Final Selection_Award Info

170 KB Posted

Attached to
Electrical Vault Modification Projects FY22-27
Solicitation number
2052-22
Issued by
Fulton County, Georgia

About this file

This is a Final Selection/Award Information document from Georgia Institute of Technology, a unit of the University System of Georgia, regarding design-bid-build construction services for multiple electrical vault modification projects. The solicitation (Bid-Solicitation No. 2052-22) sought qualified contractors to provide installation, modification, maintenance, inspection, and repair of underground network power distribution equipment and cabling on the GT campus for the period of fiscal years 2022 through 2027. The qualifications submission deadline was 2:00 PM on Tuesday, March 29, 2022, submitted to the Georgia Institute of Technology Office of Infrastructure & Sustainability. A shortlist announcement was released on April 11, 2022, followed by the final selection announcement on April 12, 2022. The contract will commence on July 1, 2022, and conclude on June 30, 2027, representing a five-year term with no renewal options mentioned.

JAH Power Services, Inc. was selected as the successful contractor following completion of proposal evaluations and interviews conducted by the Selection Committee. The design-bid-build construction contract will be awarded with a contract amount not to exceed $5,000,000. The contracting officer is Donna Vongsouvan (donna.vongsouvan@facilities.gatech.edu) and the project manager is Brian Clarke (brian.clarke@facilities.gatech.edu), both located at Georgia Institute of Technology, 151 Sixth Street NW, Atlanta, Georgia 30332.

Text of this file

A Unit of the University System of Georgia An Equal Education and Employment Opportunity Institution

April 12, 2022 Via Georgia Procurement Registry (GPR)

FINAL SELECTION / AWARD INFORMATION

Request for Qualified Contractor to Provide

Design-Bid-Build Construction Services For:

“Multiple GT Electrical Vault Modification Projects FY2022-2027” Bid-Solicitation No. 2052-22

Georgia Institute of Technology

Atlanta, Georgia

FINAL SELECTION:

Upon completion of the evaluation of the proposals and interviews by the Selection Committee, it has been determined that JAH Power Services, Inc.

(Firm) is the successful Contractor. Firm will be contacted by the Project Manager to proceed with the award process.

AWARD INFORMATION:

Design-Bid-Build Construction Contract will be awarded to:

JAH Power Services, Inc.

Contract Start Date: 07/01/2022 Contract End Date: 06/30/2027 Contract Amount: NTE $5M

End of Final Selection / Award Information

Donna Vongsouvan, Contracting Officer donna.vongsouvan@facilities.gatech.edu Brian Clarke, Project Manager brian.clarke@facilities.gatech.edu

151 Sixth Street., NW Atlanta, Georgia 30332

Other files

File Type Posted
RFQC —
Shortlist Announcement —

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .