Final Location Sheet D5 Sweeping 1-9-25 Version.xlsx
XLSX spreadsheet 17 KB Posted
- Attached to
- Eq Rental Highway Sweeping D-5
- Solicitation number
- RFB 605 2500000376 2
- Issued by
- Bath County, Kentucky
About this file
This is a Location Sheet for highway sweeping work in District 5, prepared by the Kentucky Transportation Cabinet for the state's roads in Bullitt, Shelby, and Jefferson counties. The document outlines sweeping services required on Interstate 65, Interstate 64, Interstate 71, Interstate 265, and Kentucky Route 841, with work divided into three frequency categories: 3-cycle locations covering 1.418 miles, 6-cycle locations covering 15.283 miles, and 12-cycle locations covering 141.12 miles, totaling approximately 157.821 miles of roadway requiring regular sweeping. Services include sweeping of curblines, bridges, barrier walls, overhead bridges, and all pavement areas at designated rest areas. The work must be completed with a maximum of 21 calendar days for a full sweeping cycle and 5 calendar days for designated partial sweeping cycles. Additional sweeping paid for by the Louisville and Southern Indiana Ohio River Bridges (LSIORB) covers 6.902 miles on two segments of Interstate 64 and Interstate 65.
The document specifies anticipated annual sweeping totals of approximately 1,619.738 miles across all designated locations. Work descriptions detail specific highways, mileposts, county lines, bridges, and landmarks that define each sweeping zone. The contract areas are identified by project numbers beginning with "FE01," indicating these are federally-eligible maintenance operations. The sheet serves as the baseline for contractor performance requirements, defining the scope of work to be performed at each location and the frequency of service cycles necessary to maintain highway cleanliness and safety throughout District 5.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Highway Sweeping Work Location Sheet |
| District 5 |
| Route | County | Project Number | From | To | Sweeping Miles (Miles Paid) | Anticipated # of Cycles/YR | Anticipated Total Miles/YR (Sweeping Miles X # of cycles) | Work Description including incidentals |
| 3 Cycle Locations | ||||||||
| (Miles measured from begin to end of RA Ramps) | ||||||||
| I-65 | Bullitt | FE01 015-0065 | Rest Area Exit Ramp | Rest Area Entrance Ramp | 0.698 | 3 | 2.094 | Sweep all pavement areas at the Rest Area |
| 112-114 | (MP 113.650) | (MP 112.952) |
| I-64 | Shelby | FE01 106-0064 | Rest Area Exit Ramp | Rest Area Entrance Ramp | 0.72 | 3 | 2.16 | Sweep all pavement areas at the Rest Area |
| 028-029 | (MP28.250) | MP28.970 |
| Subtotal | 1.418 | |||||||
| 6 Cycle Locations | ||||||||
| (Miles for length of cleaning ONLY) | ||||||||
| KY 841 | Jefferson | FE01 056-0841 | US 31W | I-65 | ||||
| 000-010 | (MP 0.000) | (MP 10.000) | 2.45 | 6 | 14.7 | Sweep curblines, bridges & barrier walls |
| I-265 | Jefferson | FE01 056-0265 | I-65 | I-71 | 12.833 | 6 | 76.998 | Sweep curblines, bridges & barrier walls (Added 5.278 miles for new barrier wall and bridges along IMOVE project) |
| 010-035 | (MP 10.000) | (MP 35.000) |
| Subtotal | 15.283 | |||||||
| 12 Cycle Locations | ||||||||
| (Miles for Centerline Mile, Cardinal and Non-Cardinal paid seperately; all other work incidental according to contract and descriptions below) | ||||||||
| I-264 | Jefferson | FE01 056-0264 | I-64 | I-71 | 46.11 | 12 | 553.32 | Sweep curblines , Bridges, barrier walls and |
| 000-024 | (MP 0.000) | (MP 23.055) | overhead bridges at KY 864, KY 1703, KY 1932 | |||||
| I-64 , US 60 and US 42 |
| I-64 | Jefferson | FE01 056-0064 | Mellwood Bridge (Eastside) | 0.047 mile West of Browns Lane | 10.348 | 12 | 124.176 | Sweep all bridges and tunnels |
| 006-012 | (MP 6.701) | (MP 11.875) |
| I-64 | Jefferson | FE01 056-0064 | 0.700 mile East of I-264 | 1.0 miles West of I-265 | 9.946 | 12 | 119.352 | Sweep curblines , Bridges, barrier walls and |
| 012-018 | (MP 12.943) | (MP 17.916) | overhead bridges at Blankenbaker Parkway | |||||
| (KY 913) |
| I-64 | Jefferson | FE01 056-0064 | English Station Rd Bridge | Shelby Co Line | 8.802 | 12 | 105.624 | Sweep curblines, bridges & barrier walls |
| 019-024 | (MP 19.573) | (MP 23.974) |
| I-65 | Bullitt | FE01 015-0065 | Hardin Co Line | 0.672 mile North of Hardin Co Line | 1.344 | 12 | 16.128 | Sweep curblines, bridges & barrier walls |
| 103-104 | (MP 103.308) | (MP 103.980) |
| I-65 | Bullitt | FE01 015-0065 | Beginning of the Roadway Bridge | End of the Railroad Bridge | 0.274 | 12 | 3.288 | Sweep curbline of the railroad bridge and the roadway bridge |
| 112-113 | (MP 112.517) | (MP 112.654) |
| I-65 | Bullitt | FE01 015-0065 | 0.2 Mile South of KY 480 | 0.2 Mile North of KY 44 | 3.088 | 12 | 37.056 | Sweep curblines, bridges, barrier walls and |
| 115-117 | (MP 115.321) | (MP 116.865) | the overhead bridges at KY 44, KY 245 and KY1526 |
| I-65 | Bullitt | FE01 015-0065 | Beg. Of Barrier Wall | End of Barrier Wall | 0.138 | 12 | 1.656 | Sweep the barrier wall ( NORTHBOUND ONLY) |
| 118-119 | (MP 118.180) | (MP 118.042) |
| I-65 | Jefferson | FE01 056-0065 | 0.8 Mile North of the | 0.245 Mile South of the | 14.778 | 12 | 177.336 | Sweep curblines, bridges, barrier walls and |
| 123-132 | Bullitt County Line | Phillips Lane Bridge | overhead bridges at I-265, KY 1065, KY 1631 | |||||
| (MP 123.900) | (MP 131.289) | and all ramp bridges at I-265 |
| I-71 | Jefferson | FE01 056-0071 | I-64 | I-264 | 9.932 | 12 | 119.184 | Sweep bridges and curblines |
| 000-005 | (MP 0.000) | (MP 4.966) |
| I-64 | Shelby | FE01 106-0064 | Beg. Of Barrier Wall | End of Barrier Wall | 17.802 | 12 | 213.624 | Sweep curblines, bridges barrier walls and |
| 023-033 | (MP 23.974) | (MP 32.875) | overhead bridges at KY 1848 and KY 55 |
| I-65 | Jefferson | FE01 056-0065 | 0.254 Mile South of the | South End Ali Bridge | 8.582 | 12 | 102.984 | Sweep all paved areas outside of roadway |
| 131-136 | Phillips Lane Bridge | (MP 135.58) | ||||||
| (MP 131.289) |
| I-64 | Jefferson | FE01 056-0064 | Sherman Minton Bridge | River Road Bridge | 9.976 | 12 | 119.712 | Sweep all paved area outside of roadway |
| 000-005 | (MP 0.000) | (MP 4.988) |
Subtotal 141.12
Sweeping Paid for by LSIORB
| I-64 | Jefferson | FE01 056-0064 | River Road Bridge | Mellwood Bridge (Eastside) | 3.426 | 12 | 41.112 | Sweep all paved area outside of roadway |
| 005-007 | (MP 4.988) | (MP 6.701) |
| I-65 | Jefferson | FE01 056-0065 | South End Ali Bridge | North End of River Bridges | 3.476 | 12 | 41.712 | Sweep all paved areas outside of roadway |
| 136-138 | (MP 135.58) | (MP 137.318) |
Subtotal 6.902
| Maximum time to complete a Full Sweeping Cycles : 21 Calendar Days |
| Maximum time to complete a Designated Partial Sweeping Cycle: 5 Calendar Days |
File details come from the government source that posted it. Updated .