This Statement of Objectives (SOO) outlines requirements for completing an Anechoic Chamber fire suppression system installation at Building 90 on Eglin Air Force Base. The existing system is already plumbed and charged with agent but requires final connection, commissioning, and training.

The contractor must connect the fire suppression control panel to building power, integrate it with the existing building alarm system, ensure HVAC damper closure before agent release, commission and program the system, conduct testing for fire marshal approval (without agent release), provide operational training and manuals, and ensure compatibility with existing hardware. Key requirements include completion within 30 days of award, 12-month warranty coverage, and compliance with UFC 3-600-1, NFPA 13, NFPA 72, and relevant NFPA codes. The work is being solicited as a small business set-aside under NAICS 561210 with quotes due by January 21, 2025, 09:00 AM CST. A site visit opportunity is available for interested contractors, with RSVP required by January 2, 2025.

View the file

Other files

File Type Posted
(1)COMBO Fire Supression_Redacted.pdf PDF
(1)Site Visit Instructions B90_Redacted.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Objectives for Anechoic Fire Suppression completion

BACKGROUND: procured and installed an Anechoic Chamber into building 90 on Eglin Air Force Base. As part of the chamber, a fire suppression system was installed but the final connection, commissioning of the system and the training was not completed.

Fire suppression system is plumbed and charged with agent.

A site visit will be allowed for contractors wishing to bid on this effort.

REQUIREMENTS:

1. Contractor shall connect the Fire Suppression control panel to building power.

2. Contractor shall integrate the existing fire suppression system into the existing building Alarm, Supervisory, and Trouble system.

3. Contractor shall ensure that HVAC dampers close prior to release of fire suppression agent.

4. Contractor shall commission and program the fire suppression system.

5. Contractor shall perform a pre-test without the fire marshal; contractor shall then perform a final test for fire marshal approval. This requirement will not be considered satisfied until the fire marshal approves the system for operation. These test will not allow release of fire suppression agent.

6. Contractor shall provide training on the operations of the fire suppression system.

This training will include leave behind operations manuals.

7. Contractor shall provide specifications in the quote for any hardware utilized in this effort.

8. All work performed under this contract shall be 100% compatible with the existing installed hardware.

9. Work shall be performed within 30 days of contract award.

10. Contractor shall provide a 12-month warranty assuming normal usage and maintenance processes are followed.

Contractor is expected to provide all materials and labor for the performance of this contract. All work must be IAW UFC 3-600-1, NFPA 13, NFPA 72, and all current and relevant NFPA Codes.

13 December 2024