This document is a construction drawing for a Portland General Electric (PGE) project located in Gresham, Oregon. The project involves installing an underground electrical circuit, 13 aluminum poles, and LED lights to be connected at 240V. The customer is responsible for providing trenching, backfilling, conduit, elbows, junction boxes, vaults, and pads. PGE will determine the size and number of conduits required and will provide a standby crew to open all energized PGE vaults, junction boxes, and equipment/facilities. The project is located at 10811 SE 172nd Ave in Happy Valley, within the Clackamas School District.

The document outlines detailed construction requirements, including specifications for duct, clearances, transformer pad installations, and ground rod installations. It also includes a vicinity map and a notice regarding the required right-of-way permit from the local jurisdiction. This project appears to be part of a larger state and local contract opportunity for the extension of SE 162nd Avenue and related infrastructure improvements in the area.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PGE CONSTRUCTION DRAWING

This document accurately represents FIELD Construction.

Foreman: Date:

AS-BUILT VERIFICATION & NESC VIOLATIONS CORRECTED

DATE: SCALE: ACCOUNT: AWO: JOB NO:

TITLE:

CIRCUIT:

LOCATION:

DESCRIPTION:

COUNTY:

DESIGN BY:

SECTION (S):

DRAWN BY:

WORK WITH: SHEET:

SIZE:

PHONE:

© PORTLAND GENERAL ELECTRIC CO. - ALL RIGHTS RESERVED

(503)

OF

GRESHAM

LINE CREW CENTER

1705 NE BURNSIDE ST

GRESHAM, OR 97030

672-5417RICO SOLIS LUIS BLANCO

D1331BCLACKAMAS

Install UG circuit, 13 Aluminum poles and LED lights, connect at 240V

10811 SE 172nd Ave, HAPPY VALLEY

PLEASANT VALLEY-SUN 17X22

N Clack School Dist/Clack Co Service Dist. # 5/Scouters Mt Elem CUP-01/Job 11-23

M333587110000091061070001NTS10/06/2023

CONST. PROJECT MGR: PHONE:

Date:General Foreman:

(Signature only required for field construction changes.)

CONSTRUCTION NOTES: SLCST

1. CUSTOMER TO PROVIDE ALL TRENCHING, BACKFILLING, CONDUIT, ELBOWS, JUNCTION

BOXES, VAULTS AND PADS. JOINT USE TRENCH WITH GAS, TRENCH TO BE 48 INCHES DEEP

AND 30 INCHES WIDE, MEASURED FROM FINAL GRADE. ALL PGE CONDUCTORS TO BE

INSTALLED IN GRAY, SCHEDULE 40, ELECTRICAL GRADE, PVC CONDUIT WITH NYLON PULL

STRINGS (MIN. 500 LBS. TEST). PGE TO DETERMINE THE SIZE AND NUMBER OF CONDUITS

REQUIRED. MAINTAIN 12 VERTICAL INCHES AND 24 HORIZONTAL INCHES CLEARANCE

BETWEEN GAS AND OTHER UTILITIES. ALL ELBOWS 4 INCH & SMALLER TO BE 36 INCH

RADIUS. RIGID STEEL OR PGE APPROVED FIBERGLASS BENDS ARE REQUIRED FOR RUNS

OF 151 FEET OR LONGER, OR FOR ANY LENGTH RUN WITH MORE THAN 180 DEGREES IN

BENDS. PVC SCHEDULE 40 BENDS ARE ACCEPTABLE FOR RUNS OF 150 FEET OR LESS THE

MAXIMUM TOTAL BENDS IN ANY CONDUIT RUN IS 270 DEGREES. ALL BENDS MUST BE

FACTORY MADE. REFER TO LETTER OF RESPONSIBILITY FOR FURTHER DETAILS.

2. A PGE STANDBY CREW IS REQUIRED FOR OPENING ALL ENERGIZED PGE VAULTS, JUNCTION

BOXES, AND EQUIPMENT/FACILITIES, INCLUDING CONNECTION OR INSTALLATION OF

CONDUITS AND PULL STRINGS. CALL SERVICE COORDINATION AT 503-323-6700 TO SCHEDULE

A PGE STANDBY CREW.

3. ALL CONCRETE FOOTINGS NEED TO BE INSTALLED WITH TOP OF BASE FLUSH TO CURB /

SIDEWALK.

4. CUSTOMER RESPONSIBLE FOR ROAD CROSSINGS. ALL CROSSINGS MUST EXTEND FROM

PROPERTY LINE TO PROPERTY LINE. CROSSINGS TO BE 48 INCHES DEEP, MEASURED FROM

FINAL GRADE.

5. DIRECTIONAL BORING REQUIREMENTS: BLACK HDPE (HIGH DENSITY POLYETHYLENE) DUCT

OR SCHEDULE 40 PVC WITH A MECHANICAL CONNECTION (CERTA-LOK OR LIKE MECHANICAL

CONNECTION PRODUCT) AS AN ALTERNATIVE TO HDPE DUCT. HDPE SHALL MEET THE

REQUIREMENTS OF PGE SPECIFICATION L22501 (AVAILABLE ON REQUEST FROM PGE

PROJECT MANAGER). FOR SAFETY REASONS THE DUCT SHALL BE BLACK WITH THREE

EQUALLY SPACE EXTRUDED RED STRIPES (WHICH IS A SPECIFICATION REQUIREMENT).

MANDREL TEST OF HDPE PIPE IS REQUIRED AFTER INSTALLATION WITH PGE INSPECTOR

PRESENT.

6. TRANSFORMER PADS ARE TO BE SET SO THAT THE TOP IS 2 INCHES ABOVE FINAL GRADE.

CONDUIT IS TO BE INSTALLED IN PAD AS INDICATED IN DETAIL AND TO EXTEND 1 INCH

ABOVE THE PAD.

7. ALL PGE TRANSFORMERS TO BE INSTALLED 8 FEET (MIN) FROM ANY COMBUSTIBLE

BUILDING, WALL OR OVERHANG AND 4 FEET (MIN) FROM ANY FIRE HYDRANT. PGE

TRANSFORMERS MUST BE WITHIN 15 FEET OF A DRIVEABLE AREA. ALWAYS MAINTAIN 10

FEET CLEARANCE IN FRONT OF ALL TRANSFORMERS.

8. STEEL BARRIER POSTS ARE REQUIRED AROUND TRANSFORMERS THAT ARE EXPOSED TO

VEHICLES. REFER TO ELECTRICAL SERVICE REQUIREMENTS (ESR) SECTION 5.6.8.

9. AS NEEDED-FRONT LOT PUBLIC UTILITY EASEMENT (P.U.E.) TO BE 8 FEET (MIN), 10 FEET

(PREFERRED).

10. CONSULT WITH PGE REPRESENTATIVE 2 WEEKS BEFORE STARTING MAIN POWER

TRENCHING FOR A PRECONSTRUCTION CONFERENCE. INCLUDED IN THIS CONFERENCE

WILL BE EXCAVATOR, PGE, TELCO, CATV, AND GAS.

11. CUSTOMER TRENCH AND ELBOW CONFIGURATIONS, ALL CONDUIT, VAULT AND PAD

INSTALLATIONS MUST BE INSPECTED BY PGE PRIOR TO BACKFILLING. WHEN YOU ARE

READY FOR PGE TO INSPECT (AFTER INSTALLATION IS COMPLETE) CALL 503-736-5450 OR

503-463-4348 (SALEM AREA). ALLOW UP TO 2 WORKING DAY FOR INSPECTION TO OCCUR.

12. REFER TO THE PGE ELECTRIC SERVICE REQUIREMENTS BOOKLET FOR SPECIFIC

REQUIREMENTS.

13. DESIGN IS BASED ON STANDARD UNDERGROUND EQUIPMENT. NON-STANDARD UNDER-

GROUND EQUIPMENT MAY BE AN OPTION AT AN ADDITIONAL COST TO THE CUSTOMER.

VICINITY MAP

RIGHT-OF-WAY PERMIT NOTICE:

A PERMIT FROM THE LOCAL JURISDICTION IS REQUIRED BEFORE ANY

WORK IN THE RIGHT-OF-WAY MAY BE PERFORMED. ONLY PGE APPROVED

CONTRACTORS AND CONTRACTORS WHO HAVE MADE OTHER SPECIAL

AGREEMENTS WITH PGE WILL BE ALLOWED TO WORK UNDER PGE'S PERMIT.

THE CONTRACTOR MUST NOTIFY THE LOCAL JURISDICTION 48 HOURS

BEFORE WORK IS TO BEGIN. A COPY OF THE PERMIT MUST BE ON SITE.

YOUR PROJECT REQUIRES A PRECONSTRUCTION MEETING. CONTACT YOUR SERVICE & DESIGN

PROJECT MANAGER 7 TO 10 WORKING DAYS PRIOR TO EXCAVATION TO COORDINATE THE

PRE-CON. PGE'S FIELD CONSTRUCTION COORDINATOR (FCC) WILL PROVIDE YOUR TRENCH

AND CONDUIT INSPECTIONS.

PRE-CONSTRUCTION MEETING / TRENCH AND CONDUIT INSPECTION

ANY DEVIATION FROM THIS DESIGN MUST

BE APPROVED BY PGE PROJECT MANAGER

Know what's below.

Call before youdig.

CALL 811 BEFORE YOU DIGATTENTION:

OREGON LAW REQUIRES YOU TO FOLLOW RULES ADOPTED

BY THE OREGON UTILITY NOTIFICATION CENTER.

THOSE RULES ARE SET FORTH IN OAR 952-001-0001

THROUGH 952-001-0100. YOU MAY OBTAIN COPIES OF

THE RULES BY CALLING THE OREGON UTILITY

NOTIFICATION CENTER ADMINISTRATION @ (503-232-1987)

TO REQUEST UTILITY LOCATES CALL THE OREGON

UTILITY NOTIFICATION CENTER, 811 AT LEAST

2 BUSINESS DAYS PRIOR TO EXCAVATION.

CONTACT SERVICE COORDINATOR

FOR TRENCH AND CONDUIT INSPECTION PRIOR

TO BACKFILL. PGE WILL NOT INSTALL WIRE

UNTIL TRENCH IS 100% BACKFILLED.

SERVICE COORDINATOR

503-323-6700 OR 800-542-8818

THINK

SAFETY

FIRST!

PGE FACILITIES NOT DRAWN TO SCALE

THIS DRAWING IS A GRAPHICAL REPRESENTATION OF PORTLAND GENERAL

ELECTRIC FACILITIES IN THE FIELD. THIS MAP ILLUSTRATES ELECTRICAL

CONNECTIVITY, TYPES AND NUMBERS OF CONDUCTORS AND PLACEMENT OF

EQUIPMENT WITHIN THE DISTRIBUTION SYSTEM. IT IS RECOMMENDED THAT

THE USER NOT RELY ON THIS DIAGRAM FOR GEOGRAPHICAL LOCATIONS

JUNCTION BOX INSTALLATIONS

FOR STREET LIGHTING

CONTACT PGE FOR APPROVED MANUFACTURERS

8' GROUND ROD

INSTALLED BY

CUSTOMER

1" PVC SCH 40 ELECTRICAL GRADE

TO OPTIONAL ST LT POLE

2" OR 3" PVC SCH 40

ELECTRICAL GRADE

(DETERMINED BY PGE)

SCH 40 GREY PVC FACTORY BENDS

(STEEL OR PGE APPROVED FIBERGLASS

FOR RUNS OVER 150', OR 180 DEGREES

OR MORE IN BENDS)

*36'' RADIUS 90 BEND

3"

2"54

1"

STREET SIDE

TOP VIEW

1" CONDUIT TO

STREET LIGHT POLE

2" OR 3"

CONDUIT

2" OR 3"

CONDUIT

GROUND

ROD

INSTALL GROUND ROD AND

CONDUIT ON THE SOURCE SIDE

13''x24''x18'' DEEP OR 17"x30"x18" DEEP

PGE APPROVED

JUNCTION BOX

DETERMINED BY PGE

FINAL GRADE IF SOFT SURFACE

FINAL GRADE IF HARD SURFACE (FLUSH)

JUNCTION BOXES CANNOT BE COVERED BY LANDSCAPE MATERIALS.

IF PGE LOCATES A HIDDEN JUNCTION BOX WITHIN 6 MONTHS OF

PGE TAKING OWNERSHIP, PGE WILL BILL THE DEVELOPER FOR THE

COST TO LOCATE AND MAKE ANY ADDITIONAL REPAIRS TO BRING THE

JUNCTION BOX TO GRADE.

INSTALL 30A FUSES IN SECONDARY PEDESTALS OR SECONDARY

VAULTS (WHICHEVER IS ST LT POINT OF ATTACHMENT) FOR EACH

STREET LIGHT PER T&D CONSTRUCTION STANDARD LC11550

NEW PGE FACILITIES TO BE INSTALLED

(UNLESS OTHERWISE SPECIFIED)

LIGHTING LEGEND

REMOVE FACILITIES INSTALL FACILITIES

INSTALL ADDITIONAL FACILITIES/MODIFY FACILITIES

INSTALL 1-#10 CU-TX ST LT CIRCUIT IN 1" SCH40 PVC CONDUIT

PROVIDED & INSTALLED BY CUSTOMER

INSTALL 1-1/0 AL-TX ST LT CIRCUIT IN 2" SCH40 PVC CONDUIT

PROVIDED & INSTALLED BY CUSTOMER

CUSTOMER INSTALLED 1324 STREETLIGHT JUNCTION BOX

PGE TO PROVIDE GROUND ROD, CUSTOMER TO INSTALL

CUSTOMER INSTALLED 1730 SECONDARY VAULT

PGE TO PROVIDE GROUND ROD, CUSTOMER TO INSTALL

INSTALL 88W LED LEOTEK GREEN COBRA GRAY LIGHT

ON NEW SLO 30' ALUMINUM DAVIT POLE

USE NEW 6' MAST ARM

ON 5CL-LB-PGE CONCRETE BASE

SET 2' FP-FC

CONNECT 240VOPT A

UTILITY VAULT 20R-LB-4-PGE (870 lb)

PRECAST CONCRETE FOOTING

1.

Notes:

Tamped 3/4-inch minus crushed rock backfill is required around all poles and footings regardless of soil CONDITION to maintain proper pole alignment.

3. Maximum working moment for this footing is 4,255 lb-ft.

4. WHEN INSTALLING ALUMINIUM POLES, ONE 8'-5/8" GALVANIZED

GROUND ROD WITH #6 SOLID CU WIRE MUST BE INSTALLED

AT LEAST 2" BELOW FINAL GRADE IN UNDISTURBED SOIL.

PER NESC 21 5C

Anchor Bolt Size and Spacing as Required Customer to Supply (4 Places in Top)

2.

Bolt Circle = 11" Dia.

3-1/2" Bolt Projection 1"-8NC x 36" NC Galv Steel

20" DIA

11"

3-1/2"

48"

See Note 1

Crushed Rock

2-3/8" Dia conduit chase

(4 places)

Finish Grade

See Note 2

3/4"-Minus

FIELD SIDE

FINAL GRADE

STREET SIDE

18" COILED AT TOP OF

FOOTING FOR PGE

(NOTE#4)

CONCRETE

FOOTING

GROUND

CLAMP

8' GALVANIZED

5/8" GROUND ROD

#6 AWG BSD CU

GROUND

CONDUCTOR

1" SCHED 40

CONDUIT

W/36" SWEEP

STREET SIDE

FIELD SIDE

STREET LIGHT FOOTING

GROUND ROD LOCATION

TOP

VIEW

NOTES: (PGE TO PROVIDE GROUND ROD &

COPPER WIRE, CUSTOMER TO INSTALL)

1. THE GROUND ROD & #6 AWG BSD CU MUST BE

INSTALLED DURING STREET LIGHT FOOTING

INSTALLATION.

2. THE GROUND ROD MUST BE INSTALLED IN

UNDISTRURBED SOIL AT LEAST 2" BELOW

FINAL GRADE, PER NESC 215C APPROVED BY PGE.

3. CUSTOMER TO COIL 3" OF COPPER WIRE

AROUND TOP OF GROUND ROD. PGE WILL MAKE

FINAL CONNECTIONS.

4. BONDING IS ACCOMPLISHED BY CONNECTING

THE NEUTRAL CONDUCTOR (GREEN CONDUCTOR)

TO THE GROUNDING CONDUCTOR NEAR THE

POLE GROUNDING TAB.

MIN

6"

4"

GROUND ROD INSTALLATION

FOR METAL STREET LIGHT POLES

OPT. A

NOTE:

PGE TO PROVIDE CONCRETE BASES & GROUND RODS FOR

CUSTOMER TO INSTALL AT THE SAME TIME AS THE CONDUIT.

INSTALL 40W LED AURORA PENDAND LIGHT

ON NEW SLO 23' ALUMINUM DECORATIVE BLACK POLE

USE NEW 4' MAST ARM

ON 20R-LB-PGE CONCRETE BASE

SET 2' FP-FC

CONNECT 240VOPT A

LAMP POLE FOOTING

No. 5CL-LB (750 lb)

5'-0"

See Note 1

Crushed Rock

1'-2" 1'-2"

See Note 2 11"

3/4"-Minus

3-1/2"

Finish Grade

3. WHEN INSTALLING ALUMINIUM POLES, ONE 8'-5/8" GALVANIZED

GROUND ROD WITH #6 SOLID CU WIRE MUST BE INSTALLED

AT LEAST 2" BELOW FINAL GRADE IN UNDISTURBED SOIL.

PER NESC 21 5C

1. Tamped 3/4-inch minus crushed rock backfill is REQUIRED around all poles and footings regardless OF SOIL CONDITION to maintain proper pole alignment.

Anchor Bolt Size and Spacing as Required Customer to Supply (4 Places in Top)

2.

Bolt Circle = 11" Dia.

3-1/2" Bolt Projection 1"-8NC x 36" NC Galv Steel

Notes:

E10376 Snapshot

E10376 PolyLine

E10376 Image

E10376 Rectangle

E10376 Text Box

JOB SITE

E10376 Text Box 23'-Unknown None

E10376 Rectangle

E10376 Rectangle

E10376 Text Box 23'-Unknown None

E10376 Snapshot

E10376 Rectangle

E10376 Snapshot

E10376 Text Box 23'-Unknown None

E10376 Rectangle

E10376 Text Box 23'-Unknown None

E10376 Snapshot

E10376 Text Box 23'-Unknown None

E10376 Text Box 23'-Unknown None

E10376 Text Box

VT-756

E10376 Text Box

VT-755

E10376 Text Box 30'-Unknown None

E10376 Text Box

VT-754

E10376 Text Box

VT-753

E10376 Text Box 30'-Unknown None

E10376 Text Box

VT-752

E10376 Text Box 30'-Unknown None

E10376 Text Box

VT-751

E10376 Text Box 30'-Unknown None

E10376 Text Box

VT-750

E10376 Text Box 30'-Unknown None

E10376 Text Box

VT-757

E10376 Rectangle

E10376 Text Box

VT-758

E10376 Rectangle

E10376 Text Box

VT-759

E10376 Rectangle

E10376 Text Box

VT-760

E10376 Rectangle

E10376 Rectangle

E10376 Text Box 23'-Unknown None

E10376 Snapshot

E10376 Text Box

VT-749

E10376 Text Box 30'-Unknown None

E10376 Text Box 165'

E10376 PolyLine

E10376 Rectangle

E10376 Text Box

POWER SOURCE

E10376 Text Box 155'

E10376 Text Box 60'

E10376 Text Box 110'

E10376 Text Box 120'

E10376 Text Box 115'

E10376 Text Box 150'

E10376 Text Box 115'

E10376 Text Box 100'

E10376 Text Box 35'

E10376 Text Box 220'

E10376 Text Box 150'

E10376 Text Box 120'

E10376 Snapshot

E10376 Snapshot

E10376 Text Box

INSTALL 6 WAY BUS

E10376 Arrow

E10376 Arrow

E10376 Rectangle

E10376 Text Box CUSTOMER TO CALL PGE SERVICE DESK AT 503-323-6700 TO SCHEDULE A STANDBY CREW WHILE PLUMBING INTO PD-16