Final_RFB_785_2100000220_5_SO_FORM.PDF

PDF 1 MB Posted

Attached to
RFB-107-21 Asbestos Abatement, Old Boiler House NTC Burgin
Solicitation number
RFB 785 2100000220 7
Issued by
Meade County, Brooksville City, Kentucky

About this file

This is a Solicitation Modification document issued by the Commonwealth of Kentucky for asbestos abatement services at the Northpoint Training Center in Burgin, Kentucky. The project involves the complete removal and disposal of regulated asbestos-containing materials (ACMs) from the interior and exterior of a boiler house originally constructed in 1937. The scope of work includes abating asbestos from four existing boilers, all associated piping, elbows, valves, breeching, ductwork, and related fittings. All asbestos-containing materials must be managed, transported, and disposed of as friable waste at a permitted landfill in compliance with the Kentucky Energy and Environment Cabinet and other applicable authorities. A pre-bid meeting was scheduled for October 29, 2020, at 9:30 AM Eastern Time at the project site, with background checks required for site access. The bid closing date was initially scheduled for multiple dates but was ultimately changed to January 21, 2021, at 2:00 PM. All bid submissions were required to be made electronically through the Owner's Document Collaboration System (eCommunications), with no physical deliveries accepted due to COVID-19 restrictions.

The project base bid is estimated at 375 tons of total abated and disposed material, with unit pricing to be provided by bidders and used to reconcile and adjust final costs based on actual quantities documented on the disposal manifest from the approved permitted landfill. This pricing structure allows for adjustments between the estimated and actual tonnage removed. The solicitation required all forms to be completely filled out at time of submission, with bidders instructed to identify their firm's position as prime bidder, miscellaneous subcontractor, material supplier, or other entity. All project documents, including bid documents, specifications, and drawings, were available through the State Plan Room at no charge for electronic downloads, with hard copies available for an additional fee. Contact for procurement administration was Kristi Sharp, CPPB, at the Division of Engineering and Contract Administration, with project engineering support provided by Jeff Lee of Lee Engineering, LLC.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document ID: RFB 785 2100000220 Page: 1

Commonwealth of Kentucky

SOLICITATION MODIFICATION

Addenda: Yes Addenda #: 5

TITLE: RFB-107-21 Asbestos Abatement, Old Boiler House NTC Burgin

Date Issued:

12/21/20 Record Date:

2020-12-21

Solicitation Closes Date:

1/21/21 Time:

14:00

Solicitation No:

RFB 785 2100000220

Online Bidding Prohibited: Yes

For Information Call:

Kristi Sharp 502-564-3636

Bid Receiving Location:

Finance - Division of Engineering & Contract Administration Bid Clerk The Bush Building, 403 Wapping St, 2nd Floor

Frankfort KY 40601

Vendor Customer Number:

Vendor Name:

Phone Number:

Fax Number:

Email Address:

Ordering

Address:

City, State, Zip:

Contact Name:

Contact Email:

Contact Phone Number:

Payment

Address:

City, State, Zip:

Contact Name:

Contact Email:

Contact Phone Number:

Ownership Type

__ Sole Proprietorship __ Partnership __ Corporation __ Other_________________________

SIGNATURE OF AUTHORIZED AGENT IS REQUIRED UNLESS RESPONSE

IS SUBMITTED ELECTRONICALLY. FAILURE TO SIGN SHALL RENDER

THE BID INVALID.

Signature X_________________________________________ FEIN#____________________ Date____________

All offers subject to all terms and conditions contained in this solicitation.

Document ID: RFB 785 2100000220 Page: 2

Line Items

Commodity Group: Default

Line CL Description Quantity UOM Unit Cost Line Total or Contract Amnt

1 RFB-107-21 Asbestos Abatement, Old Boiler House NTC Burgin

Comm Code Comm Description Manufacturer Model # Manuf Part #

912 CONSTRUCTION SERVICES, GENERAL

(INCL. MAINTENANCE AND REPAIR

Extended Description The boiler house was built circa 1937 and renovated in subsequent projects. The four existing boilers are all similar in design and appearance. The boiler house is slated for eventual demolition by others, but the scope of this project is to abate regulated asbestos containing materials from the interior and exterior of the boiler house.

The regulated ACMs include friable thermal insulating materials in the boiler walls and on piping and associated fittings and joints. An asbestos survey has been completed for this project.

Abate Asbestos From 4 Boilers Remove all asbestos from the fire box (walls, floors, and tops), steam drum, mud drum, and any other component considered part of the boiler system. Abate Asbestos From Piping and Associated Fittings Remove all asbestos from all piping, elbows, valves, breeching, ductwork and any other fittings.

Manage, transport, and dispose asbestos containing materials as a friable waste in a permitted landfill. Contractor to comply with all authorities having jurisdiction including but not limited to those of the Kentucky Energy and Environment Cabinet.

Project Base Bid will be based on 375 Tons estimate of total abated and disposed material. Unit pricing provided will be used to reconcile and adjust based on total quantities provided from Disposal Manifest from approved permitted landfill.

Shipping Information

Billing Information Finance - Division of Engineering & Contract Administration

The Bush Building, 403 Wapping St 1st Floor

Frankfort KY 40601

Document ID: RFB 785 2100000220 Page: 3

Submission Checklist

The following items will be required to be submitted with bid:

Item

There will be a pre-bid on the above referenced project. Representatives of the Facilities and Support Services, and Dept of Corrections will meet contractors at 9:30 AM, Eastern Time on 10/29/2020 at Northpoint Training Center, 710 Walter Reed Drive, Danville, Kentucky. This is the only time a site tour will be conducted and all interested contractors are encouraged to attend. Background checks will be performed prior to admittance into the facility. The background check form must be submitted to Warden Brad Adams at Brad.Adams@ky.gov by close of business on

October 26, 2020. List at least two people on the background check form.

When forwarding the background check form DO NOT COPY ANYONE; ONLY

SEND TO MR. ADAMS. Please limit attendance to the prebid meeting to one representative per company. Be prepared for temperature checks at various state agency entry points. If you have a fever, you will be turned away. Face masks are also required by employees/contractors when working, traveling or meeting in groups or in common areas (breakrooms, hallways, etc.).

: Jeff Lee, Lee Engineering, LLC, Phone: (502) 859-0190, jlleeeng@bellsouth.net

: Scott Baker, Division of Engineering, Phone: (502) 564-5850, Scott.Baker2@ky.gov

Tony Waddell, Dept of Corrections, Phone: (502) 330-4720, tonya.waddell@ky.gov

Kristi Sharp, CPPB, Division of Contract Administration, Phone: (502) 564-3636, Kristi.Sharp@ky.gov https://www.stateofkyplanroom.com/View/Default.aspx. For customer

Document Description Page 4

2100000220 RFB-107-21 Asbestos Abatement, Old Boiler House NTC Burgin mailto:Brad.Adams@ky.gov https://www.stateofkyplanroom.com/View/Default.aspx service you may contact Lynn Imaging, Phone: 1-800-888-0693. There is no charge for plans and specifications. Contractors will need to download bid documents, specifications and drawings. If contractors want a hard copy, they can choose to pay for this option. Contractors that receive plans and specifications from other sources as a planholder and .

. For all other project information you must visit the State Plan Room.

All documents related to this project shall be submitted, transmitted, transferred, reviewed, approved or rejected, and/or otherwise processed using the Owner's Document Collaboration System (eCommunications) which is the Owner's web-based document collaboration system that shall be used by all project participants. No submission, transmittal, transfer, review, approval or processing shall be deemed Official without the use of this system.

It is important that requesting firms identify the position of their firm as to the PRIME BIDDER, MISC. SUBCONTRACTOR, MATERIAL

SUPPLIER OR OTHER.

Due to the COVID-19 virus, the Bush Building is closed until further notice.

to the Bush Building. All forms in your bid document shall be completely filled out when your bid is submitted.

In structions are included in the solicitation.

I Bidders are encouraged to take a screen

Document Description Page 5

2100000220 RFB-107-21 Asbestos Abatement, Old Boiler House NTC Burgin shot verifying bid submittal. This is a secure website, no one can see these bids but the buyers. They are date and time stamped when submitted.

Please note that the instructions for MOVEit state that contractors will be notified when their bid is received. Buyers will NOT be notifying contractors.

All results will be posted to Lynn Imaging planroom after the bid opening and review. If additional information is needed from the successful bidder the buyer will be in contact.

NOTE: Your bid must be sent in time to arrive prior to the bid closing date and time.

Bidder assumes full responsibility for timely delivery of the bid in compliance with the above described procedures and conditions.

Bidder assumes full responsibility for timely delivery of the bid in compliance with the above described procedures and conditions.

Document Description Page 6

: RFB-107-21

Asbestos Abatement Old Boiler House Northpoint Training Center Burgin, Kentucky

October 22, 2020

Due to the COVID-19 virus, the Bush Building is closed until further notice. Bids will no longer be accepted via postal carrier (USPS, UPS, FED EX, etc.) nor can bids be delivered to the Bush Building. All forms in your bid document shall be completely filled out when your bid is submitted.

. Instructions are attached.

I

. This is a secure website, no one can see these bids but the buyers. They are date and time stamped when submitted.

Please note that the instructions for MOVEit state that contractors will be notified when their bid is received. Buyers will NOT be notifying contractors.

All results will be posted to Lynn Imaging planroom after the bid opening and review.

If additional information is needed from the successful bidder the buyer will be in contact.

Bidder assumes full responsibility for timely delivery of the bid in compliance with the above described procedures and conditions.

Document Description Page 7

Invitation to Bid No. RFB-107-21 For: Asbestos Abatement

Old Boiler House Northpoint Training Center Burgin, Kentucky

Kristi Sharp, CPPB, Statewide Procurement Analyst II Division of Engineering and Contract Administration

Document Description Page 8

Old Boiler House Northpoint Training Center Burgin, Kentucky

November 12, 2020

Item 1: Change official bid opening date to December 2, 2020. Time remains the same.

Invitation to Bid No. RFB-107-21 For: Asbestos Abatement

Old Boiler House Northpoint Training Center Burgin, Kentucky

Kristi Sharp, CPPB, Statewide Procurement Analyst II Division of Engineering and Contract Administration

Document Description Page 9

Old Boiler House Northpoint Training Center Burgin, Kentucky

November 23, 2020

Item 1: Change official bid opening date to December 22, 2020. All other bid information remains the same. The Commonwealth is working to get a final determination concerning the measures required to remove and process refractor brick and similar items that will be removed under this scope.

Invitation to Bid No. RFB-107-21 For: Asbestos Abatement

Old Boiler House Northpoint Training Center Burgin, Kentucky

Kristi Sharp, CPPB, Statewide Procurement Analyst II Division of Engineering and Contract Administration

Document Description Page 10

Old Boiler House Northpoint Training Center Burgin, Kentucky

December 21, 2020

Item 1: Change Official Bid Opening date the January 21, 2021. Time remains the same..

Invitation to Bid No. RFB-107-21 For: Asbestos Abatement

Old Boiler House Northpoint Training Center Burgin, Kentucky

Kristi Sharp, CPPB, Statewide Procurement Analyst II Division of Engineering and Contract Administration

Document Description Page 11

File details come from the government source that posted it. Updated .