This document is a Request for Qualifications (RFQ) for a task order under the VISN 8 Architectural and Engineering (AE) Multiple Award Task Order Contract (MATOC). The Department of Veterans Affairs is seeking professional AE services to design the replacement of the emergency generators, controls, and fuel polishing system at the C.W. Bill Young VA Medical Center in Bay Pines, Florida, under Project Number 516-25-605.

The project involves replacing the existing 600 kW generators and related equipment in Building 100, including the paralleling switchgear and diesel fuel polishing system. The AE firm must have specialized experience in designing emergency power and fuel delivery systems for healthcare facilities. The contract has a 224-calendar day period of performance and is set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs). The estimated construction cost range is between $5-10 million. Qualifications submissions are due by September 16, 2024, and the contract will be awarded based on the most highly qualified firm.

View the file

Other files

File Type Posted
Architectural Plan 1-page.pdf PDF
36C24824R0155.docx DOCX document
AE Interview Questions 08-19-2024 1-Page.docx DOCX document
SOW 08-19-2024 88-Pages.docx DOCX document
Campus Map 1-page.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHABAYBYRNEG

Text Box APPROXIMATE LOCATION OF EXISTING 4-30k gal UNDER GROUND TANKS. INSTALLED 2011. TANK #2 FEEDS THE GENERATOS.

VHABAYBYRNEG

Text Box APPROXIMATE LOCATION OF EXISTING 4-40k gal UNDER GROUND TANKS. INSTALLED 2015.

VHABAYBYRNEG

Polygon

VHABAYBYRNEG

Polygon

VHABAYBYRNEG

Callout REMOVE 5 EXIST 600kw GENERATORS AND CONTROLS AND REPLACE W 5 NEW 750kw GENERATORS AND CONTROLS.

VHABAYBYRNEG

Text Box

TEMPORATY EMERGENCY GENERATOR LOCATION?

VHABAYBYRNEG

Rectangle

VHABAYBYRNEG

Callout

REMOVE EXIST ALARM PANEL AND REPLACE WITH NEW.

VHABAYBYRNEG

Callout INSTALL FUEL POLISHING SYSTEM. CAPTURE EXIST FUEL LINE TO BOILER PLANT IN NEW SYSTEM.

VHABAYBYRNEG

Text Box 2017 07 21 gjb