7. Bid Schedule 2024 Repair Runway 14-32 Phase 3,Rev1.xlsx
XLSX spreadsheet 546 KB Posted
- Attached to
- REPAIR RUNWAY 32 PAVEMENT PHASE 3
- Solicitation number
- FJXT220010
About this file
This document is a bid schedule spreadsheet for a federal contract opportunity to repair Runway 14/32 at Dover Air Force Base. The project involves milling and repaving 2,100 linear feet of the runway, crack sealing the shoulders, and restriping the pavement markings. The spreadsheet provides a template for the contractor to input labor and material costs across various divisions of work. The contractor is instructed to complete the labor and material estimates, as well as provide their overhead, profit, and risk/bonding rates. This information will automatically populate the summary page to provide the total contract price. The solicitation is for the Department of the Air Force's Air Mobility Command, with a project location at Dover Air Force Base in Delaware. No design has been completed, so the contract is being procured under a preliminary design basis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1. SOW FY24 Repair Runway 14-32 Phase 3 Revision 1.pdf | ||
| 2. Bid Schedule.docx | DOCX document | |
| 3. SFS ACL template.docx | DOCX document | |
| Solicitation - FA449724R0014.pdf | ||
| 1. SOW, Design new wash rack for AGE units, B779.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions Use the information from the prefilled division sheets below to complete the 50 Divisions Cost Estimate CSI* Format tool to build your proposal. The information from the prefilled division sheets may not be all inclusive. The contractor is allowed to include any missing items from each division and is allowed to fill in other divisions that are not listed in the prefilled division sheets. If there is a disagreement with the prefilled division sheets, the contractor should not delete the element(s), but instead leave it blank and then include their suggested element(s) at the bottom of that division tab. Please note that on the summary page there is a place to fill in overhead and profit percentages for both the prime and the subcontractor that will self-populate the summary page and all the division tabs.
Exceptions:
(1) if each subcontractor has a different overhead and profit rates than the percentage placed on the summary page, an adjustment will have to be made to that specific division page. The spreadsheet will still calculate correctly.
(2) If the prime is self-performing the work for that division then the profit and overhead will need to be zeroed for that particular division, because the primes overhead and profit is already captured on the summary page.
The ktr is required to complete the areas marked "Fill Here" in the summary tab. The rest of the information in the summary tab will automatically tabulate from the individual division tabs except for the few exceptions listed above.
Divisions 1, 2, and 3 show sample inputs to illustrate how the spreadsheet works.
* CSI = Construction Specifications Institute
&"Verdana,Bold"Construction Cost Estimate
&P of &N
Summary
| BID SCHEDULE | Date: | |
| 7-Mar-24 | ||
| COMPANY | ||
| 436th Civil Engineering |
| PROJECT | ||||
| Repair Runway 14/32 Phase 3 | ||||
| LOCATION | PROJECT NO. | FJXT 220010 | ||
| DOVER AIR FORCE BASE, DE | ||||
| DIVISION | DESCRIPTION | % by | ||
| Division | Division Total |
| DIVISION 01 | GENERAL REQUIREMENTS | ERROR:#DIV/0! | - 0 | |
| DIVISION 02 | EXISTING CONDITIONS | ERROR:#DIV/0! | - 0 | |
| DIVISION 03 | CONCRETE WORK | ERROR:#DIV/0! | - 0 | FILL IN AS REQUIRED (this will link to the entire document) |
davisjam: davisjam:
Percentages listed are place fillers. Please complete as required
| DIVISION 04 | MASONRY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 05 | METALS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 06 | WOOD, PLASTICS AND COMPOSITES | ERROR:#DIV/0! | - 0 | GC Overhead | |
| DIVISION 07 | THERMAL AND MOISTURE PROTECTION | ERROR:#DIV/0! | - 0 | GC Profit | |
| DIVISION 08 | OPENINGS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 09 | FINISHES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 10 | SPECIALTIES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 11 | EQUIPMENT | ERROR:#DIV/0! | - 0 | Risk/Bonding | |
| DIVISION 12 | FURNISHINGS | ERROR:#DIV/0! | - 0 | Design | |
| DIVISION 13 | SPECIAL CONSTRUCTION | ERROR:#DIV/0! | - 0 | This spreadsheet contains many formulas... please save a copy prior to editing in case you make a mistake. All shaded areas are either linked or contain formulas | |
| DIVISION 14 | CONVEYING EQUIPMENT | ERROR:#DIV/0! | - 0 | ||
| DIVISION 15 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 16 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 20 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 21 | FIRE SUPRESSION | ERROR:#DIV/0! | - 0 | ||
| DIVISION 22 | PLUMBING | ERROR:#DIV/0! | - 0 | 2 | |
| DIVISION 23 | HEATING, VENTILATING AND A/C | ERROR:#DIV/0! | - 0 | 2 | |
| DIVISION 24 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 25 | INTEGRATED AUTOMATION | ERROR:#DIV/0! | - 0 | 0 | |
| DIVISION 26 | ELECTRICAL | ERROR:#DIV/0! | - 0 | ||
| DIVISION 27 | COMMUNICATIONS | ERROR:#DIV/0! | - 0 | Select Area Cost Factor Type: | |
| DIVISION 28 | ELECTRONIC SAFETY AND SECURITY | ERROR:#DIV/0! | - 0 | ||
| DIVISION 29 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 30 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 31 | EARTHWORK | ERROR:#DIV/0! | - 0 | ||
| DIVISION 32 | EXTERIOR IMPROVEMENTS | ERROR:#DIV/0! | - 0 | ||
| DIVISION 33 | UTILITIES | ERROR:#DIV/0! | - 0 | ||
| DIVISION 34 | TRANSPORTATION | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 36 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 37 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 38 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 39 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 46 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| DIVISION 47 | RESERVED | ERROR:#DIV/0! | - 0 | ||
| ERROR:#DIV/0! | - 0 | ||||
| DIVISION 49 | RESERVED | ERROR:#DIV/0! | - 0 |
HARD COST TOTAL ERROR:#DIV/0! - 0
| PRIME GENERAL CONTRACT OFFICE OVERHEAD (Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| PRIME GENERAL CONTRACTOR'S PROFIT(Fill in%) | 0% | - 0 |
| SUBTOTAL | - 0 | |
| 0.00% | - 0 | |
| SUBTOTAL | - 0 | |
| BUILDER'S RISK / PERFORMANCE BONDS (Fill in%) | - 0 | |
| CONTRACT TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Sustainment Repair/Const ACF Already Factored
UFC 3-701-01
Table 4-4: Operation and Maintenance Escalation Rates
| Budget Guidance | Projected | ||
| FY | Annual Escalation Rate | End of Fiscal Year | Escalation Factor |
| (Note 1) | (Note 2) | ||
| 2019 | 1.0000 | ||
| 2020 | 2.00% | 2020 | 1.0200 |
| 2021 | 2.00% | 2021 | 1.0404 |
| 2022 | 2.00% | 2022 | 1.0612 |
| 2023 | 2.00% | 2023 | 1.0824 |
| 2024 | 2.00% | 2024 | 1.1041 |
| 2026 | 2.00% | 2025 | 1.1262 |
| Note 1: Annual Inflation Guidance rates for military construction budget authority published by USD (Comptroller) on 16 December 2019. | |||
| Note 2: Use these factors to adjust plant replacement value to the target year. |
| AREA COST FACTOR | SUSTAINMENT ACF | |
| DOVER AFB SITE #1 | 11% | 13% |
Div1
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | EQUIPMENT | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| GENERAL REQUIREMENTS | |||||||
| Site Superintendent | 60 | HR | - 0 | - 0 | - 0 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | ||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div2
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXISTING CONDITIONS | |||||||
| LS |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| FY Escalation Rate | 0.00% | - 0 | |
| Dover Area Cost Factor | 0.00% | - 0 | |
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div3
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONCRETE WORK | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div4
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| MASONRY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div5
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| METALS |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| FY Escalation Rate | 0.00% | - 0 | |
| Dover Area Cost Factor | 0.00% | - 0 | |
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div6
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| WOOD, PLASTICS AND COMPOSITES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div7
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| THERMAL AND MOISTURE PROTECTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div8
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| OPENINGS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div9
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FINISHES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div10
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIALTIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div11
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div12
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FURNISHINGS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div13
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| SPECIAL CONSTRUCTION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div14
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| CONVEYING EQUIPMENT | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div15
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div16
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div20
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div21
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| FIRE SUPRESSION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div22
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| PLUMBING | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div23
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| HEATING, VENTILATING AND A/C | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div24
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div25
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| INTEGRATED AUTOMATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div26
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRICAL |
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| FY Escalation Rate | 0.00% | - 0 | |
| Dover Area Cost Factor | 0.00% | - 0 | |
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div27
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| COMMUNICATIONS | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div28
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| ELECTRONIC SAFETY AND SECURITY | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div29
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div30
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div31
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EARTHWORK |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| - 0 | - 0 | - 0 | |
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |
| SUBTOTAL | - 0 | ||
| 0.00% | - 0 | ||
| FY Escalation Rate | 0.00% | - 0 | |
| Dover Area Cost Factor | 0.00% | - 0 | |
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div32
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 240004 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| EXTERIOR IMPROVEMENTS | |||||||
| Pavement Milling | 70000 | SY-IN | - 0 | - 0 | - 0 | ||
| Sawcutting | 9000 | LF-IN | - 0 | - 0 | - 0 | ||
| Hot-laid Biituminous Concrete PG 76-22 | 3920 | SY-IN | - 0 | - 0 | - 0 | ||
| Pavement Markings | 18360 | LF | - 0 | - 0 | - 0 | ||
| Crack Sealing Bituminous Pavement | 24240 | SY | - 0 | - 0 | - 0 | ||
| Groove Asphalt Paving | 35000 | SY | - 0 | - 0 | - 0 | ||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| - 0 | |||||||
| - 0 | |||||||
| - 0 | |||||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div33
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| UTILITIES | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div34
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| TRANSPORTATION | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div35
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| RESERVED | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div36
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div37
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div38
| BID SCHEDULE | DATE | |||
| 45,358.00 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div39
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div40
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div41
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div42
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div43
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div44
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div45
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| 0 | |||||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| - 0 | - 0 | - 0 | |||||
| TOTAL LABOR/MATERIALS | - 0 | - 0 | |||||
| SUBTOTAL | - 0 | ||||||
| 0.00% | - 0 | ||||||
| FY Escalation Rate | 0.00% | - 0 | |||||
| Dover Area Cost Factor | 0.00% | - 0 | |||||
| TOTAL | $ - 0 |
&"Verdana,Bold"Construction Cost Estimate
Div46
| BID SCHEDULE | DATE | |||
| March 7, 2024 | ||||
| PROJECT | BASIS FOR ESTIMATE | |||
| Repair Runway 14/32 Phase 3 | CODE A (No design completed) | |||
| LOCATION | CODE B (Preliminary design) | |||
| DOVER AIR FORCE BASE, DE | CODE C (Final design) | |||
| COMPANY | PROJECT NO. | OTHER (Specify) | ||
| 436th Civil Engineering | FJXT 220010 | |||
| DRAWING NO. | ESTIMATOR | CHECKED BY |
| QUANTITY | LABOR | MATERIAL | |||||
| ITEM DESCRIPTION | NO. UNITS | UNIT MEAS. | PER UNIT | TOTAL | PER UNIT | TOTAL | TOTAL COST |
| RESERVED | |||||||
| - 0 | - 0 | - 0 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .