FFG-62 Industry Day Presentation.pdf

PDF 3 MB Posted

Attached to
Design-Bid-Build, FFG-62 Land Based Engineering Site, Philadelphia Navy Yard Annex, Philadelphia, PA
Solicitation number
Not on record
Issued by

About this file

This document is an industry day presentation for the Design-Bid-Build, FFG-62 Land Based Engineering Site (LBES) repair project at the Philadelphia Navy Yard Annex in Philadelphia, PA. The presentation provides an overview of the project, including the scope of work, construction schedule, and anticipated work environment. Key details include modifications to Building B77H, such as a new pile-supported foundation and slab, interior platforms, a control house, and utility infrastructure improvements. Site improvements are also planned, such as demolition of Building B480 and new/replacement utilities. The project will be procured through full and open competition using a best value trade-off evaluation. The Navy plans to issue the RFP in May 2024, with proposals due in July 2024 and contract award in November 2024. The project will be completed in four milestones, with the control house and southeast site portions scheduled for earlier completion. Environmental permits have been or will be obtained by the Navy prior to award.

View the file

Other files

File Type Posted
Industry Day Sign-in Sheet.pdf PDF
Attachment 1 - PLA Questionnaire.docx DOCX document
FFG-62 Industry Day Flyer.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Live! Hotel Philadelphia

900 Packer Ave Philadelphia, PA 19148

10 April 2024

Industry Day

FFG-62 Land Based Engineering Site (LBES) Repair Package

Agenda Time Action Presenter

0900 Opening Remarks NAVFAC PM

0905 Introductions All

0910 Ground Rules NAVFAC Contracting Officer

0920 Project Presentation NAVFAC Design Team (WRA)

1015 Questions NAVFAC Contracting Officer

1100 Adjourn

Presenter: NAVFAC and NSWCPD/PMS-515 Leadership

Opening Remarks

Presenter: All

Introductions

Presenter: NAVFAC Contracting Officer

Ground Rules

Ground Rules

• This meeting is informational and for planning purposes only.

• This is not a Request For Proposal (RFP). Discussions today will not be evaluated in response to any future requests for proposals.

• Do not provide the Government with proprietary information, trade secrets, or any other information deemed source selection sensitive, or information that you do not want disseminated to the public.

• A record of all discussions will be made. If you have not already done so, please sign the acknowledgement / sign in sheet, indicating your understanding and consent to the government making publicly available a summary without attribution of everything discussed today.

• Effort that any contractor/entity expends on this effort is at its own time, risk, and expense.

• Hold all questions until the end of the presentation.

• Everything you see today is a DRAFT and is subject to change.

Industry Day Goals

• To notify the Industry of the upcoming solicitation for the FFG-62

LBES Repair construction project.

• Inform Industry of the scope, timeline, and possible construction challenges for the project.

• Solicit private sector input to help shape the project procurement.

Project Solicitation Details

• Acquisition Strategy

• Full and Open Competition

• Best Value Trade Off

• Labor Agreement required per the FAR

Presenter: NAVFAC Design Team

Project Presentation

Project Location

FFG-62 LBES REPAIR

PROJECT SITE

B77 COMPLEX

N

Primary Project Area

N

Project Presentation Project Location

S-Lot – Designated area for

Contractor construction trailer(s), Material Storage and Staging

B77 Complex Primary Work Area

• Ability to avoid conflict with other active construction projects in the project area.

• Building B77H and the

B77 Complex will be occupied during construction.

• Construction activities from current and future projects.

• 2nd Shift work anticipated.

Project Presentation Anticipated Work Environment

B77 Complex

• B77H Modifications

• Site/Utility Improvements

• Construction Completion Milestones

Project Presentation Project Overview

B77H Google Earth View

• Primary area of work: 40,000SF

• Pile Supported Foundation and

Slab

• FFG-62 Early Demolition project

Project Presentation B77H Modifications

Foundation Plan

B77H Modifications

First Floor Plan

• Two Interior Platforms

• Control House

• Two Exterior Platforms (above

Part A and Part E)

• Cooling Water Trench

• Utility Infrastructure

• Existing Lab

B77H Modifications

N N

Foundation Plan First Floor Plan

Key Plan

B77H Cross Section Looking North

B77H Modifications

B77H Modifications

Control House Cross Section Looking North

• Control House

• 7,500SF

• 2 Levels

• Steel framing extends through roof to support platform above

B77H Modifications

3D View Looking Northeast

B77H Modifications

3D View Looking Southwest

Control House – Interior Image

Control House – Interior Image

Project Presentation B77H Modifications

• Fire Alarm and Protection

Improvements

• Demolish and replace existing.

• Includes B756 (FA Only), B670, B485, B77H

• Mass Notification

• Existing platforms ~16,000SF

• Existing offices ~60,000SF

• Roof ~ 140,000SF

Fire Alarm / Protection - B77 Complex

Project Presentation Site Improvements

• Southeast site

• B480 demolition

• Fire service to B485

• Temporary pump house

• New/existing utilities

• Southwest site (not shown)

Southeast Site Plan

Project Presentation Site Improvements

• B480 demolition

• 2 story

• ~6,000SF

Photo – B480 Exterior B480 – Floor Plan

Project Presentation Const. Completion Milestones

Milestones have been established to allow partial occupancy and outfitting activities to begin.

• Milestone 1: Control House

• Milestone 2: Southeast Site

• Milestone 3: Primary Work Area

• Milestone 4: Remainder

N

MILESTONE 3 MILESTONE 1

MILESTONE 2

• Permits Acquired by Navy prior to Award

▪ Philadelphia Water Department

• Post-Construction Stormwater Management Approval

▪ PA Department of Environmental Protection

• NPDES Permit for Stormwater Discharges Associated with

Construction Activities

• Contractor required to submit Co-Permittee

Acknowledgement Form to PADEP for operational control of NPDES Permit

▪ Title IV Operating Permit – Major Source

• All soil taken off site must be handled, tested, and disposed of in compliance with federal, state and local regulatory requirements.

Environmental / Permitting

• Issue RFP May 2024

• Contractor Site Visit TBD

• Receive Proposals July 2024

• Award Construction Contract November 2024

• Milestone Construction PoP

• M1 – Control House 550 days after NTP

• M2 – Southeast Site 245 days after NTP

• M3 – Primary Work Area 850 days after NTP

• M4 – Remaining 1000 days after NTP

Tentative Project Schedule

Presenter: Contracting Officer

Questions

Additional questions can be submitted in writing to:

brittany.n.cristelli.civ@us.navy.mil

Adjourn

Slide 1: FFG-62 Land Based Engineering Site (LBES) Repair Package
Slide 2: Agenda
Slide 3: Opening Remarks
Slide 4: Introductions
Slide 5: Ground Rules
Slide 6: Ground Rules
Slide 7: Industry Day Goals
Slide 8: Project Solicitation Details
Slide 9: Project Presentation
Slide 10: Project Presentation Project Location
Slide 11: Project Presentation Project Location
Slide 12: Project Presentation Anticipated Work Environment
Slide 13: Project Presentation Project Overview
Slide 14: Project Presentation B77H Modifications
Slide 15: Project Presentation B77H Modifications
Slide 16: Project Presentation B77H Modifications
Slide 17: Project Presentation B77H Modifications
Slide 18: Project Presentation B77H Modifications
Slide 19: Project Presentation B77H Modifications
Slide 20: Project Presentation B77H Modifications
Slide 21: Project Presentation B77H Modifications
Slide 22: Project Presentation B77H Modifications
Slide 23: Project Presentation B77H Modifications
Slide 24: Project Presentation Site Improvements
Slide 25: Project Presentation Site Improvements
Slide 26: Project Presentation Const. Completion Milestones
Slide 27: Project Presentation Environmental / Permitting
Slide 28: Project Presentation Tentative Project Schedule
Slide 29: Questions
Slide 30: Adjourn