This document is a Statement of Work (SOW) for a refrigeration repair project at the Federal Correctional Institution (FCI) Talladega in Alabama. The SOW requires a contractor to remove and replace all old refrigeration equipment and materials, including condensers, evaporators, and compressors, at the FCI and Federal Prison Camp (FPC) Talladega foodservice and warehouse facilities. The contractor will be responsible for wiring, piping, and ensuring the new refrigeration units are fully functional. Key requirements include using energy-efficient equipment, adhering to all relevant codes and regulations, and meeting quality assurance and security/safety standards. The related federal contract opportunity, solicitation number 15B31324Q00000016, is for a firm-fixed price contract, with quotes due by August 1, 2024 and an anticipated award date of August 9, 2024. The government will award to the most advantageous offeror based on past performance and price, with past performance weighted higher.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK/SPECIFICATIONS

FCI Talladega – 24Z3A2E Repair F/S cooler Freezer

I. SPECIFICATIONS:

A. INTRODUCTION

The Federal Bureau of Prisons (FBOP), Federal Correctional Institution located at 565 East Renfroe Rd in Talladega, Alabama intends to make a single award to a responsible entity that will provide all necessary equipment, labor, materials, and incidentals to provide a new and install new refrigeration units and necessary components that are more energy efficient.

B. SCOPE OF WORK

1. FCI & FPC Camp Food Service

FCI TDG

The contractor will remove all old equipment and materials and provide and install new refrigeration units(condensers, evaporators, and compressors) at the FCI Foodservice and FPC foodservice and Warehouse, with onsite start up once its installed. All existing wiring will be used. Contractor will be responsible to wire up and pipe in all connections to properly have the new refrigeration units 100% functional. Compressors shall be hermetic for freezers operation at 20 degrees F or below and shall be scroll for freezers and coolers operating above 20 degree F with refrigerant accumulators, crankcase heaters, high/low pressure controls, and insulated discharge thermostat. Select for operating conditions required and with vapor injection to maximize efficiencies and reliability using Refrigerant R-404A or approval equal. -25 degrees F to 20 degrees F interior temperature at 105 degrees F condenser temperature, 4.0 EER to 5.0 EER, respectively. Confirm that compressors used are economical and the most energy efficient product on the market at the time of construction. Provide refrigeration piping evacuation, leak test, refrigerant charges as required under the manufacture’s installation personnel requirements. Refrigerant charge varies on each project depending upon actual piping lengths required. Compressors shall be located near the access door for ease of access and maintenance at a location approved on site by the project manager. Compressor locations preferred are near the cooler/freezer on compressor racks at floor level, but not a loading docks or on top of cooler/freezer. Hard mount multiple compressors on one rack. Use soft neoprene mounts for single compressor mounting. The Warehouse Freezer is master built 30’x60’ and coolers are roughly 10’x10’ and condenser and evaps are dscdo4dac, mhmdo12ac mhmdo12a, e1ldo124b-tes and elmdo136a-ta2. The contractor may visit the site to collect data and to observe the existing conditions prior to submitting a proposal. The contractor shall field verify all dimensions and specifications, and guidelines before commencement of any work. The contractor must ensure Federal, State and Local Environmental codes and regulations are fully adhered to.

A. QUALITY ASSURANCE/INSTALLATION REQUIREMENTS

All installers/technicians shall be qualified and certified by the manufacturer to install and start up, trouble shoot new Refrigeration units.

All seismic zone requirements, environmental compliance, Life Safety, NFPA, ADA-ABA, and Federal, State and Local codes and regulations will be considered during all phases of this project.

It is the contractor’s responsibility to obtain permitting, should it be required. Copies of all permits must be submitted to the COR upon receipt from local agency.

B. UTILITIES

The FBOP will provide water, use of restrooms and minimal electricity service (120V) for small hand power tools including battery chargers. The contractor will provide all other equipment, supplies and materials needed to complete this project.

C. HOUSEKEEPING AND MATERIAL DISPOSAL

The contractor awarded the contract will be responsible to ensure the premises are kept clean and free from accumulations of waste materials and rubbish at all times. The contractor will remove all debris, scrap, and rubbish from the work area daily. Surplus materials and all equipment shall be promptly removed from the site upon completion of the work. The Contractor shall be responsible to remove all debris and waste materials from the job site and placed in waste dumpsters that is provided by FCI Talladega upon conclusion and acceptance of the project.

G. SUBMITTALS

Submittals:

1. All security clearance paperwork/documentation shall be submitted to the COR a minimum of (14) working day prior to the start of work (see below).

2. The Contractor shall provide to the COR three (3) copies of the Safety Data Sheets (SDS) on all materials and substances that may be used during the course of the project. In the event the material is not approved by the Safety Manager, it shall be the responsibility of the Contractor to locate and procure an alternative product.

3. For security and safety purposes, forty-eight (48) hour advance notice in writing, prior to disruption to the system must be given to the Contracting Officer and COR.

4. Provide complete narrative descriptions of all materials.

5. Any deviations from this Statement Of Work will be considered an Change Order Request and must be authorized through the institution’s Contracting Officer prior to the implementation of the requested change.

6. It is the Contractor’s responsibility to repair and/or replace any Government property damaged by contractors/subcontractors employees. Damage will be corrected and restored to previous condition at no cost to the Government.

7. It shall be the Contractor’s responsibility for obtaining all measurements and data requirements to comply with manufacturer’s installation recommendations. All installations must be in accordance with product manufacture’s recommendations.

II. CONTRACTOR SECURITY/WORKING REGULATIONS

A. Work Hours:

Work Hours for the contractor are 7:00 AM – 3:30PM, Monday - Friday, excluding weekends and federal holidays. Any work required to be completed at any other time than noted above must be requested in writing to the COR five (5) working days prior to the start of the work. In the event of any equipment being replaced that would result in downtime of the normal orderly running of the institution, alternate work hours may be authorized in accordance with the time frame stated above.

Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight-hour work day. The Government assumes no responsibility to the Contractor nor to any of his subcontractors for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines.

Contractors should plan for a minimal amount of time accrued for security considerations, i.e., check-in screening, delay due to inmate movements, institution lock-down, institution emergencies, etc. In the event of an institution emergency, the Contractor will be instructed to secure all work, secure and stow all tools, equipment and materials, and the Contractor will be escorted out of the institution. Work will resume once the institution emergency passes.

B. Delivery of Materials:

All construction materials/equipment required for work on this project is required to be processed by the Contractor and coordinated with the institution COR for temporary storage.

Any construction related deliveries which are directly shipped to the contractor can be received between the hours of 7:00 a.m. to 12:00 p.m., Monday through Friday, excluding Federal Holidays. At no point will a Bureau of Prisons (BOP) staff member receive or sign for a delivery if the contractor or his representative is not present to verify and accept the delivery.

Under no circumstances will FCI Talladega or its staff be responsible for the acceptance of any Contractor or company deliveries. The contractor shall be responsible for providing their own means of loading and unloading contractor material or equipment.

The contractor shall not use the institution entry/driveway for the loading, unloading, or storage of any materials and equipment. The contractor will not impede/block the driveway at any time during or after the work shift.

C. Storage of Materials and Equipment:

All construction materials/tools shall be stored in a designated area mutually agreed upon between the COR and the contractor. The storage area will be a secure lockable gang box or similar, size to be determined by the contractor and the COR. If required, the contractor shall provide a securable, single point access storage container, such as a Job or Gang Box that will be left in the agreed upon storage area for the duration of the project. Size of the storage container will be determined by the contractor and the COR. The container will be secured using a padlock protocol with two locks to secure it. One shall be a contractor lock and the other lock provided by the institution. If necessary, a heavy duty chain provided by the contractor may be used to facilitate the locking requirement. All materials and equipment stored within the container will be maintained in a safe an orderly fashion

All tools will be inventoried prior to entering the institution and will be inventoried back in to ensure accurate accountability when exiting the institution at the end of each workday.

Materials cannot be stored at a height that would create a fall hazard. All tools will be inventoried prior to entering the Institution. At the start of each workday all tools will be inventoried out on a daily tool inventory sheet and at the end of the workday all tools will be inventoried back in to ensure accurate accountability of all tools at the end of each workday.

All contractor owned extension cords that will be used during the project, regardless of length, shall be in good condition with no broken outer Insulation. Extension cords are considered a “high risk” tool having a Federal Bureau of Prisons’ tool classification of Double A. All contractor owned extension cords used for this project will be required to exit the institution at the end of every workday for the duration of the project.

All contractor owned ladders approved for use within the institution, regardless of the size, shall be stored in a pre-determined area and secured to a stationary fixture with a heavy link chain and lock which would prevent removal.

D. Security Clearance/Contractor Badges:

The contractor shall provide the COR with all the necessary security clearance documents for all contractors and subcontractor employees accessing the institution and be security cleared for badging within 14 days of receiving the Notice to Proceed, as stated above. Security clearance documents will only be accepted from the prime contractor. If submitted by a sub-contractor, they will be rejected. It is the prime contractor’s responsibility to review security clearance submissions to ensure they are complete.

In the event a contractor or subcontractor employee cannot pass the security clearance process, it will be the contractor’s responsibility to provide another candidate. By law the BOP cannot, and will not, release any information to the contractor concerning the nature of why a contractors or subcontractor employee was not able to pass the security clearance process.

All contractors and subcontractor employees will provide a check list of all employees on site each day to the COR, verifying the number of workers on site each day and that all workers are approved to be on site.

E. Safety and Personal Protective Equipment:

All contractors and employees shall have and wear the required personal protective equipment (PPE) prescribed by industry standards at all times while on the job site. It is the responsibility of the contractor to provide all PPE equipment. All ladders regardless of the size shall be stored and secured to a stationary fixture with a chain and lock in a predetermined area, in a way that they cannot be removed. If ladders are required, immediately consult with the COR to ensure that he or she can make timely notification to appropriate institution staff. All extension cords regardless of length shall be in good condition with no broken outer insulation and will be secured in a locked construction gang box.

Should a system require Lock-out/Tag-out, the system will be required to have both Contractor and FCI Talladega locks on the isolation point to prevent shock. All Lock-out/Tag-out procedures will be in compliance with the institution Lock-out program.

F. Additional Considerations:

1. Contractors will NOT be allowed to bring cell phones, cameras or two way pagers into FCI Talladega. The Facilities Department maintains a digital camera that will be utilized by BOP staff to document the project work. The Contractor may request copies of these documentation photos for record keeping.

2. Contractor will be permitted to wear jeans in the institution, however, shorts, green or khaki-color clothing will not be allowed. The clothes will be proper and suitable for the services that are being provided.

3. Federal smoking policy on Federal property states that smoking is only allowed in outdoor designated areas. This policy will be strictly enforced.