Final_RFB_605_2600000512_1_SO_FORM.PDF
PDF 568 KB Posted
- Attached to
- Electrical Maintenance D9
- Solicitation number
- RFB 605 2600000512 1
- Issued by
- Kentucky
About this file
Summary: Electrical Maintenance D9 Request for Bid
This Request for Bid (RFB) document is issued by the Kentucky Transportation Cabinet Division of Purchases on behalf of Highway District 9 for electrical maintenance and repair services. The solicitation encompasses field construction, troubleshooting, and repair of traffic signals, flashing beacons, school flashers, and various lighting installations (roadway, aviation, bridge, pedestrian, rest area, weight station, intersection, tunnel, and navigation lighting) across ten counties: Bath, Boyd, Carter, Elliott, Fleming, Greenup, Lewis, Mason, Nicholas, and Rowan. The bid includes 90 line items with estimated quantities for labor (electricians, laborers, equipment operators), equipment (bucket trucks, line trucks, service vehicles, skid steer loaders, and specialized tools), materials (conduit, wire, cable, poles, cabinets, junction boxes), and installation services. The deadline for written questions is April 8, 2026 by 4:00 PM, with responses posted by April 13, 2026. Bids are due electronically by April 21, 2026 at 1:30 PM Eastern Time, with a tentative award date of June 1, 2026. The initial contract period runs from June 1, 2026 through May 31, 2027, with four optional one-year renewal periods available. The contract requires electronic bid submission through the Kentucky Vendor Self Service system, and all bidders must be pre-registered in the eProcurement system.
Pricing is the sole evaluation criterion (100 points), with the award going to the lowest-priced responsive bidder. Specific maximum hourly rates are established: electricians at $88.00 per hour, laborers at $58.00 per hour, equipment operators at $73.00 per hour, and on-call electricians at $10.00 per hour. The contractor must be licensed as an electrical contractor by the Department of Housing, Building, and Construction, maintain crews of at least three persons with at least one licensed electrician, carry Commercial General Liability Insurance of $1,000,000 per occurrence and $2,000,000 aggregate, and provide Automobile Liability Insurance and Kentucky Workers Compensation Insurance. The contractor must submit vehicle Identification Numbers (VINs), employee qualifications including IMSA certifications, and proof of Work Zone Traffic Control Supervisor and flagging credentials prior to award. No guarantee of quantities is provided; the Commonwealth is obligated only to the extent of needed services during the contract term. Price increases are not permitted during the first 12 months and thereafter require written justification based on industry-wide price changes. Prices remain firm for the contract period except as adjusted. The contractor is responsible for all equipment maintenance, damage to existing facilities, workmanship warranty for six months, and compliance with OSHA, KOSHA, National Electrical Code, and KYTC Standard Specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| How to Submit an Online Response - March 2023.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Document ID: RFB 605 2600000512 Page: 1
Commonwealth of Kentucky
SOLICITATION
Modification: No Version #:
TITLE: Electrical Maintenance D9
Date Issued:
04/03/2026 Record Date:
04/03/2026
Solicitation Closes Date:
04/21/2026 Time:
13:30
Solicitation No:
RFB 605 2600000512
Online Bidding Prohibited: No
For Information Call:
LATASHA CHENAULT
502-782-5673
Bid Receiving Location:
Bid Receiving
See Terms & Conditions for Bid Submission Instructions
Other KY
Vendor Customer Number:
Vendor Name:
Phone Number:
Fax Number:
Email Address:
Ordering
Address:
City, State, Zip:
Contact Name:
Contact Email:
Contact Phone Number:
Payment
Address:
City, State, Zip:
Contact Name:
Contact Email:
Contact Phone Number:
Ownership Type
__ Sole Proprietorship __ Partnership __ Corporation __ Other_________________________
SIGNATURE OF AUTHORIZED AGENT IS REQUIRED UNLESS RESPONSE
IS SUBMITTED ELECTRONICALLY. FAILURE TO SIGN SHALL RENDER
THE BID INVALID.
Signature X_________________________________________ FEIN#____________________ Date____________
All offers subject to all terms and conditions contained in this solicitation.
Document ID: RFB 605 2600000512 Page: 2
Line Items
Commodity Group: Default Commodity Group
Line CL Description Quantity UOM Unit Cost Line Total or Contract Amnt
1 Electrician 200.00000 HOUR
Comm Code Comm Description Manufacturer Model # Manuf Part #
96883 Traffic Signal Maintenance and Repair
Extended Description Electrician
A maximum amount has been set for the hourly rate of this line item. This unit price shall not exceed $88.00.
***ONLY ONLINE BIDS WILL BE ACCEPTED FOR THIS RFB.***
Emailed and hard copies delivered by any method WILL NOT BE ACCEPTED.
See section 1.00 for Specifications.
See attached document How to Respond to an Online Bid through the Kentucky Vendor Self Service site (updated).pdf.
2 Laborer 500.00000 HOUR
Laborer
A maximum amount has been set for the hourly rate of this line item. This unit price shall not exceed $58.00.
See Section 1.00 for specifications
3 Equipment Operator 400.00000 HOUR
Equipment Operator
A maximum amount has been set for the hourly rate of this line item. This unit price shall not exceed $73.00.
Document ID: RFB 605 2600000512 Page: 3
See Section 1.00 for specifications.
4 Service Vehicle 100.00000 HOUR
Service Vehicle
5 30' Bucket Truck 100.00000 HOUR
30' Bucket Truck
6 50' Bucket Truck 50.00000 HOUR
50' Bucket Truck
Document ID: RFB 605 2600000512 Page: 4
7 Skid Steer Loader 5.00000 HOUR
Skid Steer Loader
8 Flatbed Truck 5.00000 HOUR
Flatbed Truck
9 Air compressor with Tools Including Jackhammer
5.00000 HOUR
Air compressor with Tools Including Jackhammer
10 Aerial Lift Device 5.00000 HOUR
Aerial Lift Device
Document ID: RFB 605 2600000512 Page: 5
11 1 1/2 ton Line Truck 40.00000 HOUR
1 1/2 ton Line Truck
12 Furnish and Install Rigid Steel Conduit 1/2" up to 1"
400.00000 FT
Furnish and Install Rigid Steel Conduit 1/2" up to 1"
13 Furnish and Install Rigid Steel Conduit 1 1/4" 150.00000 FT
Furnish and Install Rigid Steel Conduit 1 1/4"
Document ID: RFB 605 2600000512 Page: 6
14 Furnish and Install Rigid Steel Conduit 2" 200.00000 FT
Furnish and Install Rigid Steel Conduit 2"
15 Furnish and Install Rigid Steel Conduit 2.5" up to 4"
5.00000 FT
Furnish and Install Rigid Steel Conduit 2.5" up to 4"
16 Furnish and Install PVC Conduit 1/2" to 1" 400.00000 FT
Furnish and Install PVC Conduit 1/2" to 1"
17 Furnish and Install PVC Conduit 1 1/4" 300.00000 FT
Furnish and Install PVC Conduit 1 1/4"
Document ID: RFB 605 2600000512 Page: 7
18 Furnish and Install PVC Conduit 2" 2200.00000 FT
Furnish and Install PVC Conduit 2"
19 Furnish and Install PVC Conduit 2.5" to 4" 100.00000 FT
Furnish and Install PVC Conduit 2.5" to 4"
20 Furnish and Install Rigid Flex Conduit 3/4" to 2"
5.00000 FT
Furnish and Install Rigid Flex Conduit 3/4" to 2"
Document ID: RFB 605 2600000512 Page: 8
21 Wire No.4 or Smaller (does not include loop wire)
2500.00000 FT
Wire No.4 or Smaller (does not include loop wire)
22 Wire No.2 or Larger 200.00000 FT
Wire No.2 or Larger
23 Wire - Loop Wire (IMSA 51-7) 9000.00000 FT
Wire - Loop Wire (IMSA 51-7)
24 Cable - Signal Cables 3c, 5c, and 7c(IMSA 19-1)
10000.00000 FT
Cable - Signal Cables 3c, 5c, and 7c(IMSA 19-1)
Document ID: RFB 605 2600000512 Page: 9
25 Cable - Lead in Cable (IMSA 19-2) 10000.00000 FT
Cable - Lead in Cable (IMSA 19-2)
26 Cable - Multi-conductor 1200.00000 FT
Cable - Multi-conductor
27 Span Wire - 10,800lbs/15,400lbs or Similar 2500.00000 FT
Span Wire - 10,800lbs/15,400lbs or Similar
Document ID: RFB 605 2600000512 Page: 10
28 Cabinet - Model 332 Base - Mounted 5.00000 EA
Cabinet - Model 332 Base - Mounted
29 Cabinet - Model 336 Pole - Mounted 5.00000 EA
Cabinet - Model 336 Pole - Mounted
30 Cabinet - Lighting Cabinet - Base or Pole Mount
5.00000 EA
Cabinet - Lighting Cabinet - Base or Pole Mount
31 Enclosure - Other 5.00000 EA
Enclosure - Other
Document ID: RFB 605 2600000512 Page: 11
32 Pole - 35 ft. to 55 ft. Wooden 5.00000 EA
Pole - 35 ft. to 55 ft. Wooden
33 Pole - 45 ft. or Less, Steel (includes mast arm poles)
10.00000 EA
Pole - 45 ft. or Less, Steel (includes mast arm poles)
34 Pole - 46 ft. to 120 ft. Steel 5.00000 EA
Pole - 46 ft. to 120 ft. Steel
Document ID: RFB 605 2600000512 Page: 12
35 Pole - Pedestal 5.00000 EA
Pole - Pedestal
36 Pole - Roadway Luminaire 10.00000 EA
Pole - Roadway Luminaire
37 Tower - 20 ft. to 40 ft. Aluminum 5.00000 EA
Tower - 20 ft. to 40 ft. Aluminum
38 Furnish & Install Base - 46 ft. to 120 ft., Steel Pole
5.00000 CUYD
Furnish & Install Base - 46 ft. to 120 ft., Steel Pole
Document ID: RFB 605 2600000512 Page: 13
39 Furnish and Install Base - 45 ft. or less, Steel Pole
50.00000 CUYD
Furnish and Install Base - 45 ft. or less, Steel Pole
40 Furnish & Install Base - Luminaire 5.00000 CUYD
Furnish & Install Base - Luminaire
41 Furnish & Install Base -Pedestal 5.00000 CUYD
Furnish & Install Base -Pedestal
Document ID: RFB 605 2600000512 Page: 14
42 Furnish & Install Pad - Cabinet, Enclosure, or Tower
10.00000 CUYD
Furnish & Install Pad - Cabinet, Enclosure, or Tower
43 Traffic Signal 100.00000 EA
Traffic Signal
44 Pedestrian Signal 5.00000 EA
Pedestrian Signal
45 Pedestrian Push Button 5.00000 EA
Pedestrian Push Button
Document ID: RFB 605 2600000512 Page: 15
46 Accessible Pedestrian Push Button 5.00000 EA
Accessible Pedestrian Push Button
47 Signal - Electrical Service 5.00000 EA
Signal - Electrical Service
48 Furnish & Install 60 amp to 100 amp Lighting Electrical Serv
Furnish & Install 60 amp to 100 amp Lighting Electrical Serv
480 Volt Single Phase
Document ID: RFB 605 2600000512 Page: 16
49 Furnish & Install 200 amp Electrical Service 5.00000 EA
Furnish & Install 200 amp Electrical Service
480 Volt Single Phase
50 Furnish & Install Lighting Electrical Service 5.00000 EA
Furnish & Install Lighting Electrical Service
120/240 Volt
51 Signal - Ground Rod 5.00000 EA
Signal - Ground Rod
Document ID: RFB 605 2600000512 Page: 17
52 Lighting Conventional - Ground Rod 5.00000 EA
Lighting Conventional - Ground Rod
53 Furnish & Install Lighting - High Mast Ground Rod
Furnish & Install Lighting - High Mast Ground Rod
54 Junction Box Type B 30.00000 EA
Junction Box Type B
55 Furnish & Install Junction Box Type A 5.00000 EA
Furnish & Install Junction Box Type A
Document ID: RFB 605 2600000512 Page: 18
56 Junction Box Type C 5.00000 EA
Junction Box Type C
57 Loop Saw, Slot, and Fill 2600.00000 FT
Loop Saw, Slot, and Fill
58 Trenching & Backfilling 1000.00000 FT
Trenching & Backfilling
Document ID: RFB 605 2600000512 Page: 19
59 2" Rigid Steel Roadway Conduit Crossing 5.00000 FT
2" Rigid Steel Roadway Conduit Crossing
60 3" to 4" Rigid Steel Roadway Conduit Crossing 5.00000 FT
3" to 4" Rigid Steel Roadway Conduit Crossing
61 2" Rigid Steel Directional Boring 5.00000 FT
2" Rigid Steel Directional Boring
62 3" to 4" Rigid Steel Directional Boring 5.00000 FT
3" to 4" Rigid Steel Directional Boring
Document ID: RFB 605 2600000512 Page: 20
63 Install Above Ground Sensor 5.00000 EA
Install Above Ground Sensor
64 Install Radio/Wireless Router, Telephone Modem, Above Sensor
Install Radio/Wireless Router, Telephone Modem, Above Sensor
65 Program Above Ground Sensor Module Radio Wireless Router
Program Above Ground Sensor Module Radio Wireless Router
Document ID: RFB 605 2600000512 Page: 21
66 Install Sensor in Pavement 5.00000 EA
Install Sensor in Pavement
67 Remove Sensor 5.00000 EA
Remove Sensor
68 Luminaire Arm 5.00000 EA
Luminaire Arm
69 Sign 20.00000 EA
Sign
Document ID: RFB 605 2600000512 Page: 22
70 Install LED Module 30.00000 EA
Install LED Module
71 Install LED Pedestrian Signal Module 5.00000 EA
Install LED Pedestrian Signal Module
72 Luminaire - Cobra Head or Offset 30.00000 EA
Luminaire - Cobra Head or Offset
Document ID: RFB 605 2600000512 Page: 23
73 Luminaire - High Mast 5.00000 EA
Luminaire - High Mast
74 Luminaire - Wall or Ceiling Mount 5.00000 EA
Luminaire - Wall or Ceiling Mount
75 Luminaire - Navigation or Aviation 5.00000 EA
Luminaire - Navigation or Aviation
76 Fuse Connector 5.00000 EA
Fuse Connector
Document ID: RFB 605 2600000512 Page: 24
77 Replacement of Luminaire Bulb 100.00000 EA
Replacement of Luminaire Bulb
78 Remove and Reset Guardrail 5.00000 FT
Remove and Reset Guardrail
79 Furnish & Install Sod 5.00000 SQYD
Furnish & Install Sod
Document ID: RFB 605 2600000512 Page: 25
80 Furnish & Install AC or Solar School Flasher 5.00000 EA
Furnish & Install AC or Solar School Flasher
81 Furnish & Install AC or Solar Blinker Sign 5.00000 EA
Furnish & Install AC or Solar Blinker Sign
82 Replacement Door Plan 1.00000 LMP
Replacement Door Plan
83 Install Door for Replacement Door Plan 1.00000 LMP
Install Door for Replacement Door Plan
Document ID: RFB 605 2600000512 Page: 26
84 Move/Align Traffic Signal head/Pedestrian/ Sign
Move/Align Traffic Signal head/Pedestrian/Sign
85 Install transformer base only 5.00000 EA
Install transformer base only
86 Remove and install anchors 6.00000 EA
Remove and install anchors
Document ID: RFB 605 2600000512 Page: 27
87 F&I 200 amp Lighting Electrical Service (double disconnect)
6.00000 EA
F&I 200 amp Lighting Electrical Service (double disconnect)
88 Furnish and Install 36x36x36 Junction Boxes 6.00000 EA
Furnish and Install 36x36x36 Junction Boxes
89 Furnish and Install 48x48x48 Junction Boxes 6.00000 EA
Furnish and Install 48x48x48 Junction Boxes
90 On Call 5.00000 EA
On Call
Document ID: RFB 605 2600000512 Page: 28
Shipping Information KYTC District 9 - Fleming Co Traffic Facility
KY 32 B
Flemingsburg KY 41041
Billing Information KYTC District 9 - Flemingsburg District Office
822 Elizaville Rd PO Box 347 Flemingsburg KY 41041
Document ID: RFB 605 2600000512 Page: 29
Submission Checklist
The following items will be required to be submitted with bid:
Item Price
ELECTRONIC BID SUBMISSION
Bid responses shall be received by electronic submission in the eProcurement system.
Link: https://vss.ky.gov
An electronic bid shall be authorized by the proper agent of the firm by the act of submitting it electronically through the eProcurement system.
Bid information MUST be completed online. Response must contain all required information for the Solicitation.
All bidders MUST be registered in the Commonwealth eProcurement System via the Vendor Self Service System at https://vss.ky.gov
Allow 24 – 48 hours to complete Vendor Registration. Vendors must be logged in to their Vendor Self Service (VSS) account in order to submit a response. Registrations completed the day of bid closing must be completed by the Vendor in the VSS portal. The Customer Resource Center is not able to complete registrations and activate accounts on the same day. Closing dates will not be extended for Vendors not registered by the date/time of the bid closing. Vendor Self Registration Guides are provided at https://finance.ky.gov/eProcurement/Pages/ doing-business-with-the-commonwealth.aspx
All bidders are cautioned to begin their electronic submission in sufficient time to complete before the closing date and time. Delays due to technical difficulties or document upload impediments shall not be justification for acceptance of a late bid or proposal. Vendor attention to this advisory is encouraged. If you need assistance, please contact the Customer Resource Center (CRC) by email at Finance.CRCGroup@ky.gov or phone 502-564-9641 or toll-free 877-973-HELP (4357).
BID PRICES SUBMITTED ON COMPANY QUOTE FORMS ARE DISCOURAGED. COMPANY TERMS AND
CONDITIONS AND/OR SALES AND USE AGREEMENTS OFTEN CONFLICT WITH STANDARD SOLICITATION
REQUIREMENTS AND MAY RESULT IN REJECTION OF BID OFFER.
Online bid responses must be in an “Accepted” status and shall be assigned a date and time stamp from the eProcurement system at the time of final acceptance and formal submission by the vendor. The system will not allow submission of an online response after the published date and time for closing.
An offer may be modified or withdrawn by electronic or written notice ONLY if received prior to the bid closing date and time. An electronic offer may be modified by applying the appropriate electronic signature and following the procedure in the state’s eProcurement signature.
PUBLIC BID READINGS
Any person wishing to hear a bid reading may call the conference line at 866-830-9434, Participant Code 21327950, at 3:00 pm, Eastern Time on the bid closing date.
BID SUBMISSION CHECKLIST
The vendor MUST include the following with the bid submission. If the items below are not submitted with the bid, the Commonwealth MUST deem the bid non-responsive and SHALL NOT be considered for award.
_____ BID INFORMATION – COMPLETED (See Section 5.00)
All other items MUST be submitted prior to award however, vendors are strongly encouraged to include with bid submission.
_____ CERTIFICATE OF AUTHORITY – REGISTRATION WITH SECRETARY OF STATE BY FOREIGN
ENTITY (See Section 2.26)
_____ REQUIRED AFFIDAVIT(S) (See Attachments A, B, C, etc. as applicable)
Document Phase Document Description Page 30
2600000512 Final Electrical Maintenance D9 Total Pages: 74 https://vss.ky.gov https://vss.ky.gov https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx mailto:Finance.CRCGroup@ky.gov
_____ REQUIRED VINs (Section 1.08)
_____ EMPLOYEE QUALIFICATIONS (Section 1.09)
_____ CERTIFICATE OF INSURANCE (See Section 1.28)
PLEASE READ THIS SOLICITATION AND ITS INSTRUCTIONS IN ITS ENTIRETY.
This is a Request for Bid (RFB).
Vendors shall comply with the terms and conditions stated in the solicitation.
Any efforts to negotiate these terms and conditions SHALL NOT be accepted and SHALL cause the bid to be deemed non-responsive.
Vendors should review and comply with the general bidding requirements listed under “Procurement Laws, Preference, Regulations and Policies” and “Response to Solicitation” located on the eProcurement Web page at https://finance.ky.gov/eProcurement/Pages/procurement-laws-regulations-and-policies.aspx and https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx respectively. The vendor must comply with all applicable statutes, regulations and policies related to this procurement.
Section 1 - Scope of Work – Service
1.00#Specifications of Service Requirements
MILEAGE IS INCIDENTAL TO THIS CONTRACT AND IS NO LONGER A PAY ITEM.
ANY TRAFFIC CONTROL BY THE CONTRACTOR SHALL BE INCIDENTAL TO THE WHOLE
CONTRACT.
ELECTRICAL MAINTENANCE AND REPAIR CONTRACT
1.01 – SCOPE OF WORK
The scope of this contract shall include, but not be limited to, the following type of work:
# Field construction, troubleshooting, and repair of:
# Traffic signals # Flashing beacons # School flashers # Lighting (i.e., roadway, aviation, bridge, pedestrian, rest area, weight station, intersection, tunnel, and navigation lighting)
1.02 - LOCATIONS
All work on this contract shall take place in the following counties: Bath, Boyd, Carter, Elliott, Fleming, Greenup, Lewis, Mason, Nicholas, Rowan.
The Contractor shall provide technical expertise, labor, working equipment, and all tools necessary for the work associated with this contract. The Contractor shall be licensed by the Department of Housing, Building, & Construction as an Electrical Contractor. The Contractor should have at least a three (3) person crew for all work on this contract.
Document Phase Document Description Page 31
2600000512 Final Electrical Maintenance D9 Total Pages: 74 https://finance.ky.gov/eProcurement/Pages/procurement-laws-regulations-and-policies.aspx https://finance.ky.gov/eProcurement/Pages/doing-business-with-the-commonwealth.aspx
One employee on the crew shall be a License Electrician per the Department of Housing, Building, & Construction.
The Contract Manager shall have the final decision on the number of vehicles and persons for each crew.
All electrical work shall be conducted or supervised by a licensed electrician. Non-electrical work may be supervised by personnel without an electrical license. If questions arise, the Contractor Manager shall make the final determination as to what work needs to be supervised by a licensed electrician. The Contract Manager may require the replacement of an individual who is not performing satisfactorily.
1.03 - ELECTRICAL TRAFFIC CONTROL DEVICES WORK
The Contractor’s vehicles per signal job shall consist of two vehicles per 3-person crew. If additional vehicles are needed, the contractor shall get prior approval from the Contract Manager to add any other vehicles for each crew. The Contractor shall use bucket trucks with a maximum working height in the range of thirty (30) feet when doing signal work on this contract. If a larger bucket truck is required for signal work, the Contractor shall get prior approval from the Contract Manager before larger bucket trucks will be allowed to be used on this contract.
By the end of the initial contract term, the Contractor shall be able to furnish one person for each field crew who is certified in IMSA Level II (field or construction) or the contract will not be renewed.
1.04 - LIGHTING WORK
The Contractor’s vehicles per lighting job shall consist of a service and bucket truck per crew. If additional vehicles are needed, the Contractor shall get prior approval from the Contract Manager to add any other vehicles for each crew. The Contractor shall use bucket trucks with a maximum working height in the range of fifty (50) feet when doing lighting work on this contract. If a larger bucket truck is required for lighting work, the Contractor shall get prior approval from the Contract Manager before larger bucket trucks will be allowed to be used on this contract.
By the end of the initial contract term, the Contractor shall be able to furnish one person for each field crew who is certified in IMSA Lighting Level I, or the contract will not be renewed.
1.05 - STANDARDS
All work shall be completed in a professional manner and meet the requirements of the local utility, any supplied drawings or plans, the latest editions of the National Electrical Code, the Manual on Uniform Traffic Control Devices, the Kentucky Department of Highways’ Standard Specifications for Road and Bridge Construction including all current supplemental standard specifications, and special notes (with the exception of Section 109) and the Division of Highway Design Standard Drawings. All work shall be done in accordance with the Division of Traffic Operations’ specifications for signals and lighting. The Contractor shall be responsible for conforming to all OSHA and KOSHA safety requirements for all work performed.
The Division of Traffic Operations’ specifications for signals and lighting can be found under Traffic Design Standards and Tools on the Division of Traffic Operations webpage:
https://transportation.ky.gov/TrafficOperations/Pages/Design-Services-Branch-Standards-and-Tools.aspx
The Kentucky Department of Highways’ Standard Specifications for Road and Bridge Construction can be found on the Division of Construction’s webpage:
https://transportation.ky.gov/Construction/Pages/Kentucky-Standard-Specifications.aspx
The Manual on Uniform Traffic Control Devices can be found at:
http://mutcd.fhwa.dot.gov
Standard Drawings of various items can be found on the Division of Highway Design’s webpage:
https://transportation.ky.gov/Highway-Design/Pages/Standard-Drawings.aspx
1.06 - PUBLIC INFORMATION
The Contractor shall notify the Contract Manager three (3) business days in advance of any planned work that might significantly impact traffic flow in case the District wants to relay this information to the public.
1.07 - TERMINATION OF CONTRACT
Document Phase Document Description Page 32
2600000512 Final Electrical Maintenance D9 Total Pages: 74 https://transportation.ky.gov/TrafficOperations/Pages/Design-Services-Branch-Standards-and-Tools.aspx https://transportation.ky.gov/Construction/Pages/Kentucky-Standard-Specifications.aspx http://mutcd.fhwa.dot.gov https://transportation.ky.gov/Highway-Design/Pages/Standard-Drawings.aspx
In the event the contract is terminated for any reason, the Contractor shall be paid for the work performed or services rendered up to and including the date of cancellation.
In the event the parties cannot reach a mutual agreement as to the amount of work performed or services rendered then, the matter shall be submitted to the Secretary of the Kentucky Transportation Cabinet for review. The decision by the Secretary of the Kentucky Transportation Cabinet shall be final and binding on both parties.
1.08 - DOCUMENTATION OF VEHICLE QUALIFICATIONS
All bucket trucks and line trucks shall be maintained in good working condition, safe, reliable, and mechanically sound.
Prior to award the Contractor shall submit VIN’s of all bucket trucks and line trucks that will be used on this contract.
If the contractor will be using a rental truck, the Contractor shall submit VIN’s for verification of the age requirement.
The Contractor shall submit the titles to the Contract Manager for all bucket trucks and line trucks that are used on this contract before any truck can be used on this contract. The Contract Manager may require the replacement of any equipment that is not performing satisfactorily.
1.09 - DOCUMENTATION OF EMPLOYEE QUALIFICATIONS
The Contractor shall submit the following information:
• Proof of Electrical Contractor license issued by Department of Housing, Building, & Construction
• Proof of electrician license issued by Department of Housing, Building, & Construction for each crew
• Staffing plan
• Proof of certification for the International Municipal Signal Association (IMSA) Level 1 and 2 (Field or Construction) for all Electricians – All IMSA certifications shall be valid and up to date
• Diplomas
• Work Zone Traffic Control Supervisor Qualification (WZTCS) – Contractor is required to have at least one qualified Work Zone Traffic Control Supervisor on the crew – qualifications shall be current within five (5) years (qualifying classes can be found online at the Kentucky Transportation Center (KTC), the American Traffic Safety Services Association (ATSSA), and the Kentucky Laborers’ Joint Apprenticeship & Training Trust Fund)
• Flagging credentials – All employees shall have this requirement – Qualifications shall be current within 5 years
• Any other supporting documentation requested for each employee initially assigned to the contract
The Contractor shall submit all information necessary to verify experience and training. This staffing plan shall be submitted prior to award. The Cabinet shall verify all credentials prior to award of contract.
Pre-approved personnel shall comprise the actual field crews when work commences. Substituting less experienced personnel after award of contract may result in termination of the contract.
Field crews shall submit credentials to the Contract Manager, including IMSA, WZTCT, and WZTCS certifications (including contact info) prior to beginning work. Anytime that new crews or personnel are added, credentials shall be supplied to the Contract Manager prior to work commencing. Documentation of credentials will be required for each new employee added to the contract.
1.10 - EMPLOYEE QUALIFICATIONS
Electricians shall meet all of the following qualifications:
# Licensed electrician issued by the Department of Housing, Building, & Construction # IMSA Traffic Signal Technician I & IMSA Traffic Signal Technician II (Field or Construction) certification shall be renewed with IMSA. All electricians shall have this certification within six (6) months of the start of the contract. Proof of certification shall be sent to the Contract Manager upon renewal of contract. If certification is not presented, the contract will not be renewed.
# IMSA Roadway Lighting I certification – All electricians shall have this certification within six (6) months of the start of the contract. Proof of certification shall be sent to the Contract Manager upon renewal of contract.
If certification is not presented, the contract will not be renewed.
Document Phase Document Description Page 33
2600000512 Final Electrical Maintenance D9 Total Pages: 74
# Work Zone Traffic Control Supervisor Qualification – A crew member shall have this qualification # within six (6) months of the start of the contract.
# Work Zone Traffic Control Technician Qualification – All crew members shall have this certification within six (6) months of the start of the contract.
# Flagging credentials # Sufficient documented experience and training in the fields of traffic electronics, telecommunications, sensors, wireless data and related technologies # Individual shall be knowledgeable of the electrical safety codes and National Electrical Code.
# All individuals shall be familiar with the equipment being serviced and shall be capable of replacing components, rebooting equipment, and initial troubleshooting.
The electrician shall perform the following tasks:
# Correspond with the Contract Manager to coordinate staffing levels with upcoming work # Correspond with the Contract Manager upon receiving work orders to determine scope of work # Coordinate with the Contract Manager to procure necessary materials or pick up spare parts # Coordinate traffic control measures with the Contract Manager and district personnel # Coordinate with electrical, telephone, and other utilities for location of services # Supervise traffic control work # Perform on-site management of installation tasks # Perform initial or simple field troubleshooting # Coordinate with equipment manufacturers to resolve problems # Perform field device replacement, calibration, installation and rebooting # Perform installation tasks # Perform device rebooting # Perform traffic control work # Perform inspection, inventory and testing # Perform preventative maintenance # Perform coaxial and fiber terminations # Perform inspections and quality control functions # Manage the Laborer(s) and Equipment Operator # Complete/Review daily field sheets # Review monthly billing reports for accuracy # Provide technical support and training for the Laborer(s) # Provide technical information to the Contract Manager # Act as primary contact between the Contractor and the Contract Manager # Perform shipping and receiving functions for warranty replacement
Laborers and equipment operators shall have the following certifications and qualifications:
# Work Zone Traffic Control Technician Qualification. All laborers and equipment operators shall have this certification within six (6) months of the start of the contract.
# Flagging credentials Laborers shall have experience in basic electrical construction practices. Laborers shall be competent to operate all tools and light equipment. Individuals shall be supplied with additional tools and equipment as necessary.
Equipment operators shall have a Commercial Driver’s License (CDL) to transport and operate heavy equipment.
Equipment operators shall be physically and mentally competent to operate equipment in a safe and efficient manner.
Individuals shall be supplied with additional tools and equipment as necessary.
1.11 - EQUIPMENT FOR ELECTRICIANS
At a minimum, electricians shall be equipped with, and familiar with, the operation of the following equipment:
# Complete set of electronic and electrical hand tools # Soldering pen # Voltmeter # Coaxial stripping and crimping tools for video and RF cable # Cable Locator
Document Phase Document Description Page 34
# Wire Tracer # Laptop computer with modem and internet, email access (one per crew and for on-call services) # Windows 10 device with USB and WIFI capability # Ethernet port/USB-to-Ethernet adapter # Web browser # Admin rights on your computer # Cellular telephone with KY statewide coverage (one per crew) # Digital Camera (one per crew) # Global Positioning System (GPS) receiver (one per crew) # Clamp-on ground resistance tester
Individuals shall be supplied with additional tools and equipment as necessary.
1.12 - QUANTITY
There is no guarantee of the quantity mentioned in this invitation, and the Cabinet is obligated only to the extent of the needed services during the term of the contract.
1.13 - WORK ORDERS
The Contract Manager shall provide a written work order via email for all work. We recommend that a delivery order in eMARS is created for each work assignment before the end of the required work. This work order will contain the following information:
# Location of work # Description of work # Special instructions or revised installation details # Priority and expected response time
The Contractor shall coordinate with the Contract Manager via email before beginning work to resolve any questions about the work order. If work is not assigned through a work order, the Contract Manager shall email the Contractor with a list of the work done each day that includes the following:
# Location of work # Description of work
1.14 - WORK/TIME POLICY
It is anticipated that some repair tasks will occur outside of normal working hours. We estimate that this work will not exceed 12% of the total hours per individual. The Contractor shall be responsible for providing the labor and equipment necessary to conduct such work at the contract price.
The Contractor shall be restricted to normal work hours of between 8:00 am to 4:30 pm, five (5) days a week. If any deviation is required, there shall be approval from the Contract Manager. The Contract Manager has the right to deviate the hours to accommodate inspection schedules. The Contractor shall not perform routine work on holidays and/or holiday weekends without prior approval from Contract Manager or designee. The Contractor shall not perform routine work during active KYTC snow and ice operations without prior approval from Contract Manager or designee.
The Contractor can see this information on the goky.ky.gov website.
1.15 - RESPONSE TIMES
Routine Work:
Upon notification by the Contract Manager, the Contractor and all necessary equipment shall be on-site and working within five (5) working days.
Emergency Work:
Emergency work shall consist of situations where malfunctioning, downed, or damaged equipment is creating an immediate safety hazard.
Emergency work may include, but is not limited to, the following:
# Traffic signal in roadway
Document Phase Document Description Page 35
# Signal/lighting pole in roadway # Luminaire hanging from a pole # Signal head hanging from span # Fire caused by a short circuit at signal/lighting installations # Report of navigation/aviation light outage
The Contractor shall be readily available to the Contract Manager at all times in case of an emergency situation, either through a cell phone equipped with voice mail or other suitable means. Once contacted, the Contractor shall immediately mobilize to respond to emergency work and be on-site with all necessary equipment and working within four (4) hours.
1.16 - INVOICING AND FIELD SHEETS
The Contractor shall submit monthly invoices, including original daily field reports and detail summary spreadsheets.
Invoice quantities shall equal the sum of the daily field reports. Daily reports signed by the KYTC designee will not be the official record for the hourly and items done on a daily basis. The Contract Manager shall have the final decision of what items and hours worked will be paid on the monthly invoice. This decision will be based on the Contractor’s daily reports, KYTC designee daily reports, and the work orders that are finished during the time period for this monthly invoice. Field report summary spreadsheets shall be delivered in an Excel format agreed upon between the Contractor and Contract Manager. We require that the contractor use the attached Excel spreadsheet to do the daily field reports on the computer that each electrician is required to have. The Contractor can submit an alternative way to digitally provide the daily field sheet. This alternative shall be submitted in your documentation and will be approved/disapproved by KYTC Traffic Operations. This alternative shall have at least a way to do daily field reports and add all daily field reports digitally for the final report for the invoice. This alternative shall be accessible to the Contract Manager.
A daily field report shall be submitted for each construction work site and shall include a detailed description of the work performed each day. The daily field report shall include details of all bid items or hourly items used for each work site each day. Maintenance, troubleshooting, or inspection at multiple sites in a single day may be combined on a single field report with the approval of the Contract Manager. To reduce confusion, the daily field report shall only include information related to billing and shall not include information that the Contractor needs for their own purposes (such as daily time reporting).
The Contractor shall notify the Contract Manager of any work conducted by a non-licensed individual that the Contractor feels should qualify for the electrician pay rate. The Contractor shall notify the Contract Manager for approval of such situations before the non-licensed individual does any work as an electrician. When electrician pay is approved for non-licensed individuals, the Contractor shall be required to send the Contract Manager proof that non-licensed employees received electrician pay rate for qualifying work.
Common examples where unlicensed employees would be paid as an electrician may include the following activities:
Possible electrician’s activities to be paid as an electrician:
# Pulling wire # Pushing wire # Resplicing wire # Placing conduit (pvc or rigid) in ground or above ground # Connecting conduit (pvc or rigid) # Connecting wiring in signal/ped head/detectors # Hanging a signal head/ped head/detector # Troubleshooting a loop amp/controllers/loadswitch/conflict monitor # Reinstalling loop amp/controllers/loadswitch/conflict monitor # Cleaning filter in electrical cabinet # Replacing light bulb in cabinet # Connecting wiring for led modules/luminaires # Installing grounding bushing # Troubleshooting grounding system # Installing ground rod # Installing wire from ground rod to device # Placing wiring in saw slot for loops # Replacing fuses
Document Phase Document Description Page 36
# Replacing fans # Replacing power supplies # Replacing thermostat # Replacing traffic or lighting cabinet # New service # Replacing service # Installing camera # Replacing camera # Installing antenna # Replacing antenna # Installing surge arrestor # Connecting communication cable # Making connections for communication cables # Installing detection pucks in pavement # Installing luminaire heads # Installing navigation/aviation lights # Megging loops/wire # Testing grounding resistance # Installing photocell # Replacing photocell # Replacing roadway luminaire ballast # Troubleshooting/replacing internal components of lighting cabinet # Troubleshoot lighting circuits # Installing/replacing disconnect # Diagnostic testing (voltage, resistance, amperage, etc.)
# Replacing high mast pole breakers # Replacing high mast fixture ballast kits # Lowering high mast fixtures
The Contractor shall submit field reports for every traffic signal they respond to while being on-call. The field report shall include all materials, hours worked at each signal, AVL verification report, and all equipment used by the Contractor. A separate report detailing the date, time of notification, intersection, reported issue & source of reported issue, findings of investigation, materials/equipment replaced/used, time technician left the intersection, and the name and signature of technician.
1.17 - MATERIALS
The Cabinet will provide all materials except for bid items that are listed as furnish and install.
The Contractor shall pick up materials at the Frankfort Equipment Warehouse, pole yard, district maintenance yard, or other location as required by the Contract Manager. This mileage shall be incidental to the whole contract. Contractor personnel that transport materials will be paid hourly for one equipment operator and one laborer for the hourly bid item for personnel (maximum of two individuals), and the Contractor will be paid hourly for the vehicle that is used to transport materials. If vehicles used do not require a CDL to operate, payment will be hourly for two laborers instead of what is stated above. When the Contractor picks up materials from the district maintenance yard, they shall not be paid for hourly bid items (including equipment and personnel).
The Contractor may have to maintain a stock of materials to facilitate on-call first response. This stock will be determined by the Contract Manager and will be given to the Contractor the day they are notified. All materials shall be signed for by the Contractor. The Contractor shall be responsible for the safe storage of this equipment and the replacement of any equipment damaged or lost. All unused materials shall be returned to the Cabinet at the end of the on-call time period. If the Contractor runs out of materials, it is the responsibility of the Contractor to contact the Contract Manager/designee to acquire more materials. The stock of equipment may include items such as controllers, detectors, load switches, relays, flashers, conflict monitors, LEDs and power supplies. The Contract Manager will determine the extent of the Contractor’s stock. The Contractor is responsible for providing the Contract Manager a list of all materials and locations of the materials that were used during the on-call period. This information is required for tracking materials and auditing purposes.
Document Phase Document Description Page 37
1.18 - REMOVAL OF EXISTING EQUIPMENT
Removal of all existing equipment shall be paid for on an hourly basis except if included in the bid item. The transport of materials that are deemed recyclable/salvageable by the Contract Manager to Cabinet-owned facilities shall be paid for on an hourly basis and the mileage shall be incidental to the whole contract. The transport of disposable materials (as determined by the Contract Manager) shall be incidental to this Contract. Contractor personnel that transport materials will be paid hourly for one equipment operator and one laborer for the hourly bid item for personnel (maximum of two individuals), and the Contractor will be paid hourly for the vehicle that is used to transport materials. If vehicles used do not require a CDL to operate, payment will be paid hourly for two laborers instead of what is stated above.
The Cabinet will not pay for any support vehicles that do not transport the materials or any personnel that is over the maximum set forward in this contract.
This includes all materials removed from the project site except for any plastic materials (does not include traffic signals or blankout signs) or wood poles. All plastic materials or wood poles shall be properly disposed of by the Contractor off the project. All materials minus the exceptions shall be returned to the Cabinet as directed by the Contract Manager.
The Contract Manager shall dispose of all materials per the Cabinet’s policy.
1.19 - RECORDS RETENTION
The Contractor shall maintain books, documents, papers, electronic accounting records, and other evidence pertaining to costs incurred and make such materials available at their respective offices at all reasonable times during the contract period and for five (5) years from the date of final payment under the contract for inspection by the Cabinet, and copies thereof shall be furnished if requested. The Cabinet has the right to audit these records at any time.
1.20 - COMMUNICATIONS
The Contractor shall maintain daily communication with the Contract Manager to coordinate work and materials required.
1.21 - DAMAGE TO EXISTING FACILITIES
The Contractor shall coordinate with the applicable underground location services and local utilities before beginning any excavation task. The Contractor shall be responsible for all costs to repair any public or private underground or overhead infrastructure damaged during construction.
1.22 - WORKMANSHIP / WARRANTY
All work shall be performed in a professional manner. Work areas shall be cleaned up upon completion of the task. Cleanup shall include removal of all trash and debris in the work area. The Contractor shall warrant that all workmanship complies fully with the requirements of the contract specifications. Should any defect appear within six months after the project is completed due to inferior workmanship, the Contractor warrants that he will do immediately whatever is necessary to remedy the defects without additional cost to the Cabinet.
The Contractor shall notify the Contract Manager of existing material that is damaged, defective, or worn immediately upon identification of such material.This includes any worn signal mounting hardware, damaged wiring, bad splices, etc.
1.23 - POLE HANDHOLE COVERS, TRANSFORMER BASE DOORS, AND JUNCTION BOX LIDS
The Contractor shall reinstall all pole handhole covers, transformer base doors, and junction box lids for traffic control devices and lighting installations during any tasks. The contractor shall reinstall pole handhole covers/doors, transformer base doors, and junction box lids upon completion of work on each individual item and prior to leaving the work site. If the pole handhole covers, transformer base doors, and junction box lids are missing or cannot be reinstalled through conventional methods due to damage, the Contractor shall contact the Contract Manager with details of each location so that replacements can be ordered. The Contractor shall attempt to secure damaged pole handhole covers, transformer base doors, and junction box lids until replacements are received. Any labor, equipment or materials used to reinstall or attempt to secure pole handhole covers/doors, transformer base doors, and junction box lids shall be incidental. If replacement pole handhole covers/doors, transformer base doors, and junction box lids become available prior to completion of all required tasks on the work site, the contractor shall install these items at no additional cost to KYTC. The Contract Manager will make the final determination on when a project is called
Document Phase Document Description Page 38 complete. If the replacement is received after the project is called complete, the contractor will be paid hourly and equipment used to reinstall the item. Notify the Contract Manager if the junction box is badly damaged.
1.24 - END OF CONTRACT
At the end of the contract period all work shall be stopped. No payments for work shall be paid after the date the contract ends. The Contract Manager shall only schedule work that can be done by the end of the contract ending date. If the Contractor is still on the job, the Contractor shall be paid for the work that he has already done but shall not be paid for work that is done after the contract ending date.
1.25 - LIQUIDATED DAMAGES
The Contract Manager shall notify the Contractor by email of any of the conditions listed below. The Contractor shall complete all repairs within stated time frames and notify the Contract Manager by email upon completion of requested work. The contract manager is responsible for how liquidated damages are applied and may consider a weather-related event for extension of the days involved in the liquidated damages.
The Contractor will be subject to liquidated damages of $500 per day per occurrence until item is completed for the following conditions:
• If the installation of a full traffic signal is not completed within fourteen (14) business days.
• If the installation of one loop, piezoelectric sensor, and in-ground or above ground sensor is not completed within one (1) business day.
• If the installation of any steel strain pole base is not completed within four (4) business days.
• If the installation of a luminaire base, pedestrian pedestal base and pad is not completed with one (1) business day.
• If the on-call individual does not arrive at the first signal within two (2) hours of being called and will receive additional $500 each additional hour until he arrives.
• If the Contractor does not have all necessary/working equipment on-site for routine work within five (5) business days.
• If the Contractor does not have all necessary/working equipment on-site for emergency work within four (4) hours.
• If equipment that is requested by the Contract Manager is not on site within three (3) business days.
• If the Contractor provides a bucket truck or line truck that is older than twelve (12) years.
• If the Contractor does not complete all items on work order before the Contractor leaves the district. If the Contractor receives additional work orders while he is in the district, the Contractor shall remain in the district until all work orders are complete.
• If equipment is not in working condition, the Contract Manager can request that the equipment be replaced/fixed within three (3) business days.
• Restoration of disturbed areas to original condition within three (3) business days.
• If the Replacement Door Plan is not received within two (2) months of the issued work order.
• If the installation of all replacement doors is not installed within two (2) months of the issued work order.
• If inspected work is found to not be in compliance with all applicable standards and is not corrected within three
(3) business days.
• If each pole handhole cover, transformer base door, and junction box lid is not reinstalled/secured or not reported to the Contract Manager if missing. This will be for each pole handhole covers, transformer base doors, and junction box handhole cover or junction box lid.
1.26 - BILLING - GENERAL
Labor and equipment hours shall be billed for:
Preventative Maintenance Tasks
Document Phase Document Description Page 39
Troubleshooting of Electronic Equipment Tasks
Removal of existing equipment (outlined in Removal of Existing Equipment Section)
Material/equipment pick-up from Cabinet owned facilities outside of the district (outlined in Materials Section)
Labor and Equipment hours shall not be billed for the installation of any material listed as a bid item.
Labor and Equipment hours shall not be billed for any individual providing on-call bid item duties.
There shall be no electrician, equipment operator, or laborer hours billed for any bid item because of supervision.
Any mileage incurred by the Contractor shall be incidental to the whole contract.
Any traffic control by the Contractor shall be incidental to the whole contract.
For work billed by the hour, the Cabinet will commence counting time for paying the Contractor at the time he arrives at the work site or district maintenance facility. The Cabinet will end counting time for paying the Contractor at the time he leaves the work site or district maintenance facility.
Example:
The electrician spends one hour troubleshooting a short in a traffic signal span. He spends three hours pulling in sixty (60) feet of new cable to a signal head. The quantities billed would be one hour of electrician time and sixty
(60) feet of cable.
1.27 - BEGIN LINE ITEMS
ITEM 1 - Electrician
A maximum hourly rate has been set for this line item. The unit price shall not exceed $88.00.
Electrician pay shall be paid to licensed electricians and to employees performing electrical work under the supervision of a licensed electrician. See invoicing and field sheets for common examples where unlicensed employees would be paid electrician pay.
ITEM 2 - LABORER
A maximum hourly rate has been set for this line item. The unit price shall not exceed $58.00.
ITEM 3 - EQUIPMENT OPERATOR
A maximum hourly rate has been set for this line item. The unit price shall not exceed $73.00.
EQUIPMENT – GENERAL
Equipment bid items shall be used for preventive maintenance, equipment repair, and installation of equipment and materials not listed under material bid items.
Equipment shall be maintained in good working condition, safe, reliable, and mechanically sound. The contractor shall submit the title to the contract manager for all bucket trucks and line trucks that are used on this contract. Equipment shall have at least two supplemental yellow flashing warning lights. Equipment shall have current safety certificates for use in the State of Kentucky. Equipment may be owned, rented, or subcontracted as required. The Contract Manager may require the replacement of any unit that is not performing effectively.
Hand tools and small power tools are incidental to the contract.
Equipment hours shall not be billed for any equipment provided during on-call bid items.
ITEM 4 - SERVICE VEHICLE
Unit shall be capable of transporting equipment, tools, and individuals.
This can only be billed when:
Document Phase Document Description Page 40
• Travelling to the Central Office warehouse to pick up or drop off materials, or
• Transporting materials from the Central Office warehouse to the district, or
• Employees are being paid hourly, and there is no other equipment (Line Items 5-11) that is eligible for reimbursement at an hourly rate.
Approval of Project Manager is required, prior to starting work, if more than one service vehicle is required for hourly work.
ITEM 5 - 30’ BUCKET TRUCK
Unit shall have a working height of thirty (30) feet.
ITEM 6 - 50’…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .