Feasibility_Study.pdf
PDF 2 MB Posted
- Solicitation number
- 2026-03
- Issued by
- Hartford County, Connecticut
About this file
This document is a presentation for the Demore, Dinda, Bittner Jr. Memorial Pool Complex project, prepared for the Parks and Recreation Commission Meeting on December 12, 2024. The presentation, developed by KBA (an architectural or engineering firm), outlines several recommended improvements for the pool complex, including converting tennis courts to pickleball courts, creating a new playscape, renovating or replacing the pool house, and converting the wading and main pools to a splash pad. The proposed improvements are based on recommendations from a Town Council Meeting and include addressing accessibility issues, structural updates, and park enhancements.
The total estimated cost for the proposed improvements ranges from approximately $5,375,000 to $5,950,000, with individual project costs broken down as follows: tennis courts to pickleball courts ($625,000 - $700,000), new playscape and park improvements ($400,000 - $550,000), pool house renovation ($1,150,000 - $1,250,000) or replacement ($1,100,000 - $1,200,000), wading and main pool conversion to a splash pad ($2,500,000 - $3,000,000), and additional parking ($200,000 - $300,000). The presentation includes detailed images and floor plans, highlighting the current condition of the facilities and proposed improvements, with a note that unforeseen conditions could potentially increase the renovation costs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Demore, Dinda, Bittner Jr.
Memorial Pool Complex
Parks and Recreation Commission Meeting December 12, 2024
Summary of Options from Town Council Meeting
1. Tennis Courts to Pickleball Courts
• $625,000 - $700,000
2. New Playscape and Park Improvements
• $400,000 - $550,000
3. Pool House Renovation
• $1,300,000 - $1,500,000
4-A. Wading Pool Replacement
• $600,000 - $650,000
4-A. Wading Pool Conversion to Splash Pad
• $500,000 - $550,000
5-A. Main Pool Renovation
• $2,750,000 - $2,900,000
5-B. Main Pool Replacement
• $3,500,000 - $3,650,000
5-C. Main Pool Conversion to Splash Pad
• $2,600,000 - $2,750,000
Recommendations from Town Council Meeting
1. Tennis Courts to Pickleball Courts
• $625,000 - $700,000
2. New Playscape and Park Improvements
• $400,000 - $550,000
3-A. Pool House Renovation (reduced size)
3-B. Pool House Replacement
4. Wading Pool & Main Pool Conversion to Splash Pad
• $2,500,000 - $3,000,000
5. Additional Parking
New Base
New Surfacing
& Markings
New Ball Netting
New Fencing
Tennis Court Conversion • Lack of Accessible Means of Egress
• Cracking and Settling in Asphalt
• Delamination and Surface Wearing
• Fencing Chain-link Mesh Warped and
Posts Leaning
• End of Its Lifespan
New Accessible Access
Park and Playscape
• Lack of Accessible Means of Egress
• Swings at End-of-Life Span
• Currently Open Space
New Ages 2-5
Playscape
New Ages 5-12
Playscape
New Shade
Structure
New Safety
Surfacing
New Accessible
Access
Pool House Renovation (reduced size)
$1,150,000 - $1,250,000
• Accessibility and Code Updates
• Structurally Renovations and Updates
• New Roof
• M/E/P Updates and Replacements
Pool House Replacement
$1,100,000 - $1,200,000
• Accessibility and Code Updates
• Structurally Renovations and Updates
• New Roof
• M/E/P Updates and Replacements
Wading Pool & Main Pool
$2,500,000 - $3,000,000
(1,000 – 1,250 s.f.)
• Replace with a New Splash Pad
Recommendations from Town Council Meeting
1. Tennis Courts to Pickleball Courts
• $625,000 - $700,000
2. New Playscape and Park Improvements
• $400,000 - $550,000
3-A. Pool House Renovation (reduced size)
• $1,150,000 - $1,250,000*
3-B. Pool House Replacement
• $1,100,000 - $1,200,000
4. Wading Pool & Main Pool Conversion to Splash Pad
• $2,500,000 - $3,000,000
5. Additional Parking
• $200,000 - $300,000
*unforeseen conditions could increase price
Questions?