Final Drawings 626A4-21-205.pdf
PDF 13 MB Posted
- Solicitation number
- 36C24922B0030
About this file
This document provides details for a federal contract solicitation to upgrade the fire protection and HVAC systems at a Department of Veterans Affairs medical center. The solicitation seeks bids for project number 626A4-21-205 to completely prepare the site for construction activities including demolition and removal of existing structures, and furnish all labor, materials, and work to upgrade the warehouse fire protection and HVAC at the Alvin C. York VA Medical Center located in Murfreesboro, Tennessee. The solicitation is identified as number 36C24922B0030 and is issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24922B0030 0003.pdf | ||
| 36C24922B0030 0002.pdf | ||
| 36C24922B0030 0001.docx | DOCX document | |
| S04 SITE VISIT CHECK IN Completed.pdf | ||
| General Decision Number TN20220187.pdf | ||
| Final Specs 626A4-21-205.pdf | ||
| 36C24922B0030.docx | DOCX document | |
| Calculation of Self Performed Work.docx | DOCX document | |
| RFI Form - Upgrade Warehouse Fire Protection and HVAC.docx | DOCX document | |
| Contractor EMR Certification Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. INDICATIONS OF PROJECT LIMITS OR LINES OF DEMARCATION ARE SHOWN FOR GENERAL SCOPE DEFINITION AND REFLECT THE UNDERSTANDING OF THE DESIGNER AS TO THE LIMITATIONS OF THE WORK AREA IN AN OCCUPIED AREA. ACTUAL CONTRACT LIMITS ARE TO BE DETERMINED BY AGREEMENT
BETWEEN THE COR AND CONTRACTOR BEFORE THE START OF THE WORK.
2. DRAWINGS ARE PREPARED USING DIMENSIONS AND PRODUCT DRAWINGS FOR SPECIFIC PRODUCTS. DETAILS FOR SPECIFIC PRODUCTS MAY CHANGE BEFORE THEY ARE ACTUALLY INCORPORATED INTO THE WORK, AND PRODUCTS BY OTHER MANUFACTURERS ARE ALSO ACCEPTABLE SHOULD THEY MEET PROJECT REQUIREMENTS. THEREFORE, ACTUAL INSTALLATION DETAILS AND DIMENSIONS MAY DIFFER FROM THOSE SHOWN. CONTRACTOR SHALL VERIFY INSTALLATION REQUIREMENTS FOR ALL PRODUCTS TO BE INCORPORATED IN THE WORK (INCLUDING THICKNESS FOR RECESSED OR SEMI- RECESSED PRODUCT(S) AND IS RESPONSIBLE FOR ACCOMMODATING AND COORDINATING CHANGES TO OTHER MATERIALS OR PRODUCTS THAT ARE
NECESSARY BECAUSE OF THESE DIFFERENCES.
3. THE DRAWINGS AND SPECIFICATIONS ARE SEPARATED INTO DISCIPLINES FOR CONVENIENCE. THE SEPARATIONS ARE USED ONLY FOR THE PURPOSES OF CONVENIENCE AND REFERENCE AND IN NO WAY DO THEY DEFINE OR LIMIT THE SCOPE OR INTENT OF ANY PART OF THE DRAWINGS AND SPECIFICATIONS AS A WHOLE. THE FACT THAT THE DRAWINGS ARE SEPARATED IN NO WAY SUGGESTS THAT THE WORK IS NOT TO BE CONSTRUCTED AS A COMPLETE, INTEGRATED AND UNIFIED WHOLE.
4. THE DRAWINGS AND SPECIFICATIONS, INCLUDING DRAWINGS PREPARED BY SPECIFIC ENGINEERING DISCIPLINES ARE COMPLEMENTARY; ITEMS SHOWN IN ANY ONE LOCATION IN THE DRAWINGS SHALL BE CONSIDERED TO BE REQUIREMENTS OF THE CONTRACT FOR CONSTRUCTION. IN THE EVENT OF AN INCONSISTENCY BETWEEN THE DRAWINGS AND SPECIFICATIONS, OR WITHIN EITHER DOCUMENT, THE CONTRACTOR SHALL SEEK CLARIFICATION OR INTERPRETATION FROM THE COR PRIOR TO BIDDING. WHERE INCONSISTENCIES ARE NOT CLARIFIED PRIOR TO BIDDING, AND WHERE THE ACTUAL SOLUTION OR INTENT CANNOT BE REASONABLY INFERRED, THE CONTRACTOR SHALL PROVIDE THE BETTER QUALITY OR GREATER QUANTITY OF WORK.
5. THE CONTRACTOR SHALL NOTIFY THE COR IMMEDIATELY SHOULD DISCREPANCIES BE FOUND IN THE DRAWINGS AND SPECIFICATIONS.
6. THE CONTRACTOR IS RESPONSIBLE FOR CHECKING ALL FIELD CONDITIONS AND DIMENSIONS AS THEY RELATE TO THIS PROJECT. SHOULD DISCREPANCIES EXIST BETWEEN THE WORK INDICATED AND ACTUAL FIELD CONDITIONS NOTIFY THE COR PRIOR TO PROCEEDING WITH THE WORK.
7. DO NOT SCALE THE DRAWINGS. DRAWING SCALES AS INDICATED ARE FOR REFERENCE ONLY AND ARE NOT INTENDED TO ACCURATELY DEPICT ACTUAL
OR DESIGNATED CONDITIONS. WRITTEN DIMENSIONS SHALL GOVERN.
8. PROVIDE SEALANT AT ALL INTERSECTIONS BETWEEN DIFFERENT MATERIALS.
9. COORDINATE WORK OF ALL TRADES PRIOR TO STARTING CONSTRUCTION.
10. THE CONTRACTOR INVOLVED IN THIS PROJECT SHALL BE RESPONSIBLE FOR CONSTRUCTING AND INSTALLING THEIR RESPECTIVE WORK AND SYSTEMS TO MEET ALL APPLICABLE FEDERAL, STATE, AND LOCAL CODES, LAWS, SAFETY REGULATIONS, HAZARDOUS WASTE LAWS, ETC. THE CONTRACTOR SHALL
FURNISH ALL NECESSARY PERMITS.
11. REFER TO PLUMBING, ELECTRICAL, MECHANICAL, ETC. DRAWINGS FOR ADDITIONAL INFORMATION.
12. PROVIDE BLOCKING OR 16 GAGE METAL BACKING PLATES AT PARTITIONS AS REQUIRED FOR MOUNTING OF WALL-MOUNTED ITEMS: PROVIDE SUPPLEMENTAL FRAMING AT WALL OPENINGS INCLUDING KING STUDS, JACK STUDS, AND CRIPPLE STUDS, AS REQUIRED FOR COMPLETION OF THE
WORK.
13. COORDINATE THE WORK OF TRADES PRIOR TO THE START OF CONSTRUCTION.
14. FIELD VERIFY EXISTING CONDITIONS PRIOR TO THE START OF WORK FOR EACH PHASE.
15. DIMENSIONS SHOWN ARE TO FACE OF STUD FRAMING, FACE OF CONCRETE/MASONRY WALLS, OR FINISHED FACE OF EXISTING WALL SURFACE.
16. INSTALL ALL WORK IN ACCORDANCE WITH CURRENT APPLICABLE CODES AND PUBLISHED STANDARDS.
17. AT AREAS INDICATED TO BE PATCHED AND REPAIRED, FOR ADDTIONS AND RENOVATION PROJECTS. THE CONSTRUCTION AND ASSEMBLY OF THE PATCH OR REPAIR SHALL MATCH THE ASSEMBLY AND INTEGRITY OF THE ADJACENT EXISTING CONSTRUCTION, FOR FIRE RATING, MATERIALS, FINISH, THICKNESS, AND QUALITY.
1. KEY NOTES AND DRAWINGS ARE INTENDED TO GRAPHICALLY REPRESENT GENERAL WORK AND DO NOT PORTRAY
FULL SCOPE OF THE PROJECT. SEE SPECIFICATIONS FOR FURTHER DETAILED REQUIREMENTS.
2. REMOVE EXISTING CONSTRUCTION AS DESIGNATED HEREIN AND CLEAR AREA OF DEBRIS PRIOR TO PROCEEDING
WITH NEW CONSTRUCTION.
3. EXISTING EQUIPMENT REMOVED SHALL BE PROPERLY DISPOSED OFF MEDICAL CENTER GROUNDS. COORDINATE
WITH VA COR.
4. PATCHED WALL OPENING (S) SHALL MATCH THE INTEGRITY OF ADJACENT CONSTRUCTION UNLESS INDICATED
OTHERWISE.
5. COORDINATE WORKING HOURS ALLOWED FOR DEMOLITION AND WASTE REMOVAL WITH VA COR.
6. NOTIFY COR OF ANY DEMOLITION REQUIRED AND NOT INDICATED FOR INSTALLATION OF ELECTRICAL OR DATA ITEMS. AFTER SUCH DEMOLITION AND INSTALLATION, PATCH OR REPLACE MATERIALS AND FINISHES TO MATCH
EXISTING.
7. CONTRACTOR TO PROTECT AREA ADJACENT TO THE DEMOLITION AND NEW CONSTRUCTION WORK TO PREVENT DAMAGES, (IF DAMAGED REPAIR, RE-PATCH, SAND SMOOTH AND REFINISH TO MATCH EXISTING.) REPAIR OR
REPLACE ITEMS DAMAGED DURING CONSTRUCTION ACTIVITIES AT NO ADDITIONAL COST.
8. CONTRACTOR SHALL REPORT TO THE VA COR IMMEDIATELY WHEN DISCREPANCIES TO THE DRAWINGS ARE FOUND
IN THE FIELD.
9. THE INFORMATION CONTAINED IN THESE DEMOLITION DOCUMENTS DEFINES GENERAL SCOPE ONLY AND DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY OF PROVIDING ALL DEMOLITION REQUIRED FOR THE
COMPLETION OF THE PROJECT.
10. DO NOT ENCROACH ON ADJACENT OCCUPIED AREAS NOT INDENTIFIED WITHIN THE SCOPE OF WORK.
11. REFER TO THE COMPLETE SET OF ELECTRICAL DRAWINGS FOR FURTHER INFORMATION REGARDING DEMOLITION OF
ELECTRICAL AND ALL RELATED SYSTEMS.
12. BEFORE THE START OF WORK, IDENTIFY ANY REQUIRED DEMOLITION BEYOND THE IDENTIFIED PROJECT SCOPE WHETHER ABOVE, BELOW OR OUTSIDE PROJECT AREA. NOTIFY AND COORDINATE WITH THE COR, PROVIDE DEMOLITION OF THESE AREAS AND PATCH THE SAME AS A PART OF THE SCOPE OF THE PROJECT.
13. ALL DEMOLITION WORK SHALL BE PERFORMED WITH DUE CARE AND DILIGENCE IN ORDER TO PREVENT ARBITRARY DAMAGE OR INTERRUPTION OF SERVICE OR CONCEALED UTILITIES INTENDED TO REMAIN IN SERVICE. DISCOVERY OF UTILITIES OR CONDITIONS LOCATED DIFFERENTLY FROM THAT INDICATED OR THAT ARE NOT IDENTIFIED. SHALL
BE REPORTED TO THE CONTRACTING OFFICER IMMEDIATELY.
14. VERIFY ALL EXISTING CONDITIONS PRIOR TO BEGINNING WORK. NOTIFY VA COR AND ARCHITECT OF ANY CONFLICTS
PRIOR TO PROCEEDING WITH DEMOLITION.
15. ALL ITEMS BEING REMOVED SHALL REMAIN THE PROPERTY OF THE VA MEDICAL CENTER UNTIL CONFIRMATION HAS BEEN MADE BY THE VA COR AS TO WHETHER THE VA WILL RETAIN SUCH ITEMS. ALL ITEMS NOT BEING RETAINED BY THE VA COR OR DESIGNATED ON THE DRAWINGS TO BE RELOCATED, REINSTALLED OR REMOVED FROM THE SITE BY
CONTRACTOR.
16. VA SHALL HAVE FIRST OPPORTUNITY FOR SALVAGE. ALL ITEMS NOTE SALVAGED BY THE VA TO BE REMOVED AND DISPOSED OF BY THE CONTRACTOR IN APPROVED MANNER IN COMPLIANCE WITH LOCAL REGULATIONS.
17. CONTRACTOR SHOULD NOTIFY VA COR OF ANY AREA REQUIRING DEMOLITION OTHER THAN SHOWN IN THESE DRAWINGS DUE TO UNFORSEEN CONDITIONS TO ACCOMMODATE INSTALLATION OF MECHANICAL, PLUMBING, STRUCTURAL, ELECTRICAL, OR DATA ITEMS (INCLUDING ROOF PENETRATIONS). AFTER SUCH DEMOLITION AND
INSTALLATION, PATCH OR REPLACE MATERIALS AND FINISHES TO MATCH EXISTING.
18. COORDINATE WITH VA COR FOR CONSTRUCTION ACCESS ROUTE AND LOCATIONS OF DUMPSTER AREA.
COORDINATE WITH COR FOR SCHEDULE OF USE OF ACCESS ROUTE FOR WASTE REMOVAL AND CONTRACTOR USE
OF FREIGHT ELEVATOR. SEE DWG A-001 FOR LOGISTICS.
WALL SECTION
SYMBOL
INTERIOR ELEVATION
SYMBOL
COLUMN GRID
ELEVATION SYMBOL
REVISION NOTE
ENLARGED DETAIL CALLOUT
ROOM DESIGNATION
SYMBOL
BREAK LINE
ROOF SLOPE
DIRECTION SYMBOL
TYPICAL GRAPHIC SCALE
DETAIL #
PAGE #
DETAIL #
PAGE #
VIEW NORTH ARROW
A8.1
EXTERIOR ELEVATION
SYMBOL
DETAIL #
PAGE #
A8.1
A8.1
A8.1
BUILDING SECTION
SYMBOL
DETAIL #
PAGE #
A8.1
A8.1
DETAIL SECTION
SYMBOL
DETAIL #
PAGE #
A8.1
WALL GRID
(REPRESENTS
FACE OF EXISTING
WALL)
XX.X
XX.X
ELEVATION
0'-0"
ROOM
NAME
101A
NORTH
0 4 8 16
DEMOLITION KEYNOTE WINDOW TYPE
ROOF OR CEILING
PITCH SYMBOL
DOOR NUMBER
TYPICAL KEYNOTE CEILING/ SOFFIT
HEIGHT
MATL
1'-0"
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
PROJECT SITE MAP PROJECT LOCATION MAP
PROJECT IMAGE
/9
/2
:4
:4
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
G-001
COVER, ARCHITECTURAL SYMBOLS
AND NOTES
1 3EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129
VA PROJECT #: 626A4-21-205
LCW
DRAWING LIST
GENERAL
G-001 COVER, ARCHITECTURAL SYMBOLS AND NOTES 1 3
G-201 SITE PLAN 2 3
G-202 FIRST FLOOR AND MEZZANINE LIFE SAFETY PLANS 3 3
CIVIL
CS101 CIVIL SITE & UTILITY PLAN 1 3
CD101 DEMOLITION PLAN 2 3
CS501 CONSTRUCTION DETAILS 3 3
ARCHITECTURAL
A-001 LOGISTICS PLAN 1 5
AD101 FIRST FLOOR DEMOLITION PLAN 2 5
AE101 FIRST FLOOR PLAN AND FIRST FLOOR REFLECTED CEILING PLAN 3 5
AE301 WALL SECTIONS, BUILDING SECTION, AND DETAILS 4 5
AE701 DOOR AND ROOM FINISH SCHEDULES AND DETAILS 5 5
FIRE SUPPRESSION
FX001 FIRE SUPPRESSION GENERAL INFORMATION 1 4
FX002 FIRE SUPPRESSION DESIGN DATA 2 4
FD101 GROUND FLOOR FIRE SUPPRESSION DEMOLITION PLAN 3 4
FX101 GROUND FLOOR AND MEZZANINE FIRE SUPPRESSION PLANS 4 4
PLUMBING
P-001 PLUMBING GENERAL INFORMATION 1 3
PD101 GROUND FLOOR PLUMBING DEMOLITION PLANS 2 3
PP101 GROUND FLOOR PLUMBING PLANS 3 3
MECHANICAL
M-001 MECHANICAL GENERAL INFORMATION 1 3
MD101 GROUND FLOOR MECHANICAL DEMOLITION PLAN 2 3
MH101 GROUND FLOOR AND MEZZANINE HVAC PLANS 3 3
ELECTRICAL
E-001 ELECTRICAL GENERAL NOTES, SYMBOL LEGENDS, AND ABBREVIATIONS 1 5
ED101 FIRST FLOOR AND MEZZANINE ELECTRICAL DEMOLITION PLANS 2 5
E-101 FIRST FLOOR AND MEZZANINE ELECTRICAL PLANS 3 5
EL101 FIRST FLOOR AND MEZZANINE LIGHTING PLAN 4 5
E-601 ELECTRICAL RISERS, SCHEDULES, AND DETAILS 5 5
BLDG 146 PROJECT LOCATION
N N
GENERAL NOTES DEMOLITION NOTES
GENERAL SYMBOL LEGEND ARCHITECTURAL SYMBOL LEGEND
DocuSign Envelope ID: B5608AB8-24BF-40EF-AAE3-A7FEABFC68EE
5/9/2022
SCOPE OF WORK
BUILDING 146
BUILDING 147
BUILDING 112
NEW CONCRETE WORK
AFF ABOVE FINISHED FLOOR
ACP/APC ACOUSTIC CEILING PANEL/
ACOUSTIC PANEL CEILING
ACT ACOUSTIC(AL) TILE
ADJ ADJUSTABLE
ADT'L ADDITIONAL
AGG AGGREGATE
ALT ALTERNATE
AL ALUMINUM
APPROX APPROXIMATE(LY)
ASPH ASPHALT
AUTO AUTOMATIC
B/O BOTTOM OF
BD BOARD
BLDG BUILDING
BLKG BLOCKING
BOT BOTTOM
BRG BEARING
CENTERLINE
C/C CENTER TO CENTER
CJ CONTROL JOINT
CLL CONTRACT LIMIT LINE
CEM CEMENT(ITIOUS)
CMU CONCRETE MASONRY UNIT
CLG CEILING
CLR CLEAR
COL COLUMN
CONC CONCRETE
CONST CONSTRUCTION
CONT CONTINUOUS
CPT CARPET
CT CERAMIC TILE
CTR CENTER(ED)
DF DRINKING FOUNTAIN
DS DOWNSPOUT
DBL DOUBLE
DEG DEGREE
DEMO DEMOLITION
DET/DTL DETAIL
DIA DIAMETER
DIM DIMENSION
DN DOWN
DWG(S) DRAWING(S)
E EAST
EC ELECTRICAL CONTRACTOR
EHO ELECTRICAL HOLD OPEN
EJ EXPANSION JOINT
EW EACH WAY
EA EACH
EIFS EXTERIOR INSULATION
FINISH SYSTEM
EL ELEVATION
ELEC ELECTRIC(AL)
ELEV ELEVATOR
EMER EMERGENCY
EQ EQUAL
EQUIP EQUIPMENT
EXIST EXISTING
EXT EXTERIOR
EWC ELECTRIC WATER COOLER
FD FLOOR DRAIN
FE FIRE EXTINGUISHER
FFE FINISH FLOOR ELEVATION
FV FIELD VERIFY
FEC FIRE EXTINGUISHER CABINET
FDN FOUNDATION
FIN FINISH
FLSHG FLASHING
FLR FLOOR
FRMG FRAMING
FT FOOT/FEET
FTG FOOTING
GC GENERAL CONTRACTOR
GA GAUGE
GALV GALVANIZED
GEN GENERAL
GYP GYPSUM
HM HOLLOW METAL
HDWR HARDWARE
HOL HOLLOW
HOR HORIZONTAL
HT HEIGHT
HVAC HEATING/VENTILATION/AIR
CONDITIONING
ID INSIDE DIAMETER
IN INCH
INCL INCLUDING
INSUL INSULATION
INT INTERIOR
JAN JANITOR
JT JOINT
LAV LAVATORY
LB(S) POUND(S)
L/S LANDSCAPE
LT LIGHT
MO MASONRY OPENING
MAS MASONRY
MAT'L MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM
MISC MISCELLANEOUS
MTD MOUNTED
MTL METAL
N NORTH
NIC NOT IN CONTRACT
NTS NOT TO SCALE
NOM NOMINAL
OC ON CENTER
OD OUTSIDE DIAMETER
O TO O OUT TO OUT
OPNG OPENING
OPP OPPOSITE
OVHD OVERHEAD
PEB PRE-ENGINEERED BUILDING
PJF PREFORMED JOINT FILLER
PT PRESSURE TREATED
PERIM PERIMETER
PL PLATE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PLYWD PLYWOOD
PNT PAINT
PR PAIR
PTD PAINTED
PWR POWER
RB RUBBER BASE
RD ROOF DRAIN
RO ROUGH OPENING
RAD RADIUS
REC RECESSED
REINF REINFORCED
REQ'D REQUIRED
REV REVISED (REVISION)
RM ROOM
S SOUTH
SB SPLASH BLOCK
SF SQUARE FEET
SS STAINLESS STEEL
SIM SIMILAR
SPEC SPECIFICATIONS
SQ SQUARE
STD STANDARD
STL STEEL
STOR STORAGE
STRUCT STRUCTURAL
SUSP SUSPENDED
T&G TONGUE AND GROOVE
T/O TOP OF
TELE TELEPHONE
TRTD TREATED
TS TUBE STEEL
TYP TYPICAL
UNFIN UNFINISHED
UNO UNLESS NOTED OTHERWISE
VCT VINYL COMPOSITION TILE
VIF VERIFY IN FIELD
VERT VERTICAL
W WEST
W/ WITH
W/O WITHOUT
WC WATER CLOSET
WWF WELDED WIRE FABRIC
WD WOOD
WH WATER HEATER
WT WEIGHT
CL
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/9
/2
:4
:4
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
G-201
SITE PLAN
2 3EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
Scale: 1/16" = 1'-0"
SITE PLAN
NORTH
0 8 16 32
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
ABBREVIATIONS
UP
WH
DN
BUILDING 112
41 SF
ELEC.
X105
34 SF
OIT
X106
251 SF
BREAKROOM
X103
8516 SF
WAREHOUSE
X101
347 SF
OFFICE
X102
84'-4"
CAPACITYCLR
EXTERIOR
EXIT
35" 175
RAMP DOWN
CAPACITYCLR
EXTERIOR
EXIT
37" 185
68'-0"
1 2
A
B
C
D
E
F
MEZZANINE ABOVE
CAPACITYCLR
EXTERIOR
EXIT
35" 175
CAPACITYCLR
EXTERIOR
EXIT
35" 175
66 SF
UTILITY
ROOM
X104
CHAIN
LINK
GATE
CHAIN LINK ENCLOSURE
D
IS
T A
N C
E
'-8
EGRESS PATH
EGRESS PATH TAG
EGRESS PATH TAG - COMMON PATH
EGRESS IDENTIFICATION
AREA OF REFUGE
HAZARDOUS LOCATION
FIRE EXTINGUISHER BRACKET
FIRE EXTINGUISHER CABINET
FIRE BLANKET CABINET
EMERGENCY RESPONSE REFERENCE
CONTROLLED ACCESS - ALWAYS
UNLOCKED IN DIRECTION OF EGRESS
KNOX BOX
DELAYED EGRESS W/ ALARM
CA
DE
KB
XXX
XXX
FEB
FEC
FBC
CAPACITYCLR
EXTERIOR
EXIT
XX" ###
EXIT
IDENTIFICATION
EGRESS CLEAR
WIDTH
EGRESS CAPACITY
1573 SF
MEZZANINE
X201
BUILDING 112
1 2
A
B
C
D
E
F
EXIT DOOR
AT GRADE
LEVEL
62'-6
HIGH POINT (ABOVE)
WAREHOUSE
X101
EGRESS WIDTH
(per IBC 1005.1)
COMMON PATH OF TRAVEL
(per IBC Chapter 10)
EXIT ACCESS TRAVEL
(per IBC TABLE 1016.1)
DEAD-END CORRIDOR
(per IBC 1018.4)
EXIT DOORS = 35"/(0.20) = 175 PPL
100'-0" MAXIMUM
400'-0" MAXIMUM DISTANCE,
WITH 1017.2.2 EXCEPTIONS
50'-0" MAXIMUM
OCCUPANT LOAD
(per IBC TABLE 1004.1)
OCCUP. 1 = 9255 GSF/500 = 18 PPL
GROSS BUILDING AREA
(OUTSIDE FACE WALLS)
10,144 SF
GROSS MEASURED AREA
(INTERIOR FACE WALLS)
9,255 SF
REQUIRED # OF EXITS
(per IBC 1015.1)
1 EXIT REQUIRED IF UNDER 49
TOTAL OCCUPANTS
REQUIRED DISTANCE
BETWEEN EXITS
48'-10" MINIMUM
FLOOR
AGGREGATE FLOOR AREAS (per TABLE 503):
EXISTING NEW TOTAL
FIRST 0 SF
AREA TOTAL = 10,828 SF
AREA ALLOWED = 70,000 SF Per Story
MEZZANINE 0 SF
9255 SF
1573 SF
EGRESS INFORMATION
BUILDING HEIGHT = 36'-0"
ALLOWABLE HEIGHT = 4 STORIES
AREA AND HEIGHT REQUIREMENTS:
9255 SF
1573 SF
NOT IN PROJECT
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/9
/2
:4
:4
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
G-202
FIRST FLOOR AND MEZZANINE LIFE
SAFETY PLANS
3 3EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
CODE INFORMATION
NORTH
0 4 8 16
Scale: 1/8" = 1'-0"
FIRST FLOOR LIFE SAFETY PLAN
LIFE SAFETY LEGEND
Scale: 1/8" = 1'-0"
MEZZANINE LIFE SAFETY PLAN
NORTH
0 4 8 16
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
1 INSTALL NEW SLOPED GYPSUM BOARD
CEILING.
2 REMOVE NON-LABELLED ROLL UP DOOR
AND FRAME AND REPLACE WITH B-LABEL
ROLL UP SHUTTER.
LEGEND
PROPOSED USE:
OWNED BY:
CODE ENFORCEMENT JURISDICTION: FEDERAL GOVERNMENT
APPLICABLE CODES:
GENERAL CODE INFORMATION:
RENOVATION (EXISTING BUILDING)
CONSTRUCTION TYPE:
SRINKLERED
MEZZANINE
PRIMARY OCCUPANCY:
SECONDARY OCCUPANCY:
PROJECT NAME:
PROJECT ADDRESS:
OWNER OR AGENT:
FEDERAL GOVERNMENT
WAREHOUSE
TYPE IIB
WAREHOUSE-STORAGE S-1
NONE
2021 International Building Code
2018 International Plumbing Code
2018 International Mechanical Code 2018 ADA Code 2017 NFPA 70 National Electrical Code 2021 NFPA 101 Life Safety Code
2015 Architectural Barriers Act
VA Design Guide Architectural Manual 2014 August 01
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129
DEPARTMENT OF VETERANS AFFAIRS
1. IBC HAS BEEN USED AND REFERENCED IN THE
CODE SUMMARY FOR ISSUES NOT ADDRESSED IN
NFPA 101 AND OTHER NFPA SECTIONS PER PG-18-3
DESIGN AND CONSTRUCTION PROCEDURES, TOPIC
1 - CODE, STANDARDS AND EXECUTIVE ORDERS
AND NOTE 1, DATED SEPTEMBER 2013
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WWWWWWWWWWWWWWWWWWWWWW
WWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW
W W
W W
W
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W
W W
W W
W W
W
W W
W W
W W
W W
W W
W W
W W
W W
W
W W W W
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
WWWW
W W
W W
W W
W W
W W
W W
W W
W W
W W
W
W
W
W
W
W
W
W
WWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW
W W
BLDG 146
BLDG 118
VETERANS CIRCLE
SA
M
J A
R E
D R
O A
D
BLDG 112
BLDG 147
W W W W
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GASGAS
EXISTING STORM LINES
(TYPICAL)
SSSSSSSS
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
A B
C D
E
Dwg. of
LocationLocation
Office of Construction and Facilities Management
PROJECT MANAGER: ACG Project NumberCONSULTANTS:
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs
© COPYRIGHT Apogee Consulting Group, P.A.Revisions: Date#
Foresite Group, LLC 3740 Davinci Ct.
Suite 100 Peachtree Corners, GA 30092 o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C. YORK
3400 LEBANON PIKE
MURFREESBORO, TN. 37129 MAY 12, 2022
626A4-21-205
BID DOCUMENTS
ZLRFCM
CIVIL SITE & UTILITY PLAN
CS101
1) CONTRACTOR SHALL NOTIFY COR OF ANY DISCREPANCIES
BETWEEN THE EXISTING CONDITIONS IN THE FIELD AND THE EXISTING
CONDITIONS SHOWN ON THE PLANS BEFORE PROCEEDING WITH ANY
NEW CONSTRUCTION.
2) CONTRACTOR IS RESPONSIBLE FOR CORRECT HORIZONTAL AND
VERTICAL ALIGNMENT OF ALL TIES BETWEEN PROPOSED AND
EXISTING PAVEMENTS, CURB AND GUTTER, SIDEWALKS, WALLS, AND
UTILITIES.
3) NO OUTSIDE STORAGE IS PERMITTED. THIS INCLUDES SUPPLIES,
VEHICLE, EQUIPMENT, PRODUCTS, ETC.
4) THESE PLANS WERE PREPARED WITHOUT THE BENEFIT OF THE
SURVEY. ALL EXISTING UTILITIES AND SITE FEATURES ARE AN
APPROXIMATION
5) MAXIMUM CUT OR FILL SLOPE=3H:1V
9) CONTRACTOR TO PROVIDE VA COR WITH MINIMUM 2 WEEK
NOTICE PRIOR TO ANY INTERRUPTION OF UTILITY SERVICES OR
FACILITY ACCESS.
10) 24 HOUR CONTACT: VA COR
SHEET NOTES:
SHEET KEY NOTES:
KEY PLAN
1) PROVIDE FDC ON EXTERIOR WALL.
2) PROVIDE 8" FIRE MAIN.
3) PROVIDE 10" X 8" TEE.
4) PROVIDE 8" GATE VALVE.
5) PROVIDE POST INDICATOR VALVE AT LEAST 36' (HEIGHT OF
BUILDING) FROM BUILDING WALL.
6) PROVIDE 10" GATE VALVE.
7) JACK AND BORE NEW FIRE MAIN UNDER VETERANS
CIRCLE.PROVIDE TRAFFIC MANAGEMENT.
8) CONNECTION TO EXISTING 10" MAIN TO BE MADE WEST OF
EXISTING PRV.
9) PROVIDE NEW CONCRETE SIDEWALK. SEE CONCRETE PAVING
NOTES ON SHEET CD101 AND DETAIL 1 ON SHEET CS501.
1" = 20'
SCALE IN FEET
20 10 20 40
LEGEND
EXISTING WATER LINE
EXISTING SANITARY SEWER LINE
PROPOSED WATER LINE
EXISTING SITE LIGHTING
SS SS SS
W W W
W W W
FIS
H
ER
H O
U S E
PA
R
KIN
G S
PA
C
ES
EN
TER
EXIT
PROJECT AREA
GAS GAS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
SS
WWWWWWWWWWWWWWWWWWWWWW
WWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWWW
W W
W W
W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W W
W W
W W
W W
W W
W W
W W
W W
W W
W W
W W
W W
W
W W W W
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG
/T
UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
UG/T
BLDG 146
BLDG 118
VETERANS CIRCLE
SA
M
J A
R E
D R
O A
D
BLDG 112
BLDG 147
W W W W
W W
W W
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GASGAS
EXISTING STORM LINES
(TYPICAL)
SSSSSSSS
LEGEND
UTILITIES TO BE REMOVED.
CONCRETE TO BE REMOVED.
EXISTING WATER
EXISTING SANITARY SEWER
EXISTING FIRE HYDRANT
EXISTING VALVE
EXISTING NATURAL GAS
EXISTING LIGHT
DEMOLITION NOTES:
1) ALL NEW WORK SHOWN IN THESE SHEETS SHALL COMPLY
WITH APPLICABLE STATE, FEDERAL, AND LOCAL BUILDING AND
UTILITY INSTALLATION CODES.
2) ALL MATERIALS AND CONSTRUCTION METHODS SHALL BE IN
ACCORDANCE WITH VA STANDARD SPECIFICATIONS.
3) THERE MAY BE ADDITIONAL UTILITIES NOT SHOWN ON THESE
PLANS. THE ENGINEER ASSUMES NO RESPONSIBILITY FOR
LOCATIONS SHOWN, AND IT SHALL BE THE RESPONSIBILITY OF THE
CONTRACTOR TO FIELD VERIFY THE LOCATIONS OF ALL UTILITIES
WITHIN THE LIMITS OF CONSTRUCTION AND TO NOTIFY THE COR
AND ENGINEER IN CASE OF DISCREPANCIES THAT AFFECT THE
CONSTRUCTION PROJECT. ALL IN PLACE UTILITIES ARE TO BE
PROTECTED UNLESS OTHERWISE NOTED.
4) THE CONTRACTOR IS RESPONSIBLE FOR NOTIFICATION OF AND
LIAISON WITH UTILITY COMPANIES IN THE PROCESS OF LOCATION
AND RELOCATION OF AND TIE-IN TO UTILITIES.
5) CONTRACTOR IS RESPONSIBLE FOR ANY DAMAGE THAT MAY
OCCUR TO ANY ADJACENT STRUCTURES OR PROPERTY, OR ANY
EXISTING STRUCTURES WITHIN LIMITS OF CONSTRUCTION THAT
ARE DESIGNATED ON THE PLANS TO REMAIN, AND SHALL REPAIR
OR REPLACE SUCH DAMAGED PROPERTY TO THE COR'S
SATISFACTION AT NO COST TO THE VA.
6) THE CONTRACTOR SHALL NOT DEVIATE FROM THESE PLANS
AND SPECIFICATIONS WITHOUT THE PRIOR WRITTEN CONSENT OF
THE ENGINEER.
7) CONTRACTOR IS RESPONSIBLE FOR CONTACTING THE COR
AND ALL EXISTING UTILITY PROVIDERS BEFORE REMOVING ANY/ALL
UTILITIES FROM THEIR EXISTING LOCATION ON THE SITE. THE
CONTRACTOR SHALL PERFORM ALL UTILITY DEMOLITION OR
RELOCATION ACTIVITIES IN ACCORDANCE WITH THE EXISTING
UTILITIES SPECIFICATIONS, MATERIALS, AND REQUIREMENTS.
8) THESE PLANS WERE PREPARED WITHOUT THE BENEFIT OF THE
SURVEY. ALL EXISTING UTILITIES AND SITE FEATURES ARE AN
APPROXIMATION
9) CONTRACTOR TO PROVIDE VA COR WITH MINIMUM 2 WEEK
NOTICE PRIOR TO ANY INTERRUPTION OF UTILITY SERVICES OR
FACILITY ACCESS.
W W
SS SS
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
A B
C D
E
Dwg. of
LocationLocation
Office of Construction and Facilities Management
PROJECT MANAGER: ACG Project NumberCONSULTANTS:
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs
© COPYRIGHT Apogee Consulting Group, P.A.Revisions: Date#
Foresite Group, LLC 3740 Davinci Ct.
Suite 100 Peachtree Corners, GA 30092 o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C. YORK
3400 LEBANON PIKE
MURFREESBORO, TN. 37129 MAY 12, 2022
626A4-21-205
BID DOCUMENTS
ZLRFCM
1) EXISTING 4" WATER LINE TO BE REMOVED AT CORP STOP AT
MAIN.
2) EXISTING POST INDICATOR VALVE TO BE REMOVED.
3) EXISTING HVAC UNIT TO REMAIN.
4) EXISTING POST INDICATOR VALVE TO REMAIN.
5) EXISTING NATURAL GAS LINE TO REMAIN. THIS GAS MAIN
SERVES THE BOILERS FOR THE ENTIRE CAMPUS AND MUST BE
PROTECTED.
6) EXISTING SANITARY SEWER MAIN AND LATERAL TO REMAIN
7) EXISTING 10" WATER MAIN
1" = 20'
SCALE IN FEET
20 10 20 40
FIS
H
ER H
O U S E
PA
R
KIN
G S
PAC
ES
EN
TER
EXIT
SHEET NOTES:
SHEET KEY NOTES:
KEY PLAN
FIS
H
ER H
O U S E
PA
R
KIN
G S
PAC
ES
EN
TER
EXIT
DEMOLITION PLAN
CD101
PROJECT AREA
GAS
CONCRETE PAVING
1.) PROJECT CONDITIONS
A. TRAFFIC CONTROL: MAINTAIN ACCESS FOR VEHICULAR AND PEDESTRIAN TRAFFIC AS REQUIRED
FOR OTHER CONSTRUCTION ACTIVITIES.
2.) STEEL REINFORCEMENT
A. PLAIN-STEEL WELDED WIRE REINFORCEMENT: ASTM A 185/A 185M, FABRICATED FROM AS-DRAWN
STEEL WIRE INTO FLAT SHEETS.
B. REINFORCING BARS: ASTM A 615/A 615M, GRADE 60 ; DEFORMED.
C. JOINT DOWEL BARS: ASTM A 615/A 615M, GRADE 60 PLAIN-STEEL BARS. CUT BARS TRUE TO LENGTH
WITH ENDS SQUARE AND FREE OF BURRS.
D. BAR SUPPORTS: BOLSTERS, CHAIRS, SPACERS, AND OTHER DEVICES FOR SPACING, SUPPORTING, AND FASTENING REINFORCING BARS, WELDED WIRE REINFORCEMENT, AND DOWELS IN PLACE.
MANUFACTURE BAR SUPPORTS ACCORDING TO CRSI'S "MANUAL OF STANDARD PRACTICE" FROM
STEEL WIRE, PLASTIC, OR PRECAST CONCRETE OF GREATER COMPRESSIVE STRENGTH THAN
CONCRETE SPECIFIED, AND AS FOLLOWS:
3.) CONCRETE MATERIALS
A. CEMENTITIOUS MATERIAL: USE CEMENTITIOUS MATERIALS, OF SAME TYPE, BRAND, AND SOURCE
THROUGHOUT PROJECT.
B. NORMAL-WEIGHT AGGREGATES: ASTM C 33,, UNIFORMLY GRADED. PROVIDE AGGREGATES FROM A
SINGLE SOURCE.
1. MAXIMUM COARSE-AGGREGATE SIZE: 1 INCH NOMINAL.
2. FINE AGGREGATE: FREE OF MATERIALS WITH DELETERIOUS REACTIVITY TO ALKALI IN CEMENT.
4.) RELATED MATERIALS
A. JOINT FILLERS: ASTM D 1751, ASPHALT-SATURATED CELLULOSIC FIBER IN PREFORMED STRIPS.
5.) WHEEL STOPS
A. WHEEL STOPS: PRECAST, AIR-ENTRAINED CONCRETE, 2500-PSI MINIMUM COMPRESSIVE
STRENGTH,. PROVIDE CHAMFERED CORNERS AND DRAINAGE SLOTS ON UNDERSIDE AND HOLES
FOR ANCHORING TO SUBSTRATE.
6.) SIDEWALKS
A. SIDEWALKS: SLOPE SIDEWALKS AWAY FROM BUILDING WITH A 1.5% CROSS-SLOPE UNLESS
DRAWINGS INDICATE OTHERWISE.
7.) PREPARATION
A. REMOVE LOOSE MATERIAL FROM COMPACTED SUBBASE SURFACE IMMEDIATELY BEFORE PLACING
CONCRETE.
8.) STEEL REINFORCEMENT
A. GENERAL: COMPLY WITH CRSI'S "MANUAL OF STANDARD PRACTICE" FOR FABRICATING, PLACING, AND SUPPORTING REINFORCEMENT.
B. CLEAN REINFORCEMENT OF LOOSE RUST AND MILL SCALE, EARTH, ICE, OR OTHER BOND-REDUCING
MATERIALS.
C. ARRANGE, SPACE, AND SECURELY TIE BARS AND BAR SUPPORTS TO HOLD REINFORCEMENT IN
POSITION DURING CONCRETE PLACEMENT. MAINTAIN MINIMUM COVER TO REINFORCEMENT.
D. INSTALL WELDED WIRE REINFORCEMENT IN LENGTHS AS LONG AS PRACTICABLE. LAP ADJOINING
PIECES AT LEAST ONE FULL MESH, AND LACE SPLICES WITH WIRE. OFFSET LAPS OF ADJOINING
WIDTHS TO PREVENT CONTINUOUS LAPS IN EITHER DIRECTION.
E. ZINC-COATED REINFORCEMENT: USE GALVANIZED-STEEL WIRE TIES TO FASTEN ZINC-COATED
REINFORCEMENT. REPAIR CUT AND DAMAGED ZINC COATINGS WITH ZINC REPAIR MATERIAL.
9.) JOINTS
A. GENERAL: FORM CONSTRUCTION, ISOLATION, AND CONTRACTION JOINTS AND TOOL EDGES TRUE
TO LINE, WITH FACES PERPENDICULAR TO SURFACE PLANE OF CONCRETE. CONSTRUCT
TRANSVERSE JOINTS AT RIGHT ANGLES TO CENTERLINE UNLESS OTHERWISE INDICATED.
1. WHEN JOINING EXISTING PAVING, PLACE TRANSVERSE JOINTS TO ALIGN WITH PREVIOUSLY
PLACED JOINTS UNLESS OTHERWISE INDICATED.
2. ENSURE FORMS PROVIDE CORRECT HORIZONTAL AND VERTICAL ALIGNMENT BETWEEN NEW
AND EXISTING PAVEMENTS, SIDEWALKS, CURB AND GUTTER, ETC.
B. CONSTRUCTION JOINTS: SET CONSTRUCTION JOINTS AT SIDE AND END TERMINATIONS OF PAVING
AND AT LOCATIONS WHERE PAVING OPERATIONS ARE STOPPED FOR MORE THAN ONE-HALF HOUR
UNLESS PAVING TERMINATES AT ISOLATION JOINTS.
1. CONTINUE STEEL REINFORCEMENT ACROSS CONSTRUCTION JOINTS UNLESS OTHERWISE
INDICATED. DO NOT CONTINUE REINFORCEMENT THROUGH SIDES OF PAVING STRIPS UNLESS
OTHERWISE INDICATED.
2. PROVIDE TIE BARS AT SIDES OF PAVING STRIPS WHERE INDICATED.
3. KEYED JOINTS: PROVIDE PREFORMED KEYWAY-SECTION FORMS OR BULKHEAD FORMS WITH
KEYS UNLESS OTHERWISE INDICATED. EMBED KEYS AT LEAST 1-1/2 INCHES INTO CONCRETE.
4. DOWELED JOINTS: INSTALL DOWEL BARS AND SUPPORT ASSEMBLIES AT JOINTS WHERE
INDICATED. LUBRICATE OR COAT WITH ASPHALT ONE-HALF OF DOWEL LENGTH TO PREVENT
CONCRETE BONDING TO ONE SIDE OF JOINT.
C. ISOLATION JOINTS: FORM ISOLATION JOINTS OF PREFORMED JOINT-FILLER STRIPS ABUTTING CONCRETE CURBS, CATCH BASINS, MANHOLES, INLETS, STRUCTURES, OTHER FIXED OBJECTS, AND
WHERE INDICATED.
1. LOCATE EXPANSION JOINTS AT INTERVALS OF 30 FEET UNLESS OTHERWISE INDICATED.
2. EXTEND JOINT FILLERS FULL WIDTH AND DEPTH OF JOINT.
3. TERMINATE JOINT FILLER NOT LESS THAN 1/2 INCH OR MORE THAN 1 INCH BELOW FINISHED
SURFACE IF JOINT SEALANT IS INDICATED.
4. PLACE TOP OF JOINT FILLER FLUSH WITH FINISHED CONCRETE SURFACE IF JOINT SEALANT IS
NOT INDICATED.
5. FURNISH JOINT FILLERS IN ONE-PIECE LENGTHS. WHERE MORE THAN ONE LENGTH IS
REQUIRED, LACE OR CLIP JOINT-FILLER SECTIONS TOGETHER.
6. DURING CONCRETE PLACEMENT, PROTECT TOP EDGE OF JOINT FILLER WITH METAL, PLASTIC, OR OTHER TEMPORARY PREFORMED CAP. REMOVE PROTECTIVE CAP AFTER CONCRETE HAS
BEEN PLACED ON BOTH SIDES OF JOINT.
D. CONTRACTION JOINTS: FORM WEAKENED-PLANE CONTRACTION JOINTS, SECTIONING CONCRETE INTO AREAS AS INDICATED. CONSTRUCT CONTRACTION JOINTS FOR A DEPTH EQUAL TO AT LEAST
ONE-FOURTH OF THE CONCRETE THICKNESS, AS FOLLOWS:
1. GROOVED JOINTS: FORM CONTRACTION JOINTS AFTER INITIAL FLOATING BY GROOVING AND
FINISHING EACH EDGE OF JOINT WITH GROOVING TOOL TO A 1/4-INCH RADIUS. REPEAT
GROOVING OF CONTRACTION JOINTS AFTER APPLYING SURFACE FINISHES. ELIMINATE
GROOVING-TOOL MARKS ON CONCRETE SURFACES.
2. SAWED JOINTS: FORM CONTRACTION JOINTS WITH POWER SAWS EQUIPPED WITH
SHATTERPROOF ABRASIVE OR DIAMOND-RIMMED BLADES. CUT 1/8-INCH- WIDE JOINTS INTO
CONCRETE WHEN CUTTING ACTION WILL NOT TEAR, ABRADE, OR OTHERWISE DAMAGE
SURFACE AND BEFORE DEVELOPING RANDOM CONTRACTION CRACKS.
3. DOWELED CONTRACTION JOINTS: INSTALL DOWEL BARS AND SUPPORT ASSEMBLIES AT JOINTS
WHERE INDICATED. LUBRICATE OR COAT WITH ASPHALT ONE-HALF OF DOWEL LENGTH TO
PREVENT CONCRETE BONDING TO ONE SIDE OF JOINT.
E. EDGING: AFTER INITIAL FLOATING, TOOL EDGES OF PAVING, GUTTERS, CURBS, AND JOINTS IN
CONCRETE WITH AN EDGING TOOL TO A 1/4-INCH RADIUS. REPEAT TOOLING OF EDGES AFTER
APPLYING SURFACE FINISHES. ELIMINATE EDGING-TOOL MARKS ON CONCRETE SURFACES.
10.) FIELD QUALITY CONTROL
A. TESTING AGENCY: ENGAGE A QUALIFIED TESTING AGENCY TO PERFORM TESTS AND INSPECTIONS.
B. PROMPTLY SEND TEST REPORTS TO THE ENGINEER FOR REVIEW AND APPROVAL.
C. TESTING SERVICES: TESTING OF COMPOSITE SAMPLES OF FRESH CONCRETE OBTAINED
ACCORDING TO ASTM C 172 SHALL BE PERFORMED BY THE GENERAL CONTRACTOR'S TESTING
AGENCY ACCORDING TO THE FOLLOWING REQUIREMENTS:
1. TESTING FREQUENCY: OBTAIN AT LEAST ONE COMPOSITE SAMPLE FOR EACH 100 CU. YD. OR
FRACTION THEREOF OF EACH CONCRETE MIXTURE PLACED EACH DAY. WHEN FREQUENCY OF
TESTING WILL PROVIDE FEWER THAN FIVE COMPRESSIVE-STRENGTH TESTS FOR EACH
CONCRETE MIXTURE, TESTING SHALL BE CONDUCTED FROM AT LEAST FIVE RANDOMLY
SELECTED BATCHES OR FROM EACH BATCH IF FEWER THAN FIVE ARE USED.
2. SLUMP: ASTM C 143/C 143M; ONE TEST AT POINT OF PLACEMENT FOR EACH COMPOSITE
SAMPLE, BUT NOT LESS THAN ONE TEST FOR EACH DAY'S POUR OF EACH CONCRETE MIXTURE.
PERFORM ADDITIONAL TESTS WHEN CONCRETE CONSISTENCY APPEARS TO CHANGE.
3. AIR CONTENT: ASTM C 231, PRESSURE METHOD; ONE TEST FOR EACH COMPOSITE SAMPLE,
BUT NOT LESS THAN ONE TEST FOR EACH DAY'S POUR OF EACH CONCRETE MIXTURE.
4. CONCRETE TEMPERATURE: ASTM C 1064/C 1064M; ONE TEST HOURLY WHEN AIR TEMPERATURE
IS 40 DEG F AND BELOW AND WHEN IT IS 80 DEG F AND ABOVE, AND ONE TEST FOR EACH
COMPOSITE SAMPLE.
5. COMPRESSION TEST SPECIMENS: ASTM C 31/C 31M; CAST AND LABORATORY CURE ONE SET OF
THREE STANDARD CYLINDER SPECIMENS FOR EACH COMPOSITE SAMPLE.
6. COMPRESSIVE-STRENGTH TESTS: ASTM C 39/C 39M; TEST ONE SPECIMEN AT SEVEN DAYS AND
TWO SPECIMENS AT 28 DAYS. A COMPRESSIVE-STRENGTH TEST SHALL BE THE AVERAGE
COMPRESSIVE STRENGTH FROM TWO SPECIMENS OBTAINED FROM SAME COMPOSITE SAMPLE
AND TESTED AT 28 DAYS.
D. STRENGTH OF EACH CONCRETE MIXTURE WILL BE SATISFACTORY IF AVERAGE OF ANY THREE
CONSECUTIVE COMPRESSIVE-STRENGTH TESTS EQUALS OR EXCEEDS SPECIFIED COMPRESSIVE
STRENGTH AND NO COMPRESSIVE-STRENGTH TEST VALUE FALLS BELOW SPECIFIED COMPRESSIVE
STRENGTH BY MORE THAN 500 PSI.
E. TEST RESULTS SHALL BE REPORTED IN WRITING TO ENGINEER, CONCRETE MANUFACTURER, AND CONTRACTOR WITHIN 48 HOURS OF TESTING. REPORTS OF COMPRESSIVE-STRENGTH TESTS SHALL CONTAIN PROJECT IDENTIFICATION NAME AND NUMBER, DATE OF CONCRETE PLACEMENT, NAME OF CONCRETE TESTING AND INSPECTING AGENCY, LOCATION OF CONCRETE BATCH IN WORK, DESIGN
COMPRESSIVE STRENGTH AT 28 DAYS, CONCRETE MIXTURE PROPORTIONS AND MATERIALS,
COMPRESSIVE BREAKING STRENGTH, AND TYPE OF BREAK FOR BOTH 7- AND 28-DAY TESTS.
F. ADDITIONAL TESTS: TESTING AND INSPECTING AGENCY SHALL MAKE ADDITIONAL TESTS OF
CONCRETE WHEN TEST RESULTS INDICATE THAT SLUMP, AIR ENTRAINMENT, COMPRESSIVE
STRENGTHS, OR OTHER REQUIREMENTS HAVE NOT BEEN MET, AS DIRECTED BY ENGINEER.
G. CONCRETE PAVING WILL BE CONSIDERED DEFECTIVE IF IT DOES NOT PASS TESTS AND
INSPECTIONS.
H. ADDITIONAL TESTING AND INSPECTING, AT CONTRACTOR'S EXPENSE, WILL BE PERFORMED TO
DETERMINE COMPLIANCE OF REPLACED OR ADDITIONAL WORK WITH SPECIFIED REQUIREMENTS.
I. PREPARE TEST AND INSPECTION REPORTS.
11.) REPAIRS AND PROTECTION
A. REMOVE AND REPLACE CONCRETE PAVING THAT IS BROKEN, DAMAGED, OR DEFECTIVE OR THAT
DOES NOT COMPLY WITH REQUIREMENTS IN THIS SECTION. REMOVE WORK IN COMPLETE
SECTIONS FROM JOINT TO JOINT UNLESS OTHERWISE APPROVED BY ENGINEER.
B. DRILL TEST CORES, WHERE DIRECTED BY ENGINEER, WHEN NECESSARY TO DETERMINE
MAGNITUDE OF CRACKS OR DEFECTIVE AREAS. FILL DRILLED CORE HOLES IN SATISFACTORY
PAVING AREAS WITH PORTLAND CEMENT CONCRETE BONDED TO PAVING WITH EPOXY ADHESIVE.
C. PROTECT CONCRETE PAVING FROM DAMAGE. EXCLUDE TRAFFIC FROM PAVING FOR AT LEAST 14
DAYS AFTER PLACEMENT. WHEN CONSTRUCTION TRAFFIC IS PERMITTED, MAINTAIN PAVING AS
CLEAN AS POSSIBLE BY REMOVING SURFACE STAINS AND SPILLAGE OF MATERIALS AS THEY
OCCUR.
D. MAINTAIN CONCRETE PAVING FREE OF STAINS, DISCOLORATION, DIRT, AND OTHER FOREIGN
MATERIAL. SWEEP PAVING NOT MORE THAN TWO DAYS BEFORE DATE SCHEDULED FOR
SUBSTANTIAL COMPLETION INSPECTIONS.
VA PROJECT NUMBER
Building Number
Drawing Number
Project Title
Date Checked Drawn
Drawing Title
Approved: Project Director
VA FORM 08-6231
A
B C
D E
21 4 5 6 7
321 4 5 6 7
A B
C D
E
Dwg. of
LocationLocation
Office of Construction and Facilities Management
PROJECT MANAGER: ACG Project NumberCONSULTANTS:
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs
© COPYRIGHT Apogee Consulting Group, P.A.Revisions: Date#
Foresite Group, LLC 3740 Davinci Ct.
Suite 100 Peachtree Corners, GA 30092 o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C. YORK
3400 LEBANON PIKE
MURFREESBORO, TN. 37129 MAY 12, 2022
626A4-21-205
BID DOCUMENTS
ZLRFCM
CONSTRUCTION DETAILS
CS501
CS501
CS501
CS501
CS501
CS501
CS501
CS501
EXISTING
12'-2"
11'-3"
9'-3" 11'-5"
8'
V E
T E
R A
N S
B
LV
D
VETERANS C
IR
CLE
SOUTHVIEW DRIVE
C O
M P
T O
N R
O A
D
VETERANS CIRCLE
SAM JARED ROAD
VETERANS CIRCLE
V E
T E
R A
N S
C
IR
C L E
E A
S T
M A
IN
S
T R
E E
T
EASTVIEW DRIVE
NORTHVIEW DRIVE
B O
IL
E
R P
LA
N
T R
D
P A
R K
R O
A D
P A
R K
R O
A D
G A
R D
E N
D R
IV
E
JO
H
N F
C O
A D
Y D
R
IV
E
JO
HN
F C
O
AD
Y
DR
IV
E
LAKE RO
AD
HILL
S
TREET
LAKE ROAD
TENNESSEE
STATE
VETERANS
HOME
81121
147 112
109 107
2 9
FISHER HOUSE
FLAMABLE STORAGE
CHOP
HOUSE
LP
TANK
3/4" Propane LineApprox. 27" Below Grade
1-1/4" Propane LineApprox. 18" Below Grade
FISHER HOUSE
PARKING
27 SPACES
ENTER
EXIT
BUILDING 146
BUILDING IN CONTRACT
BUILDING NUMBERSXX
CONTRACTOR
STAGING AREA
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/9
/2
:4
:5
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
A-001
LOGISTICS PLAN
1 5EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
Scale: 1" = 100'-0"
LOGISTICS PLAN
A. CONTRACTOR SHALL PROVIDE TEMPORARY
ENTRANCES AND SCAFFOLDING TO PROVIDE
CONSTRUCTION ACCESS TO CEILING
CONSTRUCTION AREA.
B. CONTRACTOR TO ENSURE THAT SCAFFOLDING
AND PROTECTIVE MEASURES COMPLY WITH ALL
OSHA REQUIREMENTS. CONTRACTOR WILL BE
RESPONSIBLE FOR DESIGN AND ENGINEERING OF
SCAFFOLDING AND PROTECTIVE MEASURES.
C. CONTRACTOR SHALL BE REQUIRED TO INSPECT
ALL SCAFFOLDING AND PROTECTIVE MEASURES
DAILY TO ENSURE THEY ARE SAFE AND COMPLY
WITH OSHA REQUIREMENTS.
D. CONTRACTOR SHALL REPAIR ALL AREAS
DAMAGED OR DISTURBED DURING
CONSTRUCTION. THIS INCLUDES BUILDING
FINISHES, EXTERIOR OR INTERIOR, LANDSCAPE,
SIDEWALKS, PAVING OR ANY AREA DAMAGED BY
THE CONSTRUCTION WORK. RESTORE AREAS TO
ORIGINAL CONDITION.
E. DUMPSTER LOCATION IS TO BE COORDINATED
WITH THE COR PRIOR TO LOCATION ON SITE.
F. CONTRACTOR SHALL PROTECT THE LANDSCAPE
SPRINKLER SYSTEM IN CONSTRUCTION LAY
DOWN AREA FROM DAMAGE. CAP ALL HEADS IN
THIS AREA DURING THE CONSTRUCTION PERIOD.
RESTORE SPRINKLER SYSTEM TO FULL
OPERATION AT END OF CONSTRUCTION.
G. CONTRACTOR SHALL PREPARE A PLAN OF THE
LAY DOWN/SECURITY FENCE AREA WITH
LOCATION ALL ELEMENTS INCLUDING DUMPSTER
AND TRASH COLLECTION AREA AND SHALL
SUBMIT TO COR FOR REVIEW.
H. CONTRACTOR TO ENSURE THE CONSTRUCTION
FENCED AREA IS LOCKED/SECURED DURING ALL
PERIODS WHEN CONSTRUCTION WORK IS NOT
BEING PERFORMED.
I. CONTRACTOR SHALL RESTORE ALL
LANDSCAPING, HARDSCAPING AND SITE
ELEMENTS TO THE ORIGINAL CONDITION AT THE
COMPLETION OF CONSTRUCTION. CONTRACTOR
WILL PHOTOGRAPH AND DOCUMENT EXISTING
CONDITIONS PRIOR TO INSTALLING FENCING,
SCAFFOLDING OR STATING ANY CONSTRUCTION
WORK.
SITE PLAN LEGEND
1 CONTRACTOR PARKING LOCATION, LOT 8.
2 CONTRACTOR STAGING AND LAYDOWN AREA
CONTRACTOR ACCESS ROUTE
N O
R T
H
0 4 8 16
BUILDING 112
66 SF
UTILITY
ROOM
X104
251 SF
BREAKROOM
X103
8516 SF
WAREHOUSE
X101
347 SF
OFFICE
X102
41 SF
ELEC.
X105
34 SF
OIT
X106
399 SF
CAGED
STORAGE
X101A
MEZZANINE ABOVE
RAMP-DOWN
1 2
A
B
C
D
E
F
X101
1'-5"9'-2"1'-5"
NOT IN PROJECT
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/9
/2
:4
:5
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
AD101
FIRST FLOOR DEMOLITION PLAN
2 5EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
NORTH
0 4 8 16
Scale: 1/8" = 1'-0"
FIRST FLOOR DEMOLITION PLAN
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
1 REMOVE TILE FLOORING, TILE BASE FOR
SPRINKLER ENTRANCE PIPE REMOVAL.
2 REMOVE EXISTING OVERHEAD DOOR (X101),
FRAME AND TRACK.
3 REMOVE AND REINSTALL EXISTING ACT
CEILING FOR NEW FIRE SPRINKLER PIIPING
4 PORTION OF CONCRETE SLAB AND PIPE TO BE
REMOVED (SHOWN SHADED)
LEGEND
251 SF
BREAKROOM
X103
8516 SF
WAREHOUSE
X101
347 SF
OFFICE
X102
BUILDING 112
34 SF
OIT
X106
41 SF
ELEC.
X105
UTILITY
ROOM
X104
CAGED
STORAGE
X101A
B LABEL OVERHEAD DOOR
AE301
_____4
AE301
X101
AE301
1 2
A
B
C
D
E
F
12'-0"
REFLECTED CEILING PLAN
LEGEND
DENOTES GWB
SOFFIT/CEILING
CEILING CONTRACTOR TO MEASURE EACH CEILING
AREA AND ESTABLISH A CEILING LAYOUT TO BALANCE
BORDER WIDTHS AT OPPOSITE EDGES OF EACH
ROOM. AVOID USE OF LESS-THAN 6" TILES.
SPRINKLER HEAD
UNIT HEATER
CEILING FAN
8516 SF
WAREHOUSE
X101
AE301
HIGH POINT
GWB
SLOPED
CEILING
AE301
_____4
AE301
1 2
A
B
C
D
E
F
GWB
SLOPED
CEILING
AE301
AE301
WELL FOR
FAN ACCESS
WELL FOR
FAN ACCESS
NOT IN PROJECT
4"
CEILING
DEAD
AIR
SPACE
ACCEPTABLE
LOCATIONS
FOR THE
FUSIBLE LINK
DETECTOR
SIDE WALL
NEVER
HERE
NOTE: MEASUREMENTS SHOWN ARE TO
THE CLOSEST EDGE OF THE DETECTOR.
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/9
/2
:4
:5
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
AE101
FIRST FLOOR PLAN AND FIRST FLOOR
REFLECTED CEILING PLAN
3 5EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
NORTH
0 4 8 16
Scale: 1/8" = 1'-0"
FIRST FLOOR PLAN
Scale: 1/8" = 1'-0"
FIRST FLOOR REFLECTED CEILING PLAN
NORTH
0 4 8 16
1 NEW OVERHEAD FIRE RATED DOOR,
X101 (B-LABEL, 1 1/2 HR. FIRE RATED).
WITH FUSIBLE LINK-SEE DETAIL 3/AE101
2 5/8" SUSPENDED GWB CEILING
THROUGHOUT MAIN AREA.
3 REMOVE AND REINSTALL EXISTING ACT
CEILING FOR NEW FIRE SPRINKLER
PIPING.
4 INSTALL RUBBER DOOR THRESHOLD
SEAL STRIP BY JIN & BAO OR SIMILAR
WITH ADHESIVE AND 1/4" DIA.
EXPANSION BOLTS AT 32" OC.
5 PROVIDE CONCRETE PATCH
6 PROVIDE NEW CERAMIC TILE FLOORING
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
CONTRACTOR NOTE:
1. BUILDING IS OCCUPIED. WORK SHALL BE COMPLETED
IN PHASES TO PROVIDE THE LEAST DISTURBANCE
POSSIBLE. WORK SCHEDULE TO BE REVIEWED AND
CONFIRMED PRIOR TO COMMENCEMENT WITH COR AS
PER SPECIFICATIONS.
LEGEND
Scale: 3" = 1'-0"
FUSIBLE LINK LOCATION
INTERIOR PHOTOS FOR REFERENCE
FIRST FLOOR
0"
MEZZANINE
12' - 0"
BOTTOM OF CEILING
23' - 0"
GIRT ELEV. 18'-0" AFF
GIRT ELEV. 14'-0" AFF
GIRT ELEV. 12'-0" AFF
GIRT ELEV. 7'-0" AFF
EXIST. METAL WALL PANEL
EXIST. 2" BATT INSULATION
EXIST. COLUMN (BEYOND)
EXIST. GIRT
NEW SUSPENDED GWB
R-30 BATT INSULATION
D
EXIST. STANDING SEAM METAL ROOFING
EXIST. BATT INSULATION
EXIST. PURLIN
4" POLY ISO INSULATION
EXIST. SLOPED BEAM/RAFTER
COLD FORM FRAMING
SUSPENSION WIRES
GWB SUSPENSION SYSTEM
5/8" GWB CEILING (MAX. 2/12 SLOPE)
SPRINKLERS BELOW CLG.
D
R-30 BATT INSULATION
AE301
FIRST FLOOR
0"
MEZZANINE
12' - 0"
BOTTOM OF CEILING
23' - 0"
ROOF
36' - 0"
AE301
AE301
NEW SUSPENDED GWB
CELING ON 7/8" FURRING
CHANNEL
H.P. CEILING ELEV.
28'-6"
OVERHEAD DOOR AND TRACK
1 2
SUSPENDED WIRE ON COLD
FORM FRAMING
RAFTER
R-30 BATT
INSULATION
BOTTOM OF CEILING
23' - 0"
ROOF
36' - 0"
A
6'-0"
EXIST. STANDING SEAM METAL ROOFING
COLD FORM FRAMING
5/8" GWB CEILING
(MAX. 2/12 SLOPE)EXIST. METAL WALL PANEL
EXIST. FAN
3 5/8" METAL
STUDS @ 16" O.C.
2 C10 COLD FORM
MINIMUM
10" NEW CEILING JOIST
100S200 - 68 (14 GA.) @24"O.C.
THE STEEL NETWORK BC800 @4'-0" O.C.
ATTACH TO JOIST W/2≈ #10 SCREWS
ATTACH THE CRC W/2≈ #10 SCREWS
150U50 - 54 (16 GA.) BRIDGING
@48" O.C. MAX (TYPICAL)
EXISTING PEMB. FRAME
THE STEEL NETWORK STIFFCLIP 'AL800'
ATTACH TO PEMB W/3 ≈ #12 SCREWS
ATTACH TO JOIST W/4 ≈ #12 SCREWS
STAGGER CLIPS TO AVOID CONFLICTS
BETWEEN OPPOSING SCREWS
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/9
/2
:4
:5
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
AE301
WALL SECTIONS, BUILDING SECTION,
AND DETAILS
4 5EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
Scale: 3/4" = 1'-0"
WALL SECTION
Scale: 1 1/2" = 1'-0"
CEILING/ROOF SECTION
Scale: 1/8" = 1'-0"
BUILDING SECTION
Scale: 3/4" = 1'-0"
SECTION @FAN WELL
Scale: 1 1/2" = 1'-0"
COLD FORM FRAMING CONNECTION
OH-1
S E
E S
C H
E D
U L E
SEE SCHEDULE
1. REFERENCE ROOM FINISH SCHEDULE , FINISH MATERIAL LEGEND AND SPECIFICATION 09 06 00 SCHEDULE OF
FINISHES FOR MORE INFORMATION.
2. REFERENCE REFLECTED CEILING PLAN FOR ADDITIONAL CEILING INFO.
3. ALL NEW INTERIOR FINISHES, INCLUDING FLOOR, WALL, AND CEILING MATERIALS, SHALL BE IN ACCORDANCE WITH FLAME SPREAD AND SMOKE DEVELOPMENT REQUIREMENTS FOUND IN THE CURRENT EDITION OF THE
INTERNATIONAL BUILDING CODE.
4. THE CONTRACTOR SHALL BE RESPONSIBLE TO VERIFY THAT ALL NEW INTERIOR WALL AND CEILING FINISHES WILL BE CLASS B MINIMUM, WITH A FLAME SPREAD RATING OF 75 MAXIMUM AND A SMOKE DEVELOPED INDEX
OF 450 MAXIMUM PER IBC SECTION 803
5. PREPARE ALL FLOOR AND WALL CONSTRUCTION, NEW AND/OR EXISTING, TO RECEIVE NEW FINISHES IN ACCORDANCE WITH MANUFACTURER’S RECOMMENDED INSTALLATION METHODS AND MATERIALS FOR ALL
FINISHES.
6. PRIOR TO INSTALLATION OF NEW FINISHES, CONTRACTOR SHALL INSPECT ALL SUBSTRATES. IF A SUBSTRATE IS DEEMED UNACCEPTABLE, THE CONTRACTOR SHALL TAKE THE NECESSARY STEPS TO RECTIFY THE SITUATION OR CONTACT THE ARCHITECT WITH THE CONCERN. PROCEEDING WITH THE INSTALLATION OF FINISHES WILL BE INDICATION THAT THE INSTALLER / FINISHER ACCEPTS CONDITION OF SUBSTRATE.
7. USE MANUFACTURER'S RECOMMENDED INSTALLATION METHODS AND MATERIALS FOR ALL FINISHES.
8. FINISH LEVEL OF GYP. BD. WALLS, CEILINGS AND SOFFITS TO BE LEVEL 4, U.N.O.
9. ALL GYP. BOARD CEILINGS TO BE PAINTED P-1, U.N.O.
10. ALL PAINTED SURFACES SHALL RECEIVE A MINIMUM OF (1) ONE BASE COAT AND (2) TWO FINISH COATS
11. PAINTED SHEEN LEVEL TO BE SATIN/EGG-SHELL FOR ALL WALLS, U.N.O. SHEEN FOR ALL WET AREA WALLS, METAL DOORS AND METAL FRAMES TO BE SEMI-GLOSS.
12. PAINT ALL EXPOSED METAL SURFACES, SUCH AS GRILLES, FIRE EXTINGUISHER CABINETS, ETC. WITH PAINT TO
MATCH ADJACENT SURFACE.
FINISH GENERAL NOTES
CT CERAMIC TILE
ETR EXISTING TO REMAIN
PTD PAINTED
GWB GYPSUM WALL BOARD
LEGEND
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/9
/2
:4
:5
A
M C
U s e rs \e g ra n o v s k y \D o c u m e n ts
\A M u rf re e s b o ro W a re h o u s e
-2
-3 e g ra n o v s k y .r v t
AE701
DOOR AND ROOM FINISH SCHEDULES
AND DETAILS
5 5EG
UPGRADE WAREHOUSE FIRE
PROTECTION & HVAC
ALVIN C.YORK VAMC
3400 LEBANON PIKE
MURFREESBORO, TN 37129 MAY 12, 2022
BID DOCUMENTS
626A4-21-20520-317
LCW
DOOR SCHEDULE
DOOR DOOR FRAME HEAD
DETAIL NO.
JAMB
DETAIL NO.
THRESH
DETAIL NO. LBL
HDWR
SET REMARKSNO. WIDTH* HEIGHT* THICK MAT'L FINISH ELEV MAT'L FINISH ELEV
FIRST FLOOR
X101 12' - 0" 12' - 0" 2" STEEL PTD OH-1 STEEL GALV. OH-1 ETR ETR NONE 1 1/2 HR NONE
ROOM FINISH SCHEDULE
ROOM NO. NAME FLOOR BASE
WALLS CEILING
REMARKS
EAST NORTH SOUTH WEST
FIN HEIGHTFIN FIN FIN FIN
FIRST FLOOR
X104 UTILITY ROOM CT CT NONE NONE NONE NONE ETR 8' - 0"
X101 WAREHOUSE ETR NONE NONE NONE NONE NONE PTD 44' - 0"
OVERHEAD DOOR AND FRAME LEGEND
VARIES
* VERIFY IN FIELD
SLOPED CEILING
NOTE: NOT ALL SYMBOLS MAY BE USED ON THIS PROJECT
SEMI-RECESSED SPRINKLER HEAD
UPRIGHT SPRINKLER HEAD
FIRE LINEFL
CONCEALED SPRINKLER HEAD
PENDANT SPRINKLER HEAD
SIDEWALL SPRINKLER HEAD
FIRE DEPARTMENT CONNECTION (FDC)
FIRE DRAINDRAIN
POINT OF NEW CONNECTION
LIMIT OF DEMOLITION
NEW WORK KEYNOTE
DEMOLITION KEYNOTE
FIRE PROTECTION CONTRACTORFPC
TAMPER SWITCH
FLOW SWITCH
CHECK VALVE
GATE VALVE
EXTERIOR ALARM GONG (WATER ACTIVATED)
TEST AND DRAIN ASSEMBLY
BACKFLOW PREVENTER
T&D
TS
FS
ORDINARY HAZARD
GROUP 1 OCCUPANCY
DETAIL OR SECTION MARK
SHOWN ON DRAWING
DETAIL MODULE NUMBER
ORDINARY HAZARD
GROUP 2 OCCUPANCY
LIGHT HAZARD
THE FIRE PROTECTION DRAWING IS DESIGNED TO BE IN CONFORMANCE WITH NFPA
13. IT IS A PERFORMANCE BASED DRAWING INDICATING THE EXTENT OF FIRE
PROTECTION WORK FOR THE AREA THAT THIS DRAWING REPRESENTS. THIS
DRAWING IS “FOR INFORMATION ONLY”, AS A REFERENCE FOR THE FIRE
PROTECTION CONTRACTOR TO BASE THE DESIGN OF THE FIRE PROTECTION
SYSTEM ON. THE CONTRACTOR SHALL VERIFY THE EXACT CONDITIONS THAT THIS
DRAWING REPRESENTS, INCLUDING ANY PERCEIVED CONCEALED SPACES, AND THE
BUILDING TYPE AND CONSTRUCTION AS OUTLINED IN THE INTERNATIONAL BUILDING
CODE, PRIOR TO THE START OF WORK. REFER TO THE INTERNATIONAL BUILDING
CODE, NFPA 13, AND THE PROJECT SPECIFICATIONS FOR OTHER FIRE PROTECTION
REQUIREMENTS.
FLUSHING CONNECTION
FEED OR CROSS MAIN.
TYPICAL TEE WITH
CROSS MAIN PITCH
TOWARDS FEED MAIN.
NOTE: INSTALL FLUSHING
CONNECTION AT END OF
CROSS MAINS.
2" NIPPLE 4" LONG
WITH CAP.
MECHANICAL TEE
NEW PIPING
MECHANICAL TEE
SCREWED END
STEEL BEAM
RETAINING STRAP
C-CLAMP
THREADED HANGER ROD
ADJUSTABLE RING HANGER
NOTE:
HANGING DETAILS SHOWN ARE SUBJECT TO REQUIREMENTS OF…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .