Final Pavements Memo NM FLAP SIE 10(1) Lakeshore Road.pdf

PDF 318 KB Posted

Attached to
NM FLAP SIE 10(1) Lakeshore Road Federal contract opportunity
Solicitation number
6982AF22B000033
Issued by
Department of Transportation Federal Highway Administration

About this file

This memorandum provides pavement and material recommendations for the NM FLAP SIE 10(1) Lakeshore Road project in Sierra County, New Mexico. The recommendations include a 3-inch hot mix asphalt surface course over a 6-inch aggregate base course structural section. The project involves replacing four culverts along Lakeshore Road with new culverts or bridges to improve drainage and safety. Additional recommendations include nominal subexcavation and bid items for roadway aggregate, asphalt concrete pavement, and subexcavation. The memorandum notes the road experiences high seasonal traffic variability and provides traffic data used to estimate 170,000 18-kip equivalent single axle loads over 20 years for design. Construction considerations include the potential to encounter cobbles and boulders due to the mountainous terrain as well as the potential need for a local borrow source special contract requirement.

View the file

Other files for this federal contract opportunity

Other files attached to NM FLAP SIE 10(1) Lakeshore Road, newest first.
File Type Posted
Bid Tabs.pdf PDF
Bid Opening Summary.pdf PDF
QnA 5 10 2023.pdf PDF
NM_FLAP_SIE10(1)_Lakeshore_Final_Hydraulics_Report_wApp.pdf PDF
FP-14_Eng.pdf PDF
Plans.pdf PDF
IFB 6982AF22B000033 Lakeshore Road.pdf PDF
NM.FLAP.SIE.10(1).Lakeshore Road.Geotech Rpt FINAL.June 2022_Drilled Shafts Box Culverts.pdf PDF
Cross Sections.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Subject: Final Pavement & Materials Recommendations (V2) NM FLAP SIE 10(1) Lakeshore Road

From: Marty Fey Pavement & Materials Engineer, CFLHD

Through: Mike Voth Pavement & Materials Team Lead, CFLHD

To: Solomon Haile, Project Manager, CFLHD Adrian Smith, Design Engineer, CFLHD

INTRODUCTION

This memorandum provides preliminary pavement and material recommendations for the Lakeshore Road project located in Sierra County, east of Truth or Consequences, New Mexico.

The Lakeshore Road project consists of five hydraulic structure upgrades at separate locations along Lakeshore Road on the west side of the reservoir.

CFLHD standards and guidelines were used to complete the pavement and materials recommendations.

FIELD INVESTIGATION

CFLHD geotechnical engineer Brendan McGarity performed a field investigation of Lakeshore Road from January 18th to 21st, 2021. A truck-mounted drill rig with an 8” O.D. hollow stem auger was used to complete the borings. Pavement borings were logged at 5 locations.

Additional geotech borings were drilled for the project, the data and analysis for which is available in a separate geotechnical report.

Technical Memorandum

Date: October 22, 2021 Rev: March 14, 2023

The primary objectives of this field investigation were as follows:

Measure and record existing pavement and subgrade layer depths;

Gather subgrade soil samples for follow-up testing to determine engineering properties;

Evaluate and record pavement distress conditions;

Evaluate roadway and project area for constructability concerns.

Lakeshore Road has an asphalt paved surface and the structure was observed to be performing well. The construction and maintenance history of the roadway are not known at this time.

The information gathered as described above was used to support pavement rehabilitation, structural design, and material recommendations.

Below are summary tables of the data gathered and test results.

Summary of Sampling & Test Results, Lakeshore Road

Pavement Depth

Roadbase

R‐value, subgrade

Plasticity Index

Comments

2 to 4 inches

2 to 3

44 15 Resistivity values were evaluated as part of a separate geotechnical investigation.

Summary of Sampling & Test Results, CR 64

Pavement

Roadbase

R‐value, subgrade

Plasticity Index

Comments

0 to 4.5

0 to 3

22 to 73 NP to 15

Subgrade material consists of Silty Sands and Clayey Gravels, A‐1‐b (0) and A‐2‐6 (0).

Practical refusal was encountered in several locations at depths of 6 inches to 1 foot.

TRAFFIC:

Traffic counts for Lakeshore Road were provided with the FLAP application and used to developed estimates for ESALs. The road is primarily used for recreational access with little commercial use. Truck counts were based on engineering judgement and are assumed to be very low. The counts appear generally consistent with other historical traffic data and they align with what was experienced during the field investigation. An Annual Average Daily Traffic (AADT) value was used for analysis due to high seasonal variability in traffic volumes. The following is a summary of traffic data as well as the estimated ESALs used for design:

2019 AADT = 350

2039 ADT = 520 (2% growth rate) 2019 % trucks = 15% Class 5 (trucks/RVs), 1% Class 8 Directional factor = 60% Calculated Lane ESAL’s = 170,000

DESIGN RECOMMENDATIONS

The pavement design, rehabilitation method, and other recommendations are included below.

In developing the pavement structural and rehabilitation recommendations for Lakeshore Road the following criteria was used:

Design Criteria Initial Serviceability 4.2 Terminal Serviceability 2.0 Design Reliability Level 75% Overall Standard Deviation 0.49 Soil Resilient Modulus (R-value = 44) 10,800 psi Performance Period (3R) 20 years 20-year ESAL 170,000 Calculated Structural Number (SN) 2.02

The following is the recommended pavement structural section:

Lakeshore Road Layer Thickness

HACP 3 inches (two lifts) Aggregate Base Course 6 inches

SN 2.06

ADDITIONAL RECOMMENDATIONS:

Include a nominal amount of subexcavation (~200 cu yd) to be used at discretion of the

CO.

Recommend the following bid items.

Item Number Item Description Unit 20402-0000 Subexcavation CUYD 30202-2000 Roadway Aggregate, Method 2 TON 40301-0100 Asphalt Concrete Pavement, Type 1 TON

CONSTRUCTION CONSIDERATIONS & SPECIAL CONTRACT PROVISIONS

The project is located in a mountainous area where cobbles and refusal were encountered during the subsurface investigation. The contractor should expect to encounter some cobbles and boulders during construction.

CFLHD standard SCR’s related to pavements & materials will be used. If the decision is made to use a local borrow source and/or develop a source, an SCR may need to be developed.

2023-03-14T10:39:27-0600
MARTIN CHARLES FEY