FINAL_PWS.pdf
PDF 766 KB Posted
- Solicitation number
- 191BWC26R0016
About this file
This is a Performance Work Statement (PWS) from the International Boundary and Water Commission (IBWC) United States Section for the complete rebuild of one clarifier and one spare drive unit at the Nogales International Wastewater Treatment Plant in Rio Rico, Arizona.
The contract is structured as a firm fixed price engagement with a maximum performance period of 180 calendar days following award. The contractor must provide all personnel, equipment, supplies, facilities, transportation, tools, and materials necessary to complete the work. Key objectives include: complete rebuild and rehabilitation of one concrete clarifier constructed in 2009, including paint touch-up, drive rebuild, replacement of stainless steel hardware and seals, installation of a new sludge draft tube, replacement of scraper blades, leveling, and concrete grinding where needed; complete rebuild of one spare Ovivo Clarifier Drive unit through remanufacturing or replacement of the pinion gear and shaft, replacement of seals, bearings, drive motor, chain, sprocket, and torque limiter; and replacement of stainless steel blades with rubber-type blades on currently operating clarifiers. The contractor must coordinate with NIWTP to ensure the clarifier is drained and prepared five days prior to work commencement. All work must occur during normal operating hours (7:00 AM to 4:00 PM, Monday through Friday) unless alternative hours are approved in writing by the Contracting Officer Representative. Deliverables include a detailed project schedule (due within seven calendar days of award), job safety analysis, installation procedure plan, materials and equipment certifications, safety documents, warranty documentation, and comprehensive training materials. The contractor must provide factory-trained representatives to conduct on-site operations and maintenance training covering drive mechanics, sludge systems, operational procedures, troubleshooting, and maintenance protocols per the Ovivo maintenance schedule. A one-year warranty from project acceptance is required, with the contractor responsible for all testing, commissioning, and acceptance activities. Invoices must be submitted via the Invoice Processing Platform (IPP) System based on a Schedule of Values broken down into work activities including mobilization/demobilization, installation and alignment, electrical testing, and equipment testing and training. No government-furnished equipment is available; the contractor must provide all necessary equipment including cranes and rigging. The work location is completely within the United States at a federal facility, and the contractor must comply with all applicable federal, state, and local regulations, including OSHA standards, the Buy American Act, and various electrical and safety codes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 191BWC26R0016_ClarifierS_.pdf | ||
| WD_2015-5481.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
International Boundary and Water Commission United States and Mexico United States Section
Performance Work Statement (PWS) Nogales International Wastewater Treatment Plant Complete Rebuild of One Clarifier & One Spare Drive Unit and Spare Drive Unit Rio Rico, Arizona
May 2026
International Boundary and Water Commission United States and Mexico United States Section Operations and Maintenance Division
April 2026 USIBWC Solicitation
Performance Work Statement Page-2 of 19
SECTION 1
PROJECT SPECIFIC INFORMATION
1.1 Project Overview
The United States Section of the International Boundary and Water Commission (USIBWC) urgently requires a complete rebuild of one clarifier & one spare drive unit to match existing at the Nogales International Wastewater Treatment Plant (NIWTP), 865 E. Frontage Rd., Rio Rico, AZ, 85648.
1.2 General
This is a firm fixed price contract for the complete rebuild of one clarifier & one spare drive unit, to match existing and any associated and necessary parts. The Government shall not exercise any supervision or control over the Contract service providers performing the services herein. Such Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.
1.3 Description of Services
This contract is for the complete rebuild and rehab of one concrete Clarifier and one spare Drive Unit.
There is no construction involved. This is only for the refurbishment of the existing of existing clarifier.
The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary for the complete rebuild of one clarifier, replace & a spare drive unit, to match original condition at NIWTP as defined in this Performance Work Statement except for those items specified as government furnished property, equipment and services. The contractor shall perform to the standards in this contract.
The existing clarifier was built in 2009 as part of the plant expansion project. It has been maintained but it has been operating constantly (24 hours per day, seven days a week) and has experienced normal wear and tear. The gear drive has parts that wear and will need replacing, including, but not limited to, bearings, seals, chains, sprockets, and the motor.
The spare drive unit is disassembled and needs a pinion shaft and pinion gear replaced or have the existing worn pinion gear and pinion shaft rebuilt (welded and machined) to Ovivo specs. All other wear parts need to be replaced with an equal or equivalent to existing, and the unit needs to be reassembled, and a new motor to be installed.
Both drive units are Ovivo Clarifier Drives.
Page-3 of 19
NIWTP will remove the clarifier from service and prepare the clarifier for the project. The NIWTP will drain and clean the clarifier five (5) days prior, allowing the project to commence. Normal drain time is 2-3 days and one more day for cleaning. The Clarifier will be locked and tagged out by the NIWTP for the Contractor to begin the project.
The Contractor must coordinate with the NIWTP to ensure that the clarifier is ready for the Contractor to begin the service on schedule.
1.4 Objective
A. Completely rebuild of one clarifier and complete rebuild of the existing spare drive unit, to match original condition at NIWTP plus associated parts to meet the Plant’s operations, maintenance, and environmental control requirements. Contractor shall provide a price breakdown for the items listed and not listed below but submitted as necessary under this contract. Include a price breakdown for the removal and installation services.
B. The NIWTP will drain the clarifier
C. The Contractor shall rebuild an existing clarifier and one spare drive, replace the stainless-steel blades with rubber type blades on the arms of the two clarifiers currently operating, and replace any other existing worn parts with an equal or equivalent to existing model for the following:
1. Complete clarifier rebuild to include but not limited to the following:
• Touch up paint (sand to base metal where it is rusted with hand tools)
• Rebuild Clarifier Drive (Ovivo)
• Replace all hardware with SS hardware
• Replace clarifier seals with new seals
• Add new Sludge draft tube
• Modify blades to fit new draft tube
• Replace scraper blades
• Check weirs and baffles for damage and replace where needed
• Level clarifier
• Sand/grind concrete wall if bulges exist (to ensure no binding with the lower rake arm)
2. Shelf Drive (Spare) Unit (Ovivo)
• Rebuild (remanufacture) to spec or replace with a new clarifier drive pinion gear and pinion shaft
• Replace seals
• Replace bearings
Page-4 of 19
• Check gear wear
• Replace drive-motor
• Replace chain and chain guard
• Replace sprocket
• Replace and calibrate torque limiter and limit switch
Both drive units are Ovivo brands.
All equipment should be delivered to the NIWTP, and the contractor shall install all equipment and bring it up to operational status. Electrical, water, drainage, and disposal containers are all available on-site.
No Government Furnished Equipment will be available to the Contractor. Crane or any other equipment need for the project will be the responsibility of the Contractor to provide.
1.5 Project Location
A. USIBWC Nogales International Wastewater Treatment Plant (NIWTP), located at 865 E. Frontage Rd., Rio Rico, AZ, 85648.
B. The work is located completely within the United States.
1.6 Period of Performance
A. The period of performance shall be for a maximum of (180) days after the contract has been awarded to the Contractor.
1.7 Investigation of Site Conditions
A. Contractors are encouraged to attend an agency organized site visit. Site visits may be scheduled by contacting Albert Flores at 520-281-1832 or cell 520-551-6564 or email Albert.Flores@ibwc.gov.
mailto:Albert.Flores@ibwc.gov.
Page-5 of 19
While attending the site visit all contractors must adhere to personal protective equipment (PPE) steel toe footwear and hard hats. Contractors will not be permitted access to IBWC facilities without proper
PPE.
Office hours are Monday through Friday, 7:30AM to 4PM, excluding Federal holidays.
Train tracks and Union Pacific switching station are sometimes occupied and sometimes block the main entrance (access/egress) to the plant. An alternative dirt road access is available.
B. Submission of a quote shall be conclusive evidence that the Contractor has reviewed, investigated, and acknowledged all items below.
1. Conditions bearing upon transportation, disposal, handling, and storage of materials.
2. The availability of labor, water, electric power, and roads.
3. Uncertainties of weather and similar physical conditions at the site.
4. The conformation and conditions of the ground.
5. The character of equipment and facilities needed for the performance of the work.
C. Submission of a quote shall be conclusive evidence that the Contractor has investigated and is satisfied as to the conditions to be encountered, the character, quality, and work to be performed, and the quantities of materials to be furnished.
D. Submission of a quote constitutes agreement that Contractor has provided written notice of all conflicts, errors, ambiguities, and discrepancies discovered in PWS, that responses to these written notices are acceptable to Contractor, and that PWS is enough to indicate and convey understanding of all terms and conditions for performing and furnishing required work.
E. Contractor has the sole responsibility to make such independent investigation and examination as they deem necessary in order to satisfy themselves as to the conditions to be encountered in the performance of work and the quantities required to complete the work in accordance with the PWS.
F. The Government assumes no responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this Contract, unless that understanding, or representation is expressly stated in this Contract.
G. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
1.8 Duty to Inquire
A. Contractor shall review the full PWS.
B. If during review of these items, the Contractor finds discrepancies, omissions, conflicts, defects, Page-6 of 19 errors, or ambiguities, they have a duty to inquire and notify the Contracting Officer prior to the question submission deadline as established in the solicitation. The Contractor shall also inquire about items that are unclear or open to interpretation.
C. The Contractor shall not take advantage of any item of which they have a duty to inquire.
1.9 Work Restrictions
A. The Contractor is responsible for conducting business between the hours of 7:00 AM thru 4:00 PM, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government-directed facility closings.
B. The Contractor may request different working hours and must do so in writing to the Contracting Officer Representative (COR). USIBWC will make final determination as to the approval of a different work schedule.
C. This project will be occurring during normal Plant operations. Plant operators will be in the clarifier area for Plant process control measurements and data collection and RAS pump maintenance but only for approximately one hour in the morning and one hour in the afternoon and should not be within the footprint of the project.
SECTION 2
PROJECT REQUIREMENTS
2.1 General
A. The Contractor shall rebuild an existing clarifier and one spare drive, replace the stainless-steel blades with rubber type blades on the arms of a clarifier currently operating, and replace any other existing worn parts with an equal or equivalent to existing model for the following:
1. Clarifier complete rebuild to include but not limited to the following:
• Touch up paint (sand to base metal where it is rusted with hand tools)
• Rebuild Clarifier Drive
• Replace all hardware with SS hardware
• Replace clarifier seals with new seals
• Add new Sludge draft tube
• Modify blades to fit new draft tube
• Replace scraper blades
• Check weirs and baffles for damage and replace where needed
• Level clarifier
• Sand wall where bulges
2. Shelf Drive (Spare) Unit
• Rebuild (remanufacture) to spec or replace with a new clarifier drive pinion gear and pinion shaft
• Replace seals
• Replace bearings
• Check gear wear
• Replace drive-motor
• Replace chain and chain guard
• Replace sprocket
• Replace and calibrate torque limiter and limit switch
3. Not limited to other associated and necessary parts not listed but needed to be replaced.
A. The Contractor shall provide detailed cost breakdown to include all equipment, supplies, manuals, Page-7 of 19 and service required to provide maintenance to the Clarifier drive system.
B. The Contractor shall submit a Job Safety Analysis (JSA) Form filled out to be reviewed by Plant Personnel.
C. The Contractor shall conduct a Safety Meeting with all the personnel involved in the project and NIWTP Personnel prior to starting the project. In addition, daily tailgate safety meetings shall be conducted at the start of each workday for contractor staff.
D. As noted in Section 10:
1. The Contractor shall submit invoices via the Invoice Processing Platform (IPP) System. IPP is a web-based system that provides one integrated, secure system to simplify the management of vendor invoices. It is offered at no charge to federal agencies and their vendors. Further information on IPP will be provided at time of award.
2. The invoices for this Contract shall not be combined with any other work or other contracts. They shall be for this Contract only.
2.2 Clean-Up and Disposal of Waste Materials
A. The Contractor shall be responsible for the cleanup and disposal of waste materials and rubbish from the site, field office(s), and staging area(s). Used equipment will remain on site.
B. The disposal of waste materials and rubbish shall be in accordance with applicable Federal, State, and Local laws and regulations and with the requirements in this Contract. Should a conflict exist in the requirements for cleanup and disposal of waste materials, the most stringent requirements shall apply.
1. All waste unless otherwise noted in these specifications shall be disposed of at a licensed landfill or waste disposal facility.
2. Safe disposal of oils and lubricants is the responsibility of the Contractor.
3. Recyclables
a. The reusable equipment and materials shall remain property of the Government.
b. Scrap metal shall remain property of the Government.
C. No excess materials shall be deposited within Government property, unless compliance is confirmed by the Government.
D. The Contractor shall maintain work and storage areas free from accumulations of waste materials and rubbish and before completing the work, and shall remove all temporary facilities, including, buildings, unused materials, concrete forms, and other like materials, which are not a part of the permanent work.
2.3 Testing and Training
Training by the Contractor will be provided to assist the USIBWC in adhering to the OVIVO Maintenance Schedule attached (Attachment A).
The Contractor shall test the rebuilt equipment prior to refilling of the clarifier and provide training to NIWTP personnel prior to filling the clarifier and at project completion prior to project acceptance.
The functional testing shall be observed by the COR for verification and approval.
A. Prior to Contract closeout, the Contractor shall provide a comprehensive project-specific Government personnel training program for the systems and equipment designed and installed under this Contract.
B. When operating procedures are not detailed in owner’s manuals, the Contractor shall write SOPs.
Page-8 of 19
These SOPs shall be available prior to the scheduled training provided below.
1. The Contractor shall furnish factory-trained representatives as required to conduct training sessions on the operation and maintenance of rebuilt equipment. The trainers shall be qualified in providing all required training and have expert knowledge of all aspects of the operation and maintenance of their systems and associated components.
2. The Contractor shall furnish all necessary training materials and furnish each student with a detailed and comprehensive manual covering all course subjects.
3. Training materials shall become the property of the Government after completion of the training.
4. Attendance at this training course will not exceed twelve (12) Government personnel. The training sessions shall be conducted at the Nogales International Wastewater Treatment Plant Office / worksite or at a Government-provided classroom.
C. Training shall include the components listed below:
1. Basis of repair plan, shop drawings, equipment submittals, and installation procedures, operational requirements, and criteria.
2. Documentation and use of O&M Manuals.
3. Relevant health and safety issues.
4. Emergencies, including warnings, trouble indications, shutdown and special operating instructions.
5. Operations - Start-up, normal operation, shutdown, unoccupied operation, seasonal changeover, manual operation, controls set-up and programming, troubleshooting, and alarms.
6. Adjustments.
7. Troubleshooting.
8. Maintenance as well as special maintenance and replacement sources.
9. Repairs, including diagnostic instructions, disassembly, and instructions for identifying parts and components.
2.4 Warranty
A. The Contractor shall warrant that work performed under this PWS conforms to the Contract requirements and is free of any defect in equipment, material, or workmanship performed by the Contractor or any subcontractor or supplier at any tier for a period of at least one (1) year from project acceptance.
1. The Contractor is responsible for providing warranties on items when the manufacturer's warranty is less than the time indicated or when the manufacturer's warranty does not cover full repair and/or replacement as appropriate.
B. The Contractor shall obtain warranties from responsible subcontractors, suppliers, and manufacturers, within sixty (60) days after completion of the applicable item of work, but no later than the date of warranty commencement. The minimum warranty period for any item shall be one year from acceptance.
C. Starting date of warranty is date of Government acceptance of the work.
D. A warranty requires that if a warranted item fails to meet Contract requirements, it shall be repaired, replaced, or have other remedial actions taken to bring the item into compliance with the Contract requirements. Any item damaged due to failure or malfunction of item warranted under this Contract shall be repaired or replaced at no cost to the Government.
E. The Contractor shall supply the CO with a telephone number, mailing address, email address, and contact name for the point of contact for any required warranty work.
Page-9 of 19
SECTION 3
EXISTING CONDITIONS
3.1 General
The existing clarifier was built in 2009 as part of the plant expansion project. It has been maintained but it has been operating constantly (24 hours per day, seven days a week) and has experienced normal wear and tear. The gear drive has parts that wear and will need replacing, including, but not limited to, bearings, seals, chains, sprockets, and the motor.
The spare drive unit is disassembled and needs a pinion shaft and pinion gear replaced or have the existing worn pinion gear and pinion shaft rebuilt (welded and machined) to Ovivo specs. All other wear parts need to be replaced, and the unit needs to be reassembled, and a new motor to be installed.
Both drive units are Ovivo Clarifier Drives.
Page-10 of 19
3.2 Government Furnished Utilities
B. The Government will not be furnishing any equipment, material, services or utilities for this project.
3.3 Use of Government Land
A. USIBWC property is available for use as the Contractor's staging and/or storage areas, subject to the approval of the COR.
B. Housing for Contractor personnel will not be permitted on Government land.
3.4 Hazardous Materials
A. No existing hazardous materials in this project.
Page-11 of 19
SECTION 4
QUALITY REQUIREMENTS
4.1 Common Product Requirements
A. Materials Certification If applicable, the Contractor shall submit a materials certification package to COR which contains a checklist and supporting documentation for all materials used on the project. The supporting documentation shall consist of a summary of all documentation practices utilized for material acceptance and explanations of any deficiencies noted on the checklist.
1. Material certifications shall ensure that all items meet the Buy American Act (41 USC 10a -
10d).
B. Source Control
1. The Contractor shall use only materials that meet the Contract requirements.
2. Unless otherwise specified or compliance confirmed, the Contractor shall use new materials for the work. Material can be reused onsite upon written approval of COR.
3. All materials installed shall be free of defects.
4. The Contractor shall secure the Government’s compliance confirmation of the proposed source of materials to be used before their delivery.
C. Quality Control / Quality Assurance of Materials
1. The contractor shall ensure all equipment is fully operable and functioning as originally designed for the NIWTP.
2. Source Limitations
To the greatest extent possible for each item of work, the Contractor shall provide materials of a singular generic kind from a single source.
3. Compatibility of Options Where more than one choice is available as options for Contractor's selection of a product, material, or equipment, the Contractor shall select an option which is compatible with other products, materials, or equipment. Compatibility is a basic general requirement of product, material, and equipment selections.
4. Field Measurements Verify field measurements, lines, grades, locations, and details at the jobsite prior to fabrication. It shall be the Contractor's responsibility to conform to and satisfy actual field conditions, for accuracy of dimensions, proper fit, and for adequacy of use intended.
5. The Contractor shall correct or remove materials that fail to meet Contract requirements or that do not produce satisfactory results. The Contractor shall reimburse the Government for cost incurred if additional quality assurance sampling and testing is required by a change of source.
6. Materials not meeting Contract requirements will be rejected, unless the Government approves corrective actions in writing. Upon rejection, the Contractor shall immediately remove and replace rejected materials. Should the Contractor fail to comply with the removal of rejected materials, the Government may remove and replace defective material, and the cost of testing, removal, and replacement will be deducted from the Contractor’s final payment.
D. Hazardous Materials The Contractor shall use materials that are free of hazardous materials. The Contractor shall notify the Government immediately when a visual observation or odor indicates that materials in required material sources or on sites owned or controlled by the Government may contain hazardous materials.
Page-12 of 19
E. Surplus Materials
1. The Contractor shall leave surplus rebuildable equipment and materials.
2. The contractor shall remove trash and unusable/un-rebuildable materials.
3. The Contractor shall remove and dispose of materials in accordance with this PWS. If requested or otherwise noted in these specifications, the Contractor shall provide an appropriate level of documentation to verify proper disposal.
F. Storage and Protection
1. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area to minimize waste due to excessive materials handling and misapplication.
2. Store and protect products in accordance with manufacturers' instructions.
3. Store with seals and labels intact and legible.
4. Prevent contact with material that may cause corrosion, discoloration, or staining.
5. Provide equipment and personnel to store products by methods to prevent soiling, disfigurement, or damage.
6. The Contractor shall store and handle materials to preserve their quality and fitness for the work and shall store materials so that they can be easily inspected and retested. When required by the Government, the Contractor shall protect the material with cover, on wooden platforms, or on other hard, clean surfaces as necessary.
SECTION 5
DELIVERABLES
5.1 General
A. Deliverables include, but are not limited to:
1. Project Schedule
a. Project Schedule is to be delivered to COR within seven (7) Calendar Days of contract award.
2. Licenses and Certifications
a. The Contractor shall submit all Licenses and Certifications required to perform this project specified in this PWS.
3. System Design
a. All system designs shall be approved by the Treatment Plant Area Office Manager (AOM) prior to installation.
4. Installation Procedure Plan
a. The Contractor shall provide a procedure to perform this work and testing without disturbing Plant daily operations.
5. Material and equipment certifications
6. Product submittals provided for equipment and materials.
7. Safety documents
8. Warranty
9. Training
a. Training Manuals two hard copies and two electronic files
b. Provide on-site operations and maintenance training to NIWTP staff
c. O&M Manuals two (2) hard copies and electronic files of the manuals, drawings, and as-builts.
d. Service Manuals two hard copies and electronic files
Page-13 of 19
B. Standard Operating Procedure (SOP): Clarifier Gearbox Commissioning and Acceptance
1. Purpose
• This SOP outlines the step-by-step process for commissioning and accepting a newly rebuilt or installed wastewater clarifier drive gearbox. It ensures equipment is safe, fully operational, and compliant with technical and contractual requirements.
2. Commissioning Checklist
• Review rebuild/repair documentation.
• Verify manufacturer installation specifications.
• Confirm drawings and alignment requirements are available.
• Complete safety/hazard assessment.
• Inspect gearbox mounting hardware and verify torque.
• Inspect couplings, keys, and shaft connections.
• Ensure all guards and safety covers are installed.
• Confirm correct oil type and viscosity per OEM.
• Verify proper oil level in the gearbox.
• Verify gearbox breather installation.
• Check alignment: shaft, sprocket, or pinion as applicable.
• Verify motor nameplate matches controls.
• Perform insulation resistance (megger) test.
• Verify motor phase rotation.
• Verify overloads, fuses, and breakers.
• Test local and remote start/stop.
• Verify SCADA/PLC communication.
• Jog motor to verify rotation.
• Run gearbox 15–30 minutes no-load.
• Observe noise, vibration, leaks, and temperature.
• Measure amperage and output shaft speed.
• Operate under full clarifier load.
• Verify torque levels and rake/scum operation.
• Check alignment after loading.
3. Acceptance Checklist
• Review full commissioning documentation.
• Verify all deficiencies have been corrected.
• Confirm contractual specifications have been met.
• Verify performance standards have been achieved.
• Confirm operator training has been completed.
• Ensure preventive maintenance schedule is established.
• Verify break-in oil change has been scheduled.
• Approve administrative and financial acceptance documents.
4. Documentation Requirements
• Commissioning report with measurements, photos, signatures.
Page-14 of 19
• Alignment and torque data.
• Electrical test reports.
• Material specifications, including oil batch and type.
• Acceptance certificate signed by responsible parties.
5. Responsibilities
• Maintenance Supervisor: Oversees commissioning activities.
• Operations Supervisor: Validates operational readiness.
• Electrical/Instrumentation Technician: Performs motor and control testing.
• Plant Manager or Designee: Provides final acceptance authorization.
SECTION 6
PROJECT COORDINATION & ADMINISTRATION
6.1 General
A. The Contractor shall provide all materials, equipment, labor, and services required by this Performance Work Statement to perform the work for the Contract sum and within the Contract period of performance.
B. The Contractor shall be responsible for ensuring that all of its suppliers, manufactures and subcontractors have reviewed all applicable documents relative to their work. The Contractor shall provide all labor, material, equipment, and services not provided by the Contractor’s suppliers, manufacturers, fabricators, and/or subcontractors.
6.2 Security
The Contractor is responsible for securing the work site, equipment, and materials from vandalism and theft.
6.3 Safety
A. The Contractor is solely responsible for worksite safety while performing work or inspections on Government property. The Contractor shall implement a safety program that protects the lives and health of personnel in the project area, prevents damage to property, and avoids work interruptions.
B. The Contractor is responsible for being cognizant of and ensuring compliance with the requirements set forth. Such responsibility shall apply to both the Contractor’s operations and those of the Contractor’s subcontractors.
C. The Contractor shall comply with all provisions of all applicable regulations of the Occupational Safety and Health Administration (OSHA), 29 CFR 1910, Occupational Safety and Health Standards, and 29 CFR 1926, Construction Standards.
1. The OSHA 29 CFR 1910 and 29 CFR 1926 can be accessed at http://www.osha.gov or http://www.gpo.gov/fdsys/.
D. The Contractor’s personnel shall be required to use appropriate personal protective equipment such http://www.osha.gov/ http://www.gpo.gov/fdsys/
Page-15 of 19 as, but not limited to hard hats, safety goggles, welding shields, face shields, protective footwear, protective gloves, and hearing protection.
E. The Government will not provide trash bags and dumpsters.
SECTION 7
PROJECT MEETINGS
7.1 General
A. The Contractor, the COR, or the CO may schedule project meetings at any time.
B. When USIBWC schedules a meeting, the COR shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The COR shall prepare the meeting agenda and distribute it to all invited attendees.
C. When the Contractor schedules a meeting, the Contractor shall inform participants and others involved and individuals whose presence is required, of date and time of each meeting. The Contractor shall prepare the meeting agenda and distribute to all invited attendees.
D. The following meetings are anticipated, and the Contractor shall identify them in the Schedule:
1. Kickoff Meeting
2. Progress Meetings
7.2 Kickoff Meeting
A. After award of the Contract, the COR will coordinate with the Contractor and schedule a Kickoff Meeting. The meeting shall take place prior to the beginning of any Contract work.
B. The purpose of the meeting is to introduce project personnel and to review responsibilities and procedures.
C. The Contractor shall reach an understanding with the Government regarding the project requirements as stated is this Performance Work Statement. This understanding shall be documented in writing and approved by the CO after the Kickoff Meeting.
D. Attendees include, but are not limited to:
1. Contractor's Project Manager
2. CO
3. COR
4. Nogales International Wastewater Treatment Plant Representative
5. It is recommended that Contractor's engineers, inspectors, subcontractors, suppliers, and other parties concerned also attend the conference. The Contractor may invite anyone they wish to this meeting.
6. All participants at the conference shall be familiar with the project and authorized to conclude matters relating to the work.
E. Agenda Discussion of items of significance that could affect the work and project, including the following:
1. Introduction/designation of key personnel and their duties.
2. Review of the current phasing, critical work sequencing, and long-lead items.
3. Review of minimum project requirements.
4. Review of procedures for handling and processing modifications, RFIs, deliverables, and applications for payment.
Page-16 of 19
5. Preparation of deliverable documents.
6. Use of site.
7. Work restrictions.
8. USIBWC and other's occupancy requirements.
9. Safety and first aid.
10. Security.
11. Maintenance of project site.
12. Working hours.
F. Meeting Minutes The Contractor and COR will record the discussions of the meeting and distribute the minutes to all attendees for review prior to finalizing.
7.3 Progress Meetings
A. If needed, the Contractor or COR will schedule progress meetings once the Contractor has mobilized onsite. The COR will conduct and issue minutes of the meetings. Meeting minutes will become official Contract correspondence.
B. The Government may call other meetings on an "as needed" basis.
C. The purpose of these meetings shall be to analyze the progress of the work, resolve conflicts, and in general coordinate the operation of all organizations active at the project site.
SECTION 8
PROJECT SCHEDULE
8.1 Description / Purpose
A. The Contractor shall prepare a project schedule which shall reflect completion of all work under this Performance Work Statement.
B. Project schedule submittal shall include an electronic pdf file.
1. All abbreviations shall be defined.
2. Each project schedule shall show a revision date.
C. Baseline Schedule Preparation Prepare a list of all activities required to complete the work. The baseline schedule shall include all planned work activities and sequences and show Contract completion within the number of calendar days specified in the Contract.
a. Activities Prepare a list of all activities required to complete the work. Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
b. Time Frame Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
SECTION 9 REGULATORY REQUIREMENTS
9.1 Contractor's Responsibility
Page-17 of 19
A. It is the Contractor’s responsibility to perform work in compliance with all applicable requirements of federal, state, and local laws, codes, rules, regulations, ordinances, and standards, including, but not limited to, those outlined in 9.4 below.
B. It shall be the responsibility of the Contractor to acquire copies of all applicable codes, regulations, and standards for ready reference.
C. In instances where requirements are in conflict, the stricter standard shall apply.
D. All inspections, observations, or tests required for code compliance are the responsibility of the Contractor.
9.2 Permits
A. Prior to the beginning of work, the Contractor shall be responsible for researching, coordinating, obtaining, and paying all applicable fees for all permits required by Federal, state, and local entities.
The Government is not responsible for any existing or newly introduced permits required before, during and/or after work on this project.
B. The Contractor shall be responsible for and shall give and maintain all notices required by applicable regulations, laws, or permitting authorities pertaining to work on of this project.
9.3 Dates
A. For all related standards and regulatory requirements in this document, the version, edition, or year shown indicates the governing version.
B. All Public Laws, Code of Federal Regulations (CFR), Federal Acquisition Regulation (FAR), Executive Orders (EOs), Management Policies, Government Directives, Government Standards, refer to the original document as well as any subsequent amendments, corrections, and/or additions.
1. The latest amendments, corrections and additions are to be assumed applicable in the same way as the document itself.
2. The version in effect as of the issuing date of the Solicitation for this project governs unless the law, regulation, order, policy, directive, or standard is updated with a retroactive clause.
9.4 Summary of Regulatory Documents and Agencies
Regulatory requirements applicable to this project include, but is not limited to, the items listed below.
A. Institute of Electrical and Electronics Engineers (IEEE)
1. 2017 National Electrical Safety Code (NESC)
B. National Fire Protection Association (NFPA)
1. NFPA 70-2017 Standard for Electrical Safety in the workplace (also known as the National
Electrical Code [NEC]), with Errata through 70-17-4 and TIA through 17-4
C. Occupational Safety and Health Administration (OSHA)
1. Occupational Safety and Health Standards (29 CFR 1910)
a. https://www.osha.gov/law-regs.html
2. Construction Standards (29 CFR 1926)
a. https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS& p_toc_level=1&p_keyvalue=Construction
D. Public Laws and Acts:
All Public Laws and Acts can be found at http://www.gpo.gov/fdsys/ https://www.osha.gov/law-regs.html https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction https://www.osha.gov/pls/oshaweb/owasrch.search_form?p_doc_type=STANDARDS&p_toc_level=1&p_keyvalue=Construction http://www.gpo.gov/fdsys/
Page-18 of 19
1. Buy American Act [41 USC 10a - 10d]
2. National Environmental Policy Act (NEPA) [42 USC 4321-4347]
3. Resource Conservation and Recovery Act (RCRA)
4. Solid Waste Disposal Act
5. Toxic Substance Control Act
E. State of Texas
1. Texas Engineering Practice Act and Rules Concerning the Practice of Engineering and
Professional Engineering Licensure
a. http://www.tbpe.state.tx.us/downloads/law&rules.pdf
SECTION 10
MEASUREMENTS AND PAYMENTS
10.1 USIBWC Payment Processing
A. The Contractor shall submit invoices via the Invoice Processing Platform (IPP) System. IPP is a web-based system that provides one integrated, secure system to simplify the management of vendor invoices. It is offered at no charge to federal agencies and their vendors. Further information on IPP will be provided at time of award.
B. The invoices for this Contract shall not be combined with any other work or other contracts. They shall be for this Contract only.
Schedule of Values
A. Breakdown each lump sum item into component work activities used in the schedule for which invoices may be requested. The work activities broken out within the Schedule of Values shall be integrated into and made a logical part of the baseline schedule submitted under this section.
1. The total costs for the component work activities shall equal the Contract price for that lump sum item.
2. Overhead, general, and administrative expenses, escrow, bonds, profit, and other across the board markups shall be applied to each line in the Schedule of Values uniformly.
3. An unbalanced Schedule of Values providing for overpayment to the Contractor for items of work to be performed first will not be compliance confirmed but shall be revised by the Contractor and resubmitted until acceptable to the COR. If requested by the Government, the Contractor shall furnish full copies of subcontracts showing actual costs.
4. The Government may request data to verify accuracy of dollar values.
B. Do not break down unit price items. Use only the Contract price for unit price items.
C. An acceptable Schedule of Values shall be agreed upon by the Contractor and COR before the first invoice is processed.
D. The following items shall have an entry in the Schedule of Values. The Contractor may breakdown each item listed into subsections if they so choose. The Contractor may add additional items. The items shown are the minimum required.
1. Mobilization/Demobilization and receiving of parts
2. Installation and aligning/leveling
3. Electrical Testing
4. Testing of Equipment and Training http://www.tbpe.state.tx.us/downloads/law%26rules.pdf
Page-19 of 19
10.2 Progress Payment (Lump Sum CLIN)
A. The Schedule of Values shall be used to prepare an invoice request for the items, or portions of items, of the work completed during the monthly progress period.
B. The Contractor may receive a progress payment for material delivered to the project site and accepted by the COR.
C. As the activity progresses, the Contractor will be paid the value based on the percentage associated with the activity in the Schedule of Values.
--End of Performance Work Statement—
Section 11 Attachments
Attachment A: Training Ovivo circular and mechanism-based clarifiers require routine upkeep focused on cast-iron oil-lubricated drives, torque-monitoring safety switches, and sludge collection components. While a single comprehensive training highlights PDF for every proprietary model is restricted, operation relies on standard preventative maintenance protocols. Training will ensure proper operations and maintenance will ensure a long life and warranty compliance.
Contractor shall provide training for the proper Operation and Maintenance of the OVIVO CLARIFER UNIT. Training shall include the following:
Drive and Mechanical Maintenance
• Oil levels: Check the cast-iron gear housing regularly and change the oil per the specific operation and maintenance (O&M) manual schedule.
• Torque limiter: Test the mechanical or electronic overload/torque alarm monthly to ensure the drive cuts power during high-torque or jammed-rake events.
• Rotation check: Visually verify uniform rotation speed and inspect the main center cage, drive bearings, and pinion/gear alignment.
Sludge and Scum System Checks
• Scraper blades: Inspect rubber squeegees or spiral blades for wear to ensure complete floor scraping without excessive drag.
• Suction risers/valves: For suction-type clarifiers (like C3S models), clear and sample individual riser pipe gate valves to maintain balanced return activated sludge (RAS) withdrawal.
• Scum skimmers: Adjust skimmer blades, beach plates, and flushing water sprays to prevent scum accumulation and pipe clogging. [1, 2, 3] https://municipal.ovivowater.com/app/uploads/2025/05/Ovivo-Sedimentation-Suction-Pipe-Clarifiers-Type-C3S.pdf https://municipal.ovivowater.com/product/clarification-sedimentation-wastewater/clarifiers-wastewater/suction-pipe-clarifier/ https://ovivo.getbynder.com/m/b83989721bf3a37/original/Spiral-Scraper-Clarifier.pdf
| SECTION 1 |
| 1.1 Project Overview |
| 1.2 General |
| 1.3 Description of Services |
| This contract is for the complete rebuild and rehab of one concrete Clarifier and one spare Drive Unit. There is no construction involved. This is only for the refurbishment of the existing of existing clarifier. |
| 1.4 Objective |
| 1.5 Project Location |
| 1.7 Investigation of Site Conditions |
| 1.8 Duty to Inquire |
| 1.9 Work Restrictions |
| SECTION 2 PROJECT REQUIREMENTS |
| 2.1 General |
| 2.2 Clean-Up and Disposal of Waste Materials |
| 2.3 Testing and Training |
| 2.4 Warranty |
| SECTION 3 EXISTING CONDITIONS |
| 3.1 General |
| 3.2 Government Furnished Utilities |
| 3.3 Use of Government Land |
| 3.4 Hazardous Materials |
| SECTION 4 QUALITY REQUIREMENTS |
| 4.1 Common Product Requirements |
| SECTION 5 DELIVERABLES |
| 5.1 General |
| 1. Purpose |
| 2. Commissioning Checklist |
| 3. Acceptance Checklist |
| 4. Documentation Requirements |
| 5. Responsibilities |
| SECTION 6 |
| 6.1 General |
| 6.2 Security |
| 6.3 Safety |
| SECTION 7 PROJECT MEETINGS |
| 7.1 General |
| 7.2 Kickoff Meeting |
| 7.3 Progress Meetings |
| SECTION 8 PROJECT SCHEDULE |
| 8.1 Description / Purpose |
| 9.1 Contractor's Responsibility |
| 9.2 Permits |
| 9.3 Dates |
| 9.4 Summary of Regulatory Documents and Agencies |
| SECTION 10 MEASUREMENTS AND PAYMENTS |
| 10.1 USIBWC Payment Processing |
Section 11 Attachments