This is a Project Description and Solicitation Requirements document issued by the City of Jesup, Georgia for design-build services to construct a crew quarters addition to Jesup Fire Department Station No. 1. The City seeks a single design-build entity to design and construct a new crew quarters building of approximately 3,200 gross square feet (80 feet by 40 feet), single-story, connected to the existing station by an enclosed 12-foot by 12-foot connector. The project includes design and construction of the building foundation with in-slab plumbing and a metal building with brick facade; all interior construction and remaining MEP work will be performed by the City. The project is located at 411 West Bay Street, Jesup, Georgia, where the existing station was constructed in 1977. The conceptual program includes eight bedrooms, four bathrooms, one combined day room and kitchen, one laundry facility, two storage rooms, one riser room for fire sprinklers, and required corridors. Written questions for Phase 1 were due October 16, 2026; Phase 1 Statements of Qualifications were due October 19, 2026; Phase 2 proposals are due October 29, 2026; and City Commission award is scheduled for November 3, 2026, with Notice to Proceed on November 4, 2026. Substantial Completion is required 177 calendar days (approximately six months) after Notice to Proceed. A pre-submittal conference and site visits are scheduled for October 27, 2026, with Phase 2 site investigation and interviews occurring October 21-23, 2026.
The City will award the contract using a two-phase competitive sealed proposal process under a traditional design-build delivery method with a stipulated-sum contract. Phase 1 evaluation will consider design-build experience with fire stations and public-safety facilities (25 points), qualifications of key personnel (25 points), past performance and references (20 points), understanding of the project and phasing approach (15 points), and safety record and bonding capacity (15 points). Phase 2 evaluation will assess stipulated sum price (40 points), technical proposal responsiveness (30 points), phasing and operations plan (15 points), and schedule (15 points), with price points awarded by formula favoring the lowest responsive price. The contract will include AIA Document A141-2024 with the City's Public Owner Supplementary Conditions, statutory performance and payment bonds, and E-Verify affidavits. Retainage will not exceed five percent of progress payments with release at Substantial Completion; liquidated damages are $500 per calendar day for failure to meet the Contract Time. The Design-Builder will bear all costs for design, permitting, construction, general conditions, bonds, insurance, and contingencies within the stipulated sum. Prequalified offerors submitting unsuccessful Phase 2 proposals will not receive a stipend but grant the City a license to use selected ideas and work product for a negotiated sum. The City will provide boundary surveys, geotechnical reports, existing-building assessments, hazardous materials surveys, and other supporting information; the Design-Builder is responsible for all design errors, code compliance, construction means and methods, and maintaining emergency-response operations during construction through an approved phasing plan.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF JESUP, GEORGIA
DESIGN-BUILD SERVICES — FIRE STATION NO. 1 CREW QUARTERS ADDITION
RFQ/RFP No. FD-26-01
PROJECT DESCRIPTION AND SOLICITATION REQUIREMENTS
September 26, 2026
1. Purpose
The City of Jesup, Georgia (the “City”) seeks a single design-build entity (the “Design-Builder”) to design and construct a crew quarters addition to Jesup Fire Department Station No. 1, as described in Section 2 (the “Project”). The City will select the Design-Builder by competitive sealed proposals under O.C.G.A. § 36-91-21(c), using the two-phase process described in Section
4. This document is incorporated in, and forms part of, the City’s Notice of Request for
Qualifications and Proposals.
2. Project Description
2.1 Project Location
Jesup Fire Department Station No. 1, 411 West Bay Street, Jesup, Georgia 31545, which serves as the Department’s headquarters station. The existing station building is approximately 9,900 square feet and was constructed approximately 1977. The new building will be located on the station site adjacent to the existing station, with its northeast elevation facing Bay Street.
2.2 Project Description
The Project is a new crew quarters building of approximately 3,200 gross square feet
(approximately 80 feet by 40 feet), single-story, connected to the existing Station No. 1 building by an enclosed connector of approximately 12 feet by 12 feet. The connector will join the existing building at the location of an existing exterior window, which will be removed and the opening modified to accommodate a door. The Project includes all design and construction of the building foundation (including in-slab plumbing) and the metal building including a brick façade to match the front of the adjacent and connecting building. All interior construction and MEP (excluding in-slab plumbing) will be done by the Owner.
2.3 Conceptual Program
The City’s Conceptual Floor Plan (Revised 09-01-26), attached as Attachment A, reflects the following program. The Owner’s Criteria issued in Phase 2 will confirm and refine it.
Space Quantity Program Requirements
Bedrooms 8 Individual sleeping rooms, each with a bed, wardrobe or locker storage, and a nightstand, arranged along exterior walls. Doors from the corridor. Station alerting (audio and visual) in each room. Single occupancy each shift.
Bathrooms 4 Each with a water closet, lavatory, and shower, with individual lockable doors. At least one must be fully accessible; see Section 2.4.
Space Quantity Program Requirements
Day Room and Kitchen 1 Open day room with kitchen, including a kitchen island, refrigerator, range, sink, and base and wall cabinets with countertops. Located at the east end of the building, adjacent to the connector and Bay Street.
Residential-grade gas range with standard exhaust hood.
Laundry 1 Washer and dryer connections, folding counter, and storage. Laundry of station linens and personal items only. Turnout gear is laundered elsewhere in the station.
Storage Rooms 2 One at the east end, adjacent to the day room, and one at the west end, adjacent to the laundry.
Corridors — Corridors of approximately 4 feet clear width as shown conceptually, or wider where required by code or accessibility standards.
Riser Room 1 Fire sprinkler riser room with exterior access, near the connector at the
Bay Street side.
Connector 1 Enclosed connector of approximately 12 feet by 12 feet between the new building and the existing station, at the location of the existing window to be removed. It will function as the transition between the station’s operational areas and the living quarters.
2.4 Status of the Conceptual Floor Plan
The Conceptual Floor Plan illustrates the City’s program and preferred arrangement only. It is not a design, is not drawn to scale for construction, and its dimensions are approximate. The Design-
Builder is responsible for developing a design that satisfies the program and all applicable codes.
Offerors may propose refinements to the layout that improve function or code compliance, but any proposed change must be identified as a deviation under Section 3.1. At a minimum, the design must address:
• Accessibility under the 2010 ADA Standards for Accessible Design and applicable Georgia accessibility requirements, including accessible routes, door clearances, and at least one accessible bathroom and sleeping room.
• Means of egress and exterior doors from the day room, corridors, and bedroom wings.
• Structural, envelope, and energy code requirements, including wind design appropriate to the building’s risk category as determined by the building official.
2.5 Performance Objectives
The completed facility shall, at a minimum:
• Comply with the Georgia State Minimum Standard Codes and all applicable local ordinances in effect on the Phase 2 proposal due date.
• Be designed to the structural and emergency-power criteria the building official determines apply to the addition, recognizing that Station No. 1 is an emergency-response facility.
• Allow Station No. 1 to remain in continuous emergency-response service throughout construction, with uninterrupted apparatus egress, station alerting, communications, and life-safety systems.
• Use durable, low-maintenance materials and building systems appropriate for 24-hour occupancy, with a service life of at least 50 years for the structure and envelope.
• Be architecturally compatible with the existing station.
2.6 Budget
The City’s estimated budget for all design and construction services, excluding City-furnished items and City contingency, will be stated in the Phase 2 Request for Proposals.
2.7 Anticipated Schedule
Milestone Target Date
Notice first published / Georgia Procurement Registry posting October 1, 2026
Pre-submittal conference and site visits October 27, 2026
Written questions due (Phase 1) October 16, 2026
Phase 1 Statements of Qualifications due October 19, 2026
Shortlist notification October 20, 2026
Phase 2 RFP and Owner’s Criteria issued to shortlisted offerors October 21, 2026
Phase 2 site investigation period at Station No. 1 and interviews October 21 – 23, 2026
Phase 2 proposals due and opened (at least four weeks after first publication) October 29, 2026
Discussions and best and final offers (if conducted) October 30, 2026
City Commission award November 3, 2026
Notice to Proceed November 4, 2026
Substantial Completion 177 calendar days (6 months) after Notice to
Proceed
3. Delivery Method and Contract
The Project will be delivered by traditional design-build under a stipulated-sum contract. The
Design-Builder will be solely responsible to the City for all design and construction. The contract will consist of:
1. AIA Document A141–2024, Standard Form of Agreement Between Owner and Design-
Builder for a Traditional Design-Build Project, with Exhibit A (Insurance and Bonds) and
Exhibit B (Design-Build Amendment), executed together at award. Exhibit C (Sustainable
Projects) will not apply unless required by a funding source.
2. The City of Jesup Public Owner Supplementary Conditions, which will control over the
AIA forms.
3. The Owner’s Criteria issued in Phase 2, as modified by addenda.
4. The Design-Builder’s accepted Phase 2 proposal, subject to the order of precedence in
Section 3.1.
5. Statutory performance and payment bonds, E-Verify affidavits, and the non-collusion oath.
3.1 Order of Precedence
The Owner’s Criteria control over the Design-Builder’s proposal, preliminary design, and all later design documents. A deviation from the Owner’s Criteria is effective only if it is specifically identified as a deviation in the Design-Builder’s proposal and expressly accepted in writing by the
City in the Contract. General assumptions, clarifications, qualifications, or exclusions in a proposal do not modify the Owner’s Criteria.
3.2 Key Commercial Terms
The Public Owner Supplementary Conditions will include, among other terms, the following:
• Price. Stipulated sum, inclusive of all design, permitting, construction, general conditions, bonds, insurance, fees, and contingencies.
• Retainage. Not more than five percent (5%) of each progress payment, and release at
Substantial Completion subject to withholding of up to 200% of the value of incomplete work, consistent with O.C.G.A. § 13-10-80.
• Payment. Monthly progress payments in accordance with O.C.G.A. § 13-10-80.
• Liquidated damages. $500 per calendar day for failure to achieve Substantial Completion within the Contract Time, reflecting the City’s cost of interim operations.
• Standard of performance. The Design-Builder warrants that the completed design and construction will satisfy the Owner’s Criteria and applicable codes, in addition to meeting the professional standard of care.
• Indemnity and insurance. Indemnity with a duty to defend, to the extent caused by the
Design-Builder’s negligence or breach, consistent with O.C.G.A. § 13-8-2(b). Commercial general liability, automobile, workers’ compensation, professional liability (with an extended reporting period), pollution liability, and builder’s risk, in amounts stated in
Exhibit A.
• Bonds. Performance and payment bonds, each at 100% of the contract amount, on City forms conforming to O.C.G.A. Title 36, Chapter 91, and covering both design and construction obligations.
• Design professionals. The City will be an intended third-party beneficiary of the Design-
Builder’s agreements with its architect and engineers of record.
• License to documents. A license for the City to use the design documents for the Project, for completion after any termination, and for future additions to other City fire stations, without additional fee.
• Changes. Owner’s representative authority limited to $20,000 per Change Order; Change
Orders above that amount require City Commission approval.
• Termination for convenience. Recovery limited to work performed and reasonable demobilization costs, with no anticipated profit or termination fee.
• Funding. Obligations are subject to appropriation and to the funding sources identified by the City.
• Disputes. Meet-and-confer, then mediation, then litigation in the Superior Court of Wayne
County under Georgia law. No arbitration.
4. Selection Process
4.1 Phase 1 — Request for Qualifications (Prequalification)
Offerors will submit Statements of Qualifications meeting the requirements of Section 6.1. An evaluation committee will score the submissions under the Phase 1 criteria in Section 5.1, and the
City will prequalify and shortlist not more than three (3) offerors. This process is a mandatory prequalification under O.C.G.A. § 36-91-20(f). An offeror not prequalified may respond to its disqualification in writing to Nick Ellis – City Manager within five (5) business days after notice.
This procedure is not a formal appeal.
4.2 Phase 2 — Request for Proposals
The City will issue the Owner’s Criteria to prequalified offerors by addendum. The Owner’s
Criteria will include:
• the confirmed space program, developed from the Conceptual Floor Plan;
• performance requirements;
• boundary and topographic surveys;
• geotechnical reports;
• existing-building condition assessments;
• pre-renovation asbestos and hazardous-materials surveys; and
• phasing and operational constraints.
The City will then conduct a site investigation period, during which offerors may inspect Station
No. 1 under escort, and may hold confidential one-on-one meetings with each offeror. Offerors will submit sealed technical and price proposals meeting the requirements of Section 6.2.
The City will not pay each prequalified offeror that submits a responsive but unsuccessful Phase
2 proposal a stipend. However, as a condition of proposing, the offeror grants the City a license to use selected ideas and work product in its proposal for a negotiated sum to be determined.
4.3 Opening, Evaluation, Discussions, and Award
Phase 2 proposals will be opened at the time and place stated in the Notice, in a manner that avoids disclosure of their contents to competing offerors. The evaluation committee will score proposals under the Phase 2 criteria in Section 5.2.
The City may award without discussions. The City may also conduct discussions with, and request best and final offers from, all responsible offerors whose proposals are reasonably susceptible of being selected for award. The contents of any proposal will not be disclosed to competing offerors during discussions.
Award will be made to the responsible and responsive offeror whose proposal is determined in writing to be most advantageous to the City under the stated evaluation factors, subject to approval by the City Commission. The basis for the award will be documented in the contract file.
5. Evaluation Factors and Relative Importance
5.1 Phase 1 — Qualifications
Factor Points
Design-build experience with fire stations, crew quarters, and other public-safety facilities, including additions to facilities that remained in operation
Qualifications and experience of key personnel (design-build project executive, architect of record, project manager, superintendent)
Past performance on cost, schedule, quality, and owner satisfaction, including references
Understanding of the Project and preliminary approach to phasing and continuous station operations
Safety record (EMR and OSHA history) and capacity to perform 15
Bonding capacity and Georgia licensure Pass/Fail
5.2 Phase 2 — Proposals
Phase 1 scores do not carry forward. Phase 2 proposals will be evaluated as follows:
Factor Points
Stipulated sum price 40
Technical proposal: responsiveness of the preliminary design to the Owner’s Criteria, functionality, durability, and life-cycle considerations
Phasing plan and approach to maintaining continuous station operations 15
Schedule, including Contract Time to Substantial Completion 15
Price points will be awarded by formula: the lowest responsive price receives the maximum points, and each other price receives points in proportion to the ratio of the lowest price to that price.
6. Submission Requirements
6.1 Phase 1 — Statement of Qualifications
Limit to 30 pages, excluding forms, resumes, and financial information. Submit one (1) original, five (5) copies, and one electronic copy on USB drive, in a sealed package marked with the
RFQ/RFP number. Include:
1. Cover letter signed by an authorized officer, identifying the design-build entity, its legal structure (including any joint venture), and the lead contact.
2. Team organization chart identifying the design-build entity, architect of record, engineers of record, and key personnel, with resumes, Georgia licenses, and roles. Key personnel may not be substituted without City approval.
3. Descriptions of at least three (3) comparable projects completed within the last ten (10) years (fire stations, fire station living quarters, public-safety facilities, or additions to occupied facilities that remained in operation during construction), with owner references, original and final contract amounts, and original and final schedules.
4. Preliminary approach to maintaining station operations during construction.
5. Safety information: Experience Modification Rate for the last three years and OSHA citations for the last five years.
6. Litigation, claims, arbitration, contract terminations, and surety claims involving the offeror or team members within the last five (5) years.
7. Surety letter confirming the offeror’s ability to bond a project of $1,000,000 single and
$2,000,000 aggregate.
8. Evidence of ability to provide the insurance required by Exhibit A.
9. Georgia general contractor license number and Georgia registration for the architect and engineers of record.
10. Acknowledgment of all addenda.
6.2 Phase 2 — Technical and Price Proposal
The technical proposal and price proposal must be submitted in separate sealed envelopes. The technical proposal must include:
1. Evaluation of the Owner’s Criteria. Local conditions affecting the work, program allocations with square footages, code compliance evaluation, and any recommended adjustments.
2. Preliminary Design. Site plan showing the location of the new building and connector relative to the existing station, Bay Street, parking, utilities; building sections and elevations; structural system; selections and outline specifications of principal materials.
3. Phasing and operations plan showing how continuous emergency-response service will be maintained at Station No. 1, including the timing and temporary protection of the connector tie-in.
4. Project schedule showing design, City review periods, permitting, construction, and
Substantial Completion.
5. List of deviations from the Owner’s Criteria. Each deviation must be specifically identified; see Section 3.1.
6. List of proposed major subcontractors and suppliers.
7. Exceptions to the Contract or Supplementary Conditions. Exceptions may render a proposal nonresponsive and will be considered in evaluation.
The price proposal must include:
1. Stipulated sum on the City’s Price Proposal Form, with a breakdown by design, general conditions, demolition and tie-in, foundation and building design and construction.
2. Prices for any alternates stated in the Owner’s Criteria.
3. Unit prices, if requested.
4. Proposal bond in the amount of five percent (5%) of the stipulated sum confirm O.C.G.A.
§ 36-91-5.
5. Proposal validity of 90 days.
Proposal drawings and specifications are preliminary. The Design-Builder remains obligated to develop the design to satisfy the Owner’s Criteria for the stipulated sum.
6.3 Required Forms and Affidavits
• Contractor affidavit and subcontractor affidavits under O.C.G.A. § 13-10-91 (E-Verify).
• Non-collusion oath under O.C.G.A. § 36-91-21(e), to be executed by the successful offeror before commencing work.
• Conflict-of-interest disclosure.
• Acknowledgment of addenda.
• Federal or state funding certifications, if applicable.
7. Design-Builder Deliverables and Services After Award
7.1 Design Phase
The Design-Builder shall advance the accepted Preliminary Design through the following submittals, allowing the City fourteen (14) calendar days for review of each:
• Design Development — approximately 50% design, with an updated schedule of values and code analysis.
• Construction Documents — approximately 90%, with coordinated drawings and specifications for all disciplines.
• Issued for Construction — 100% documents sealed by Georgia-registered design professionals and approved for permit.
City review is for conformance with the Owner’s Criteria only and does not relieve the Design-
Builder of responsibility for the design. The Design-Builder shall obtain all building and trade permits and approvals from authorities having jurisdiction.
7.2 Construction Phase
• Construction of the Project in accordance with the approved phasing plan and Contract
Time.
• Supervision, safety programs, quality control, and special inspections required by code.
• Monthly progress reports with updated schedule, submittal log, requests for information, change log, and cash-flow forecast.
• Coordination with City-furnished equipment, systems, and separate contractors.
• Temporary facilities and protections necessary to keep Station No. 1 operational, including temporary weather and security enclosure of the connector opening.
7.3 Commissioning and Closeout
• Testing, commissioning, and start-up of mechanical, electrical, plumbing, fire sprinkler, fire alarm, kitchen ventilation, connector pressurization, and station alerting interface systems.
• Training of City personnel.
• Record (as-built) drawings in PDF and native CAD or BIM format.
• Operation and maintenance manuals, warranties, and attic stock.
• Certificates of occupancy.
• Final lien and payment releases and consent of surety.
7.4 Warranty Phase
• Correction of defective work for one year after Substantial Completion, without waiver of other warranties or remedies.
• Warranty walk-through at eleven (11) months after Substantial Completion.
• Manufacturer warranties assigned to the City, including a roof warranty of at least 20 years.
8. Allocation of Risk
The following allocation summarizes the risk structure of the Contract and is provided so offerors may price their proposals accurately. If this table conflicts with the Contract, the Contract controls.
Risk Responsible
Party Notes
Design errors, omissions, and coordination Design-Builder Includes conflicts among disciplines and between design and construction. Owner review or approval of design submittals does not shift this risk.
Code and regulatory compliance of the design Design-Builder Applies even where compliance requires deviation from a conceptual element of the Owner’s Criteria. The
Design-Builder must identify any such conflict in its proposal; unidentified conflicts are resolved at the
Design-Builder’s cost.
Functional program (spaces, adjacencies, operational requirements stated by the City)
City The City is responsible for the stated program. The
Design-Builder is responsible for a design that satisfies it.
Changes the City directs after award City Adjustment by Change Order under the Contract.
Accuracy of factual data in City-furnished surveys, geotechnical reports, and existing-building and hazardous-materials surveys
City The Design-Builder may rely on factual data
(measurements, boring logs, test results). It may not rely on interpretations, opinions, or recommendations, which it must evaluate independently.
Site and existing-building conditions that are visible, documented in City-furnished information, or discoverable by the investigation the Design-
Builder is required to perform
Design-Builder Offerors are expected to price conditions at the connector tie-in to the existing station (including the wall and window opening) that are reasonably discoverable during the site visit and investigation period.
Concealed conditions that differ materially from City-furnished information and were not reasonably discoverable
City Equitable adjustment of price and time, subject to prompt written notice before the condition is disturbed.
Hazardous materials identified in the City’s survey City — separate abatement contractor
Hazardous materials not identified and not reasonably discoverable
City Stop work in the affected area; City arranges testing and abatement; time and cost adjustment as provided in the
Contract.
Materials and labor price escalation after proposal submission
Design-Builder
Subcontractor and supplier performance, default, and pricing Design-Builder
Construction means, methods, sequencing, and jobsite safety Design-Builder
Risk Responsible
Party Notes
Maintaining emergency-response operations during construction Shared The Design-Builder designs and executes the phasing plan the City approves, including continuous apparatus egress, alerting, and life-safety systems and protection of the existing building during the connector tie-in. The
City is responsible for relocating personnel and equipment within the station in accordance with the approved plan.
Damage to the existing station, City property, and adjacent property caused by the work
Design-Builder The City maintains property insurance on the existing structures; the Design-Builder is responsible for damage it causes, subject to the waiver of subrogation in the
Contract.
Builder’s risk on the new work Design-Builder Exhibit A § A.3.3.2.1 to be selected.
Building permit, trade permits, and inspection fees Design-Builder City permit fees will be waived for City projects.
Zoning, land-use approvals, easements, and rights-of-way City
Utility service connection and impact fees City
City review of design submittals beyond the stated review periods City Time extension; cost adjustment only to the extent of documented impact.
Abnormal weather Shared Time extension only, if documented as abnormal for the period and actually affecting critical-path work. No cost adjustment.
Force majeure events beyond either party’s control Shared Time extension only.
Changes in law or codes enacted after the proposal due date that affect the work
City Equitable adjustment.
Failure to achieve Substantial
Completion within the Contract
Time
Design-Builder Liquidated damages of $500 per calendar day.
Defective work discovered after completion Design-Builder Correction obligation for one year after Substantial
Completion, without waiver of the City’s other warranty and legal remedies.
9. City-Furnished Information and Responsibilities
The City has furnished the Conceptual Floor Plan (Revised 09-01-26), attached as Attachment A.
Before or with the Phase 2 RFP, the City will also furnish:
• boundary and topographic surveys;
• geotechnical investigation reports;
• existing-building condition assessments and available record drawings;
• pre-renovation asbestos and hazardous-materials surveys; and
• available utility information.
After award, the City will designate a representative, conduct design reviews within the stated review periods, coordinate station operations and relocation of personnel and equipment under the approved phasing plan, obtain any required zoning approvals and easements, and furnish the City-furnished equipment and systems identified in the Owner’s Criteria. Record drawings of the existing station are provided for information only, and their accuracy is not warranted.
10. General Conditions of the Solicitation
• Communications. From issuance of the Notice until award, offerors and team members shall communicate about this solicitation only with the designated contact. Contact with
City Commissioners, officials, or staff about the solicitation is grounds for disqualification.
• Addenda. Interpretations and changes will be made only by written addenda posted where the solicitation is posted. No addenda will be issued within 72 hours of a submission deadline (excluding Saturdays, Sundays, and legal holidays) unless the deadline is extended as required by O.C.G.A. § 36-91-20(d).
• Costs. Except for any stipend under Section 4.2, offerors bear all costs of preparing submissions.
• Open records. Submissions are public records subject to the Georgia Open Records Act.
Material claimed as a trade secret must be clearly marked and accompanied by the affidavit required by O.C.G.A. § 50-18-72. The City does not guarantee protection of any material.
• Anti-competitive conduct. Conduct prohibited by O.C.G.A. § 36-91-21(d) will result in disqualification and may void any resulting contract.
• Labor agreements. Nothing in this solicitation requires or prohibits project labor or collective bargaining agreements (O.C.G.A. § 36-91-21(f)).
• Reservation of rights. The City may reject any or all submissions; waive technicalities and informalities; request clarifications; cancel or reissue the solicitation; and decline to award.
• No contract until execution. No contract exists until the Contract is approved by the City
Commission and executed in the manner required by the City Charter and ordinances.
ATTACHMENT A
CITY OF JESUP — CONCEPTUAL FLOOR PLAN (REVISED 09-01-26)
Fire Station No. 1 Crew Quarters Addition — 411 West Bay Street
Conceptual only. Not to scale. Dimensions approximate. See Section 2.4.