fn1457-18_amend_1.docx

DOCX document 31 KB Posted

Attached to
CONSTRUCTION PROJECTS
Solicitation number
FN1467-19
Issued by

About this file

FN1467-18 Amendment 1

View the file

Other files

File Type Posted
fn1467-18_amend_2.docx DOCX document
WAGE_GRADE_RATES_CORRECTED.pdf PDF
wage_grade_rates.pdf PDF
UNICORACH.pdf PDF
NCIC_FORM.pdf PDF
FN1467-19__UNICOR_ALLENWOOD_CONSTRUCTION_PROJECTS.pdf PDF
sf_1449_fn1467-19_ALLENWOOD_CONSTRUCTION_PROJECT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/ MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

4. REQUISITION/PURCHASE REQ. NO.

5. PROJECT NO. (If applicable)

AMENDMENT #1
11/08/2018

6. ISSUED BY

CODE

7. ADMINISTERED BY (If other than Item 6)

See Block 6

8. NAME AND ADDRESS OF CONTRACTOR (No., street, country, State and Zip Code)

(x)

9A. AMENDMENT OF SOLICITATION NO.

FN1467-18

X

9B. DATED (SEE ITEM 11)

02/ x

11/02/2018

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENT OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and the date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE

DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X)

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, Appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF :

D. OTHER (Specify type of modification and authority)

E. IMPORTANT : Contractor is not, x is required to sign this document and return 2 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

COMMODITY: Construction Projects SEE ATTACHED

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Tiffani Balestrini, Contract Specialist

15B. CONTRACTOR/OFFEROR

15C. DATE SIGNED

16B. UNITED STATES OF AMERICA

16C. DATE SIGNED

BY

(Signature of the person authorized to sign)

(Signature of contracting officer)

NSN 7540-01-152-8070

PREVIOUS EDITION UNUSABLE

30-105

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR(48 CFR) 53.243

This amendment hereby addresses issues and answers questions brought up at the site visit for LOT 2 FCI UNICOR FACTORY/Finishing Room Restoration.

1. There are 19 vents that go to the roof. Once they are removed you will be responsible for making steel plates ¼ inch thick and welding them in place to cover the hole on the inside of the building.(Each vent 19 of them) All the vents on the roof top will be removed also. After the roof top vents are removed you will be responsible for anything needed to weather proof and seal the roof top, to eliminate the possibility of any leaks.

2. The roof is a rubber roof.

3. All openings in the roof will need to be welded closed prior to leaving for the day. There will be no open roof areas at the end of a work day.

4. After roof vents are removed from the roof area, they will be loaded into an enclosed trailer for removal. It will be the responsibility of the successful offeror to find the best way to remove the vents from the roof and load into trailer.

5. There will be no inmate labor available during this project. All labor must be completed by the successful offerors work force.

6. There will be removal of all finishing booths gas lines and furnaces. At time of completion the only items remaining in finishing room will be blue air lines, lights, roof drains, support beams and steam lines.

7. Please keep in mind that if the institution is under fog restrictions, the successful offeror will not be able to gain access to the institution until the fog restrictions are lifted.

8. The finishing room track will be removed and filled with concrete. Any other “rough” areas on the flooring will smoothed down to create a smooth consistent surface across the entire floor.

9. It is the suggestion of UNICOR that the successful offeror have eight (8) trailers to have four (4) in the factory at a time, and be replaced by four (4) empty trailers. When full trailers are removed, empty trailers can be brought in at that time. If a full trailer is removed it will not be able to be emptied and brought back in.

10. The dock at FCI Allenwood is a four (4)’ high. This will need to be considered in the delivery of concrete to repair the finishing room floor.

11. The successful offeror will be allowed to have one (1) open top container for the removal of concrete only. This dumpster will be pulled at 5:00 am and it is the contractor’s responsibility to arrange for the pick up of this dumpster, and exchange with an empty dumpster.

Davis Bacon Wage Grades are posted as part of the amendment.

Closing date for additional questions for either Lot 1 UNICOR Warehouse repairs or Lot 2 UNICOR Factory repair/restoration will be 12:00 noon Tuesday, November 13, 2018. At this time one additional amendment will be posted to answer any additional questions.

Closing date for submission of offerors will be Monday November 19, 2018 at 2:00 pm EST.

Except as provided herein, all other terms and conditions remain unchanged.