dress slopes of disposed material as shown on drawings or as approved by CO.
204.15_nat_us_02_07_2007
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
Add the following note to the table:
(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
204.16_1005_us_05_04_2007
204.16 (b) Unclassified borrow, select borrow, and select topping.
Add the following:
When contract quantities are designated in the schedule as method of measurement estimate the borrow excavation quantity from design data based on prism cubic yard compacted in final position, in the embankment.
The quantity of material hauled will be based on the quantity of borrow excavation shown in the schedule. Measure haul distance between the center of the material source and the center of embanked material. Compute haul by analytical methods as determined by CO.
Haul from non-designated material source requested by the Contractor will be considered haul from Contractor-furnished sources with an adjustment in contract price, in accordance with applicable contract provisions.
Haul distance from a Contractor-furnished source will be measured as the haul distance from the designated material source if the haul distance from the Contractor-furnished material source is greater than the haul distance from the designated source.
Haul distance from a Contractor furnished-sources will be measured as the haul distance from the Contractor-furnished material source if the haul distance from the Contractor-furnished source is less than the haul distance from the designated source.
205 - Rock Blasting 205.02_nat_us_05_13_2004
205.03 Regulations
Add the following:
(e) Forest Service Manual (FSM) 6745 Explosives and Blasting Materials.
205.06_nat_us_05_12_2004
205.06 Preblast condition survey and vibration monitoring and control.
Add the following:
Limit blasting induced vibrations in saturated soils or on steep slopes as designated or as directed by the CO.
Notify the owners of nearby utilities at least 24 hours before blasting.
205.07_nat_us_05_12_2004
205.07 Test Blasting.
Add the following:
Test blast at all new sources, when rock type changes, and when blast layout changes due to slope or other changes.
205.08_nat_us_05_12_2004
205.08 Blasting.
Delete the following:
Place a stake next to each hole with hole number and total depth drilled.
Do not stem the hole with drill cuttings.
Add the following:
(8) Halt blasting operations when any of the following conditions exist:
Precipitation exceeds 1 inch in any 24 hour period.
Precipitation exceeds 3 inches in any 96 hour period.
Precipitation exceeds 4 inches in any 144 hour period.
A landslide occurs within 300 feet of a blast site under any precipitation conditions.
252 – Special Rock Embankment and Rock Buttress 252.02_nat_us_05_13_2004
252.02 Material.
Add the following:
Geotextiles, Type IV (A,B, or C) 714.01
252.03 Placing Rock.
Place geotextile according to Subsection 207.05. When geotextile is in place, request approval before placing rock on geotextile.
301 – Untreated Aggregate Courses 301.00_nat_us_03_03_2005 301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.01_nat_us_03_03_2005
301.01 Work.
Add the following:
Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.
301.02_nat_us_05_16_2005
301.02 Material.
Add the following:
| Bentonite |
| 725.30 |
| Calcium Chloride Flake |
| 725.02 |
| Lignon Sulfonate |
| 725.20 |
| Magnesium Chloride Brine or Calcium Chloride Liquid |
| 725.02 |
301.03_nat_us_02_28_2013
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.
301.04_nat_us_03_03_2005
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.
(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.
(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant. During mixing, add water to provide the necessary moisture content for compacting.
(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
Route and distribute hauling and leveling equipment over the width and length of each layer.
301.05_nat_us_05_17_2005
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08_nat_us_03_30_2005 301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)”.
301.08_nat_us_10_14_2011 Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Base and Subbase |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| --- |
| Method C |
| --- |
| AASHTO T 99 |
| 1 per type and source of material |
| Source of material |
| Yes |
| Before using in work |
| “ |
| “ |
| “ |
| “ |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| Compaction |
| --- |
| Method C, D |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
| Surfacing |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| “ |
| “ |
| “ |
| Before using in work |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
Compaction
| Method C, D |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
301.08_nat_us_03_03_2005 Table 301-1: Add the following:
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Subbase & Base Courses L, M, N, O, P, Q, R |
| Measured and tested conformance (Subsection 106.04) |
| Plastic Limit |
| - |
| AASHTO T 90 |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| Yes |
| 4 Hours |
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Aggregate Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Aggregate Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Additive |
| Measured and tested conformance (Subsection 106.04) |
| Amount of Additive |
| - |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| No |
| 4 Hours |
301.09_nat_us_07_07_2005
301.09 Measurement.
Replace the second paragraph with the following:
Measure aggregate by cubic yard compacted in place when payment is by contract quantities.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
303 - Road Reconditioning 303.01_nat_us_03_02_2005
303.01 Work.
Delete and add the following:
This work consists of reconditioning ditches, shoulders, roadbeds, cattleguards, asphalt surfaces, and aggregate surfaces.
303.06_nat_us_08_05_2008
303.06 Aggregate Surface Reconditioning.
Delete and replace with the following:
303.06 Asphalt and Aggregate Surface Reconditioning.
Repair soft and unstable areas to the full depth of the aggregate surface and according to Subsection 204.07. Scarify to the depth of the aggregate surface or to a depth of 6 inches, whichever is less, and remove surface irregularities. Reshape, finish, and compact the entire aggregate surface according to Subsection 301.05, Subsection 321.05, or Subsection 322.05 as applicable.
For asphalt surfaces, clean the existing surface of all loose material, dirt, or other deleterious substances by approved methods. Remove and dispose of unsuitable material that shows evidence of distress, excess asphalt material, or settlement in the roadbed. Patch the areas with approved material that conforms to and is compatible with the adjacent pavement structure. Perform the patch work according to Section 301, 404, 430, or other sections as applicable for the layer or courses being repaired. Clean and seal cracks in the existing asphalt surface according to Subsection 414.05. Correct surface irregularities exceeding 6 inches in depth with a specified aggregate. Place and compact the aggregate according to Subsections 301.04 and 301.05. Prelevel other dips, depressions, sags, excessive or nonexistent crown, or other surface irregularities with asphalt concrete according to Section 404. Spread and compact the asphalt concrete in layers parallel to the grade line not to exceed 2 inches in compacted depth.
Delete Table 303-1 and replace with the following:
Table 303-1 Sampling and Testing Requirements Reporting Time
| Before using in work |
| “ |
| “ |
| “ |
| Before placing next layer |
| (1) Minimum of 5 points per proctor. |
Split Sample
| Yes, when requested |
| “ |
| “ |
| “ |
| — |
| Point of Sampling |
| Processed material before incorporating in work |
| “ |
| “ |
| “ |
| In-place |
Sampling Frequency
| 1 per each mixture or change in material |
| “ |
| “ |
| “ |
| 1 per 3000 yd2 |
| Test Methods Specifications |
| AASHTO T 99 (1) |
| R-1 Marshall |
| AASHTO T 180(1) |
| R-1 Marshall |
| AASHTO T 310 or other approved procedures |
| Category |
| — |
| — |
| — |
| — |
| — |
| Characteristic |
| Moisture-density Method D |
| Moisture-density Method E |
| Moisture-density Method F |
| Moisture-density Method G |
| In-place density & moisture content |
| Type of Acceptance (Subsection) |
| Measured and tested |
for conformance (106.04)
| Material or Product |
| Existing Roadway |
303.07_nat_us_03_02_2005
303.07 Roadway Reconditioning.
Add the following:
Remove cattleguard decks. Clean the deck and the area beneath the cattleguard of soil and other material to the bottom of the original foundation over the entire width of the installation. Reinstall the cattleguard deck.
303.10_10_us_05_23_2005
303.10 Measurement
Modify the third paragraph as follows:
Measure road reconditioning, aggregate surface reconditioning, roadway reconditioning, and pulverizing by the mile, station, foot, or square yard. Measure horizontally along centerline of roadway. Measure the square yard area on horizontal plane. Do not measure isolated areas less than 20 square yards.
303.11_nat_us_03_29_2005
303.10 Measurement
Modify the second paragraph as follows:
Measure ditch reconditioning and shoulder reconditioning by the mile, station, or foot horizontally along the centerline of the roadway for each side of the roadway.
625 - Turf Establishment 625.00_1005_us_07_20_2012
625.03 General.
Delete the entire subsection and add the following:
Apply temporary turf establishment to soil cut & fill slopes within fourteen (14) days after each 2000 foot section of road has been constructed to final grade, unless otherwise agreed by the CO. Cut & Fill slopes damaged by construction activities shall be reseeded within ten (10) days of the damage. See FP section 157.04 (d) for exceptions.
Apply turf establishment to finished slopes and ditches between April 15 and September 15.
Do not seed during windy weather or when the ground is excessively wet, frozen, snow covered, extremely dry, cloddy, hard pan, or is otherwise not friable.
Application Methods for Seed, Fertilizer, & Limestone
"Furnish the kinds of seed and the amounts to be applied in terms of pure live seed as follows:
Seed mixture contains no more than 0.01% of other seed whether identified or not.
Kind of Seed Live Seed (Lbs/Acre)
1. * Boreal Red Fescue ______ ___________10__________ (Festuca Rubra, Boreal variety)
2. Annual Ryegrass ___________ ___________10__________ (Lolium multiflorum)
3. * Arctared Fescue__________ ___________5__________ (Festuca rubra, Arctared variety)
4. __________________________ _______________________
5. __________________________ ______________________
6. __________________________ _______________________
Total ________25 _____________
· * If Boreal Red Fescue or Arctared Fescue is unavailable Fawn Tall fescue may be substituted. If Fawn Tall Fescue is unavailable, then the amounts of the available two may be adjusted to 100%.
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
| Example |
| 5 lbs. pure live seed/acre = |
| 6.55 lbs. commercial |
0.90 x 0.85 seed per acre; purity = 90% and germination = 85%
Apply seed by the ___dry or hydraulic method__. Fertilizer shall be applied at a rate of 200 pounds plus 103 for urea at pounds per acre in all applications by either the dry or hydraulic method and have a chemical analysis as listed below:
Nutrient Percent
Nitrogen, N . . . . . . . . . . . . . ____10_____
Phosphorus, P205 . . . . . . . . . ____20_____
| Potassium, K . . . . . . . . . . . . . | ____10_____ |
| Nitrogen, Urea . . . . . . . . . . . . . | ____46_____ |
Retest Germination after 6 months of Purchase.
Apply mulch when specified at a rate of 1205 pounds per acre by the hydraulic method only.
625.04 Preparing Seedbed.
Delete entire Subsection
625.05 Watering.
Add the following:
During dry soil conditions,
625.11 Measurement.
Delete the second paragraph and add the following:
Seeding and mulching acreage by the acre on ground surface will not be measured for payment. The Contract Quantity for seeding and mulching will be determined by approved designs or averages from design segments included in quantity tables utilized in linear grading pay item.
635 – Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
651 - Development of Pits & Quarries 651.00_1005_us_01_18_2005 Description
651.01 This work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development.
Construction Requirements
651.02 General. Submit a plan of operations according to Section 105. Perform all work in accordance with Sections 105, 201, 203, 204, 205, 625, and 635, landscape preservation requirements, and the approved pit and quarry development plan of operations. Perform the work in accordance with MSHA 30 CFR, part 56.
Confine blasted material and overburden within the designated clearing limits. Unless otherwise approved by CO, retrieve all material which falls outside the designated clearing limits and either incorporate it into the work or stockpile it in designated areas.
Access Roads. Construct or recondition access roads to the pit or quarry as specified in Section 204 and 303, and as SHOWN ON THE DRAWINGS.
651.03 Acceptance. Developing pits and quarries will be evaluated under Subsections 106.02 and 106.04.
Measurement
651.04 Measure the Section 651 items listed in the bid schedule according to Subsection 109.02.
Payment
651.05 The accepted quantities will be paid at the contract price per unit of measurement for the Section 651 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
703 - Aggregate 703.05_nat_us_08_14_2009 Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
| (1) Gradation | Table 703-2 |
| (2) Liquid limit, AASHTO T 89 | 25 max. |
| (3) Plastic limit, AASHTO T 90 | Nonplastic |
| (4) Los Angeles abrasion, AASHTO T 96 | 40% max. |
| (5) Sodium sulfate soundness loss (5 cycles), | 12% max. |
AASHTO T 104
| (6) Durability index (coarse), AASHTO T 210 | 35 min. |
| (7) Durability index (fine), AASHTO T 210 | 35 min. |
| (8) Fractured faces, ASTM D 5821 | 50% min. |
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
| (1) Gradation | Table 703-3 |
| (2) Liquid limit, AASHTO T 89 | 35 max. |
(3) Plastic Index, AASHTO T 90
| a) If the percent passing the No. 200 sieve is less than 12% | 2 to 9 | ||
| b) If the percent passing the No. 200 sieve is greater than 12% | Less than 2 | ||
| (4) Los Angeles abrasion, AASHTO T 96 | 40% max. | ||
| (5) Sodium sulfate soundness loss (5 cycles), | 12% max. |
AASHTO T 104
| (6) Durability index (coarse), AASHTO T 210 | 35 min. |
| (7) Durability index (fine), AASHTO T 210 | 35 min. |
| (8) Fractured faces, ASTM D 5821 | 75% min. |
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Do not furnish material that contains asbestos fibers.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary. Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
| (1) Gradation | Table 703-16 | |||
| (2) Plastic Index, AASHTO T 90 | Less than 9 | |||
| (3) Los Angeles abrasion, AASHTO T 96 | 55% max. |
(4) Free from organic matter and lumps or balls of clay.
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Delete Table 703-2 and replace with the following:
Table 703-2 Target Value Ranges for Subbase and Base Gradation
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
| Grading Designation |
| E (Base) |
| 62 – 90 (6) |
| 36 – 74 (6) |
| 12 – 26 (4) |
| 4.0 – 7.0 (3) |
( ) The value in the parentheses is the allowable deviation () from the target values..
D (Base)
| 100 |
| 86 – 100 (6) |
| 51 – 82 (6) |
| 36 – 64 (6) |
| 12 – 26 (4) |
| 4.0 – 7.0 (3) |
C (Base)
| 80 – 100 (6) |
| 64 – 94 (6) |
| 40 – 69 (6) |
| 31 – 54 (6) |
4.0 –7.0 (3)
B (Subbase)
| 100 |
| 97 – 100 |
40 – 60 (8)
4.0 – 12.0 (4)
| A (Subbase) |
| 100 |
| 97 – 100 |
65 – 79 (6)
45 – 59 (7)
| 28 – 42 (6) |
| 9 – 17 (4) |
| 4.0 – 8.0 (3) |
| Sieve Size |
| 2½ inch |
| 2 inch |
| 1½ inch |
| 1 inch |
| 3/4 inch |
| 1/2 inch |
| 3/8 inch |
| No. 4 |
| No. 40 |
| No. 200 |
Delete Table 703-3 and replace with the following:
Table 703-3 Target Value Ranges for Surface Gradation
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
| Grading Designation |
| U |
| 71 – 90 (6) |
| 50 – 68 (7) |
| 34 – 51 (6) |
| 19 – 30 (5) |
| 8.0 – 15.0 (4) |
( ) The value in the parentheses is the allowable deviation () from the target values.
If the plasticity index (PI) is greater than 0, the TV range for the No. 200 sieve size is 8-12 (4).
T
71 – 91 (6)
| 43 – 60 (7) |
| 30 – 46 (6) |
| 16 – 28 (5) |
| 8.0 – 15.0 (4) |
| S |
| 100 |
| 72 – 92 (6) |
| 51 – 71 (6) |
| 36 – 53 (7) |
| 26 – 40 (6) |
| 14 – 25 (5) |
| 8.0 – 15.0 (4) |
H
97 - 100
| 80 – 92 (6) |
| 58 – 70 (7) |
| 28 – 40 (6) |
| 16 – 26 (5) |
| 9.0 – 14.0 (4) |
G
| 100 |
| 97 - 100 |
| 70 – 80 (6) |
| 51 – 63 (7) |
| 28 – 39 (6) |
| 19 – 27 (5) |
| 10.0 – 16.0 (4) |
| F |
| 100 |
| 97-100 |
| 76-89 (6) |
| 56-68 (6) |
| 43-53 (7) |
| 23-32 (6) |
| 15-23 (5) |
| 10.0-16.0 (4) |
| Sieve Size |
| 1 1/2 inch |
| 1 inch |
| 3/4 inch |
| 1/2 inch |
| 3/8 inch |
| No. 4 |
| No. 8 |
| No. 16 |
| No. 40 |
| No. 200 |
Add Table 703-16:
Table 703-16 Gradation Requirements for Screened Aggregate
| Sieve Size |
| Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) |
Grading Designation
| L |
| M |
| N |
| O |
| P |
| Q |
| R |
| 6 inch |
| 100 |
| 100 |
4 inch
| 100 |
| 100 |
3 inch
| 100 |
| 100 |
2 inch
No. 4
15-45
15-45
15-45
703.07_nat_us_03_02_2005 Table 703-2 Correction
Include the following substitution
In Table 703-2, delete the “436 – 74 (6)” percent by mass passing for grading E (base) No. 4 sieve size and substitute “36 – 74 (6
703.10_nat_us_04_11_2011 703.10(e) Flakiness Index.
Delete and replace with the following:
Flakiness Index, FLH T 508 30% max.
703.10(i) Adherent Coating.
Ad…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .