This is a price form for the MBTA Emergency Generator Inspection, Testing, Maintenance and Repair RFP No. 149-26, administered through COMMBUYS with Bid No. BD-27-1206-40000-40000-134987. The contract requires bidders to provide monthly unit pricing for various categories of generators and related equipment, including permanent diesel generators (ranging from 150 kW to greater than 500 kW), portable generators (60 kW to greater than 500 kW), and light towers. Section A establishes unit-month pricing across five contract years, with Year 1 serving as the base and Years 2–5 as optional renewal periods. The form identifies a total of 110 unit-months of service to be priced in the base year, with separate pricing columns provided for each contract year option.

The pricing structure comprises three components: monthly unit prices for base-scope work including covered repairs (Section A), hourly rates for major repairs and additional work including labor by Massachusetts-licensed electricians, generator technicians, and gas fitters during both normal and outside normal hours (Section B), and a markup percentage on parts and materials for repairs and additional work estimated at $100,000 annually (Section C). Bidders must complete all yellow cells to ensure a complete price quote. The form notes that hourly rates are estimated and will be paid on actual hours worked, with extended annual prices calculated by multiplying unit quantities or estimated hours by the respective rates. A summary section totals pricing by contract year and calculates the total bid price across all five years.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Form

FORM XX – PRICE FORM

tc={24084D1D-44BF-4390-B18A-D1B06375E1FA}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Enter the correct number – replacing XX

MBTA Emergency Generator Inspection, Testing, Maintenance and Repair
RFP No.:149-26Legend:
COMMBUYS Bid No.:BD-27-1206-40000-40000-134987Bidder enters
Bidder Name:
Bidder Address:Calculated – do not edit
Authorized Signatory (name / title):See Instructions tab before completing.
Signature / Date:
SECTION A – MONTHLY UNIT PRICES (all base-scope work in SOW Section 2, including Covered Repairs)
Monthly Unit Price per Unit ($)Extended Annual Price = Qty × Unit Price × 12 ($)
ItemDescriptionUnitQty of Units

tc={B3FA7D21-7AA9-4C65-9775-87D6E4815B6C}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Please checkYear 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)
A1Permanent generator, diesel, ≤ 150 kWUnit-month29-----
A2Permanent generator, diesel, 151–300 kWUnit-month33-----
A3Permanent generator, diesel, 301–500 kWUnit-month15-----
A4Permanent generator, diesel, > 500 kWUnit-month7-----
A5Portable generator, ≤ 60 kWUnit-month9-----
A6Portable generator, 61–500 kWUnit-month7-----
A7Portable generator, > 500 kWUnit-month1-----
A8Light towerUnit-month9-----
Total Section A110-----
SECTION B – HOURLY RATES for Major Repairs and Additional Work (SOW 2.6–2.8); fully burdened, incl. travel, vehicle, tools
Hourly Rate ($)Extended = Est. Hours × Rate ($)
ItemDescriptionUnitEst. Hours per Year

tc={A309C927-1A8C-4D57-BCF1-204CC4A6889D}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Please update the estimated hours based on historical use or best guess?Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)
B1Massachusetts-licensed electrician – Normal HoursHour300-----
B2Massachusetts-licensed electrician – Outside Normal HoursHour100-----
B3Generator technician – Normal HoursHour400-----
B4Generator technician – Outside Normal HoursHour150-----
B5Massachusetts-licensed gas fitter – Normal HoursHour40-----
B6Massachusetts-licensed gas fitter – Outside Normal HoursHour10-----
B7Special Event standby technician (any hour)Hour200-----
Total Section B-----
SECTION C – MARKUP on parts and materials for Major Repairs and Additional Work (applied to Contractor invoice cost)
Markup (%)Extended = Est. Materials × Markup ($)
ItemDescriptionUnitMBTA Est. Materials per Year ($)Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)
C1Markup on parts and materials (single percentage per year; covers handling, procurement, overhead and profit)Percent$100,000

tc={6B1BC54E-3646-4343-9911-1A9F3A29AC35}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Please update – this is just a place holder tc={A309C927-1A8C-4D57-BCF1-204CC4A6889D}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Please update the estimated hours based on historical use or best guess?

tc={B3FA7D21-7AA9-4C65-9775-87D6E4815B6C}: [Threaded comment]

Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924

Comment:

Please check-----
SUMMARY – BASIS OF AWARD
Year 1 (Base)Year 2 (Option 1)Year 3 (Option 2)Year 4 (Option 3)Year 5 (Option 4)
Section A – Monthly Unit Prices-----
Section B – Hourly Rates-----
Section C – Markup-----
Total per Contract Year-----
TOTAL BID PRICE (sum of Years 1 through 5)-
Notes:
1. The bidder must fill all yellow cells in order to ensure complete price quote.
2. Hourly rates are estimated and shall be paid on actual hours worked.

Enter the correct number – replacing XX

Please check

Please update the estimated hours based on historical use or best guess?

Please update – this is just a place holder