FOUO C04.0 N4523A20R1058 Attachment J-2 Price Proposal Worksheet.xls

XLS spreadsheet 59 KB Posted

Attached to
Docking and Maintenance of 2 YC Barges
Solicitation number
N4523A20R1058
Issued by

About this file

This document contains a price proposal worksheet and description of a federal contract opportunity for docking and maintenance of two yard craft barges. The Regional Maintenance Center at Puget Sound Naval Shipyard & Intermediate Maintenance Facility intends to award a firm-fixed-price contract to a HUBZone small business to accomplish maintenance, repair, and preservation of Yard Craft Barge 1645 and 1646 at the contractor's facility between July and September 2020. Work will include docking, cleaning, blasting, and preserving the vessels' exterior surfaces; removing, cleaning, and remounting fendering rubber and fasteners; air testing and preserving interior steel half pipe fenders; spot preserving tanks and voids; replacing zinc anodes; preserving manhole covers and hatches; UT testing of hull and main deck plating; VT inspection of hull, decks, tanks, and voids for damage and deterioration; removing handrail brackets; and applying new non-skid to main decks. The solicitation number is N4523A20R1058 and award is anticipated in April 2020 to the responsible contractor with the lowest price meeting technical acceptability.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

vessel name

INSERT CONTRACTOR/COMPANY NAME HERE
Project =YC-1645 & 1646DATE: =
PRIMESUBCONTRACTORPRIMEPRIME
PARAGRAPH No.TITLEM/HMATERIAL PRICETOTALLabor CostMaterial CostTOTALOther Direct Cost (ODC)*G&APROFITLine Item Total
1.4Arrival Conference$0.00$0.00$0.00$0.00$0.00
1.5Required Documents$0.00$0.00$0.00$0.00$0.00
1.6Progress Meetings$0.00$0.00$0.00$0.00$0.00
1.7Availability Requirements$0.00$0.00$0.00$0.00$0.00
1.7.1Transport Vessels$0.00$0.00$0.00$0.00$0.00
1.8Care of Vessel$0.00$0.00$0.00$0.00$0.00
1.11CFR Reports$0.00$0.00$0.00$0.00$0.00
1.13Safety Requirements$0.00$0.00$0.00$0.00$0.00
1.16.1Preservation OQE$0.00$0.00$0.00$0.00$0.00
1.17Environmental/Hazwaste Management$0.00$0.00$0.00$0.00$0.00
1.21Gas Free$0.00$0.00$0.00$0.00$0.00
1.22Develop & Maintain Test Plan$0.00$0.00$0.00$0.00$0.00
3.1.1Personnel & Equipment$0.00$0.00$0.00$0.00$0.00
3.1.2Docking Procedures$0.00$0.00$0.00$0.00$0.00
3.1.3Blocking Plan$0.00$0.00$0.00$0.00$0.00
3.1.4Shifting the Vessel$0.00$0.00$0.00$0.00$0.00
3.1.5Setting and Aligning Blocks$0.00$0.00$0.00$0.00$0.00
3.1.6Docking Conference$0.00$0.00$0.00$0.00$0.00
3.1.7Docking the Vessel$0.00$0.00$0.00$0.00$0.00
3.1.8Post Docking$0.00$0.00$0.00$0.00$0.00
3.1.9Undocking the vessel$0.00$0.00$0.00$0.00$0.00
3.1.11Final Docking Report$0.00$0.00$0.00$0.00$0.00
3.2.1Identify Distinguishing Figures and Markings$0.00$0.00$0.00$0.00$0.00
3.2.2Rubber Fenders$0.00$0.00$0.00$0.00$0.00
3.2.3Zinc Replacement$0.00$0.00$0.00$0.00$0.00
3.2.4Hull Blasting and Preservation$0.00$0.00$0.00$0.00$0.00
3.2.5Hull & FB Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.2.6Hull & FB U/T Inspection$0.00$0.00$0.00$0.00$0.00
3.2.725 UT Tests$0.00$0.00$0.00$0.00$0.00
3.4.1Open, Pump, Clean, Vent, Gas Free, Close all tanks$0.00$0.00$0.00$0.00$0.00
3.4.2Tank/ Void Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.4.3Identify Color Schemes and Markings$0.00$0.00$0.00$0.00$0.00
3.4.4Preliminary Air Test$0.00$0.00$0.00$0.00$0.00
3.4.5Tank/ Void Preservation$0.00$0.00$0.00$0.00$0.00
3.4.6Access Cover Preservation$0.00$0.00$0.00$0.00$0.00
3.4.7Final Air Test$0.00$0.00$0.00$0.00$0.00
3.4.8Tank Close-out Inspection$0.00$0.00$0.00$0.00$0.00
3.5.1Main Deck Non-skid Preservation$0.00$0.00$0.00$0.00$0.00
3.5.2Main Deck Visual Inspection$0.00$0.00$0.00$0.00$0.00
3.5.3Main Deck U/T Inspection$0.00$0.00$0.00$0.00$0.00
3.5.420 UT Tests$0.00$0.00$0.00$0.00$0.00
3.5.5Remove Handrail Hinges and Base Supports$0.00$0.00$0.00$0.00$0.00
Reservation Tasking
Column Totals0$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
Scope (SOW/PWS)Labor Rate/MH:G&A Rate:Profit Rate:
Total Bid:$0.00

&C********DOLLAR ENTRIES ARE AUTOMATICALLY ROUNDED UP TO THE NEAREST WHOLE DOLLAR********* =MH*Labor Rate*G&A =(Prime Material Price+Subcontractor Total)*Profit Rate =SUM(Prime Total+Subcontractor Total+ODC+G&A+Profit) =(MH*Labor Rate)+Material Price =Sub Cost (F) *ODC-Defined as anything other than labor, subcontracts, and/or material that is directly attributable to a contract per FAR 31.202. Examples include rental charges and travel etc.

NOTE: Please fill in within the yellow highlighted boxes, the fixed labor rate, proposed G&A and proposed Profit rates.

NOTE: Labor rates and Profit rates used to calculate for the overall price of the base contract award shall be the basis for pricing on all modifications under this contract.