The document is a bid tabulation spreadsheet for the Integrated Building Services (ISB) Parking Lot Renewal Project (FP-2024-03A) in Oregon, detailing a comprehensive parking lot reconstruction bid with six competing contractors. The project involves reconstruction of an existing asphalt parking lot, including removal of existing infrastructure, installation of new storm drainage systems, concrete curbs, sidewalks, and associated site improvements. The bid opening occurred on March 11, 2025 at 1 PM, with six contractors submitting detailed unit pricing across 28 line items, covering tasks such as mobilization, temporary traffic control, erosion control, excavation, aggregate base, concrete work, pavement markings, and utility modifications.

The bid tabulation reveals total construction costs ranging from $1,024,354 (lowest bidder R6 Contracting, Inc.) to $1,184,074.50 (highest bidder Mike Becker General Contractor), with a 10% construction contingency bringing the total estimated project cost to $1,363,698.60. The project includes significant quantities of work, such as 6,556 square yards of surface removal, 5,091 cubic yards of general excavation, 1,450 tons of aggregate base, and 960 tons of asphalt concrete pavement. Key infrastructure elements include 12 catch basins, 2 storm sewer manholes, 2,460 linear feet of concrete curbs, and 1,985 square feet of concrete walks, with the existing building remaining unchanged during the renovation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ISB Park Lot Bid Tabs

BID TABULATIONS
ISB Parking Lot Renewal
March 11, 2025 1PM
FP-2024-03A
Item No.Pay Item NameUnitQuantityEngineer's EstimateR6 Contracting, Inc.Eastern Oregon ContractingHigh Desert Aggregate & PavingGranite ConstructionMike Becker General Contractor
Unit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotal
0210-0100000AMOBILIZATIONLS1$55,000.00$55,000.00$80,000.00$80,000.00$105,288.50$105,288.50$166,000.00$166,000.00$101,000.00$101,000.00$45,000.00$45,000.00
0225-0101000ATEMPORARY WORK ZONE TRAFFIC CONTROL, COMPLETELS1$5,000.00$5,000.00$1,507.50$1,507.50$7,500.00$7,500.00$9,000.00$9,000.00$10,000.00$10,000.00$5,000.00$5,000.00
0280-0100000AEROSION CONTROLLS1$7,500.00$7,500.00$64,373.00$64,373.00$15,000.00$15,000.00$6,500.00$6,500.00$25,000.00$25,000.00$73,000.00$73,000.00
0280-0100000ACONSTRUCTION SURVEY WORKLS1$7,500.00$7,500.00$16,200.00$16,200.00$15,000.00$15,000.00$25,000.00$25,000.00$10,500.00$10,500.00$28,000.00$28,000.00
0310-0101000FREMOVAL OF PIPESFOOT30$30.00$900.00$21.50$645.00$95.00$2,850.00$25.00$750.00$14.00$420.00$20.00$600.00
0310-0101000FREMOVAL OF CURBSFOOT2,460$5.00$12,300.00$3.00$7,380.00$2.04$5,018.40$5.00$12,300.00

tc={1205780D-8BC4-49E7-947C-6DE1AECD4F5A}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Math Error Bid has $12,400 however 2,460*$5 is $12,400. Doesn’t alter bid rankings

$6.15$15,129.00$9.25$22,755.00
0310-0102000JREMOVAL OF WALKS AND DRIVEWAYSSQYD1,985$5.00$9,925.00$3.00$5,955.00$2.50$4,962.50$5.00$9,925.00$12.85$25,507.25$19.50$38,707.50
0310-0103000JREMOVAL OF SURFACINGSSQYD6,556$7.50$49,170.00$3.00$19,668.00$33.50$219,626.00$4.50$29,502.00$8.00$52,448.00$11.00$72,116.00
0310-0104000EREMOVAL OF INLETSEACH2$750.00$1,500.00$1,200.00$2,400.00$500.00$1,000.00$250.00$500.00$750.00$1,500.00$1,600.00$3,200.00
0310-0105000EREMOVAL OF MANHOLESEACH2$1,800.00$3,600.00$1,200.00$2,400.00$750.00$1,500.00$750.00$1,500.00$750.00$1,500.00$1,600.00$3,200.00
0310-0106000EREMOVAL OF STRUCTURES AND OBSTRUCTIONSEACH2$2,200.00$4,400.00$1,200.00$2,400.00$2,500.00$5,000.00$2,500.00$5,000.00$200.00$400.00$1,600.00$3,200.00
0320-0100000ACLEARING AND GRUBBINGLS1$2,500.00$2,500.00$10,720.00$10,720.00$2,000.00$2,000.00$5,000.00$5,000.00$1,600.00$1,600.00$4,100.00$4,100.00
0330-0105000KGENERAL EXCAVATIONCUYD5,091$20.00$101,820.00$15.00$76,365.00$19.65$100,038.15$33.00$168,003.00$17.00$86,547.00$20.00$101,820.00
0350-0101000JDRAINAGE GEOTEXTILE, TYPE 2SQYD6,767$4.00$27,068.00$2.50$16,917.50$2.25$15,225.75$3.00$20,301.00$1.60$10,827.20$2.00$13,534.00
0350-0105000JSUBGRADE GEOTEXTILESQYD6,556$5.50$36,058.00$2.50$16,390.00$2.25$14,751.00$3.00$19,668.00$1.15$7,539.40$2.00$13,112.00
0445-035008AF8 INCH STORM SEWER PIPE, 5 FT DEPTHFOOT324$65.00$21,060.00$33.00$10,692.00$48.00$15,552.00$60.00$19,440.00$77.00$24,948.00$35.00$11,340.00
0445-035010AF10 INCH STORM SEWER PIPE, 5 FT DEPTHFOOT36$75.00$2,700.00$134.50$4,842.00$75.00$2,700.00$70.00$2,520.00$132.00$4,752.00$80.00$2,880.00
0470-0104000ECONCRETE MANHOLES, STORM SEWER POLLUTION CONTROLEACH1$8,000.00$8,000.00$3,530.00$3,530.00$9,500.00$9,500.00$5,000.00$5,000.00$7,741.25$7,741.25$7,650.00$7,650.00
0470-0332000ECATCH BASINS, TYPE 3EACH12$2,500.00$30,000.00$2,804.50$33,654.00$3,100.00$37,200.00$1,750.00$21,000.00$3,640.33$43,683.96$3,150.00$37,800.00
0640-0100000MAGGREGATE BASETON1,450$48.00$69,600.00$28.50$41,325.00$28.40$41,180.00$39.00$56,550.00$51.50$74,675.00$45.00$65,250.00
0640-0100000M3" MINUS PIT RUN (CLASS D BACKFILL)TON8,300$50.00$415,000.00$26.50$219,950.00$13.00$107,900.00$25.00$207,500.00$30.00$249,000.00$24.00$199,200.00
0745-0622000MPG 64-28 IN LEVEL 2 ACPTON960$135.00$129,600.00$194.00$186,240.00$150.00$144,000.00$115.00$110,400.00$172.00$165,120.00$172.00$165,120.00
0755-0111000JREINFORCED CONCRETE PAVEMENT 6 INCHES THICKSQYD6$1,200.00$7,200.00$343.50$2,061.00$238.40$1,430.40$300.00$1,800.00$313.00$1,878.00$415.00$2,490.00
0759-0110000FCONCRETE CURBS, STANDARD CURBFOOT2,460$32.00$78,720.00$39.00$95,940.00$40.24$98,990.40$34.00$83,640.00$40.00$98,400.00$48.00$118,080.00
0759-0128000JCONCRETE WALKSSQFT1,985$20.00$39,700.00$18.50$36,722.50$10.95$21,735.75$18.00$35,730.00$25.00$49,625.00$22.00$43,670.00
0759-0150000KCONCRETE STAIRSEACH2$5,500.00$11,000.00$5,343.50$10,687.00$5,076.93$10,153.86$7,500.00$15,000.00$9,000.00$18,000.00$11,700.00$23,400.00
0759-0154100ENEW CURB RAMPSEACH5$2,250.00$11,250.00$531.50$2,657.50$1,639.81$8,199.05$500.00$2,500.00$2,700.00$13,500.00$900.00$4,500.00
0759-0510000JTRUNCATED DOMES ON NEW SURFACESEACH5$1,200.00$6,000.00$486.00$2,430.00$350.00$1,750.00$400.00$2,000.00$384.00$1,920.00$400.00$2,000.00
0860-0200000FLONGITUDINAL PAVEMENT MARKINGS - PAINTFOOT3,300$1.50$4,950.00$2.50$8,250.00$2.35$7,755.00$1.50$4,950.00$2.40$7,920.00$2.00$6,600.00
0867-0173000EPAVEMENT LEGEND, TYPE B: DISABLED PARKINGEACH6$400.00$2,400.00$607.50$3,645.00$400.00$2,400.00$600.00$3,600.00$530.00$3,180.00$500.00$3,000.00
0905-0100000AREMOVE EXISTING SIGNSEACH6$180.00$1,080.00$277.50$1,665.00$250.00$1,500.00$100.00$600.00$12.00$72.00$100.00$600.00
1040-0196000MROCK MULCHTONS95$75.00$7,125.00$40.50$3,847.50$80.00$7,600.00$40.00$3,800.00$85.00$8,075.00$100.00$9,500.00
1140-0100000F8 INCH POTABLE WATER PIPE, FITTINGS AND COUPLINGS WITH CLASS A BACKFILLFOOT470$85.00$39,950.00$34.50$16,215.00$48.00$22,560.00$65.00$30,550.00$78.00$36,660.00$55.00$25,850.00
PARKING LOT SIGNAGEEACH6$750.00$4,500.00$1,173.50$7,041.00$500.00$3,000.00$600.00$3,600.00$785.00$4,710.00$1,000.00$6,000.00
IRRIGATION SYSTEM MODIFICATIONSLS1$6,500.00$6,500.00$1,664.50$1,664.50$5,000.00$5,000.00$2,500.00$2,500.00$2,500.00$2,500.00$5,000.00$5,000.00
CURB-O--LETS, PRODUCT ID TCD4RD-NS DRAINGE STRUCTUREEACH9$850.00$7,650.00$472.50$4,252.50$500.00$4,500.00$800.00$7,200.00$500.00$4,500.00$950.00$8,550.00
RESET BIKE RACKLS1$1,500.00$1,500.00$832.50$832.50$1,500.00$1,500.00$500.00$500.00$600.00$600.00$750.00$750.00
PRIVATE UTILITY LOCATESLS1$10,000.00$10,000.00$481.50$481.50$2,500.00$2,500.00$2,500.00$2,500.00$750.00$750.00$5,000.00$5,000.00
EXPLORATORY UTILITY POTHOLINGEACH5$481.50$2,407.50$600.00$3,000.00$500.00$2,500.00$350.00$1,750.00$500.00$2,500.00
10" C-900 CULVERT AT GRAVEL ACCESS ROADFOOT20$0.00$0.00$60.00$1,200.00$0.00$0.00
CONSTRUCTION SUBTOTAL =$1,239,726.00$1,024,354.00$1,076,366.76$1,105,529.00$1,173,878.06$1,184,074.50
Construction Contingency (10%)$123,972.60
TOTAL CONSTRUCTION =$1,363,698.60

$159,720.50 105% 108% 115% 116%

Math Error Bid has $12,400 however 2,460*$5 is $12,400. Doesn’t alter bid rankings image1.png