This document is a Form C Pricing Request for RFP 106-23 Battery Monitor & Sensor, issued by the Massachusetts Bay Transportation Authority (MBTA). The MBTA is requesting lump sum pricing for battery monitor and sensor equipment and installation across 10 substation locations in Massachusetts. Bidders must provide pricing for labor, equipment and materials, general conditions, overhead and profit for each substation location. The MBTA requires that work be completed in a specific order starting with Lincoln Switching, with each substation required to be substantially complete before beginning the next. The MBTA reserves the right to reject any bid if one or more individual items are left blank.

The pricing terms indicate that payment will be substantially complete at 90% and final acceptance at 100%. The MBTA requires that all quoted prices be inclusive of ancillary charges such as reporting, administration, prevailing wages, bonding, transportation, and other associated costs. The total bid price is requested to be provided as a single lump sum amount.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

FORM C: Price Request, submit spreadsheet with bid, not hand written. RFP 106-23 Battery Monitor & Sensor
Vendor to complete green cells - Total will auto calculate
Vendors Name
LineSUBSTATIONLaborEquipment & MaterialsGeneral Conditions, Overhead & ProfitTotal BID PRICE PER LOCATION 2
1LINCOLN SWITCHING 1$ - 0$ - 0$ - 0$ - 0
2NORTH QUINCY$ - 0$ - 0$ - 0$ - 0
3WOLLASTON$ - 0$ - 0$ - 0$ - 0
4QUINCY CENTER$ - 0$ - 0$ - 0$ - 0
5HIGH STREET$ - 0$ - 0$ - 0$ - 0
6KENMORE$ - 0$ - 0$ - 0$ - 0
7DEWEY$ - 0$ - 0$ - 0$ - 0
8WASHINGTON VILLAGE$ - 0$ - 0$ - 0$ - 0
9COLUMBIA$ - 0$ - 0$ - 0$ - 0
10CABOT$ - 0$ - 0$ - 0$ - 0
11Basis of Award (lines 1-10)$ - 0
12LAPTOPS Option$ - 0
13TOTAL BID PRICE$ - 0

NOTES:

1. Payment: Substantially complete 90%, Final acceptance 100%. Each substation must be substantially complete before beginning the next substation work.

Lincoln Switching to be the first substation for work.

2. Bidders are required to quote Lump Sum Costs per location. All quoted prices shall be inclusive of ancillary charges including but not limited to reporting, administration, prevailing wages, general conditions, overhead & profit, bonding, tooling, equipment, transportation costs, customs, duty charges, and other associated charges. Bidders shall quote only on goods and services in strict accordance with the specifications / requirements. Bidders must fill in each individual item. The MBTA reserves the right to reject any bid if one or more individual item is left blank.