FDHD_FDVD_ Power and Timing Card Procurement Specifications.pdf
PDF 470 KB Posted
- Attached to
- PTC DC Power Supply
- Solicitation number
- 378908
About this file
This is a Procurement Specification document for DC power supplies required by the Fermi National Accelerator Laboratory for the Long-Baseline Neutrino Facility (LBNF) / Deep Underground Neutrino Experiment (DUNE) project. The specification is dated January 12, 2026, and outlines requirements for Power and Timing Card (PTC) DC power supplies for Far Detector components (Horizontal Drift and Vertical Drift configurations) to be installed at the Sanford Underground Research Facility (SURF) in Lead, South Dakota.
The vendor must procure, fabricate, assemble, test, package, and deliver complete multi-channel DC power supply systems housed in 4U power bins with 1U cooling vents. Technical specifications include: voltage up to 60V, current up to 13.5A, 650W per channel, auto AC 94V-265V input voltage range, built-in 15A AC line fuse, C20 16AWG AC cord set, CE conformance with EN 50 081/82 standards and NRTL safety certification, and noise/ripple less than 3mVpp for 10m wire at 0-300MHz. The FD-HD configuration requires 27 chassis units with 6 independent floating return low voltage channels, while the FD-VD configuration requires 22 chassis units with 4 independent floating return low voltage channels. Both configurations feature front panel displays, networkable interfaces with SNMP capability, easy extraction mechanisms for maintenance, single channel interlock capability with fail-safe logic, remote sensing and regulation options, M6 rear panel power studs, cable strain relief bars, dual horizontal threaded hole grounding bars, and chassis mounting ears. Deliverables must include load and functionality test results. Post-award requirements include submission of finalized overall deliverable schedules and milestones. The subcontractor is responsible for quality control across all on-site and off-site work, including work by suppliers and sub-tier subcontractors. Delivery address is Dakota Warehouse, Rachel Pfaff, 1313 E. Saint Patrick St., Rapid City, SD 57701.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FD-HD/FD-VD Power and Timing Card (PTC) DC Power Supply
Procurement Specification Dated 1.12.2026
Fermi National Accelerator Laboratory i
VERSION CONTROL
Approvals for this document will be required from:
FFDG Procurement: Name TBD. To be filled in by Procurement prior to PO award FFDG Responsible Person: Linda Bagby, Engineering Physicist Manager
Revision History Revision Responsible
Person Date Description of Changes
0 L. Bagby 1.12.2026 Original
Fermi National Accelerator Laboratory ii
ACRONYMS AND ABBREVIATIONS
Acronym/Abbrevia on De ni on
FNAL Fermi Na onal Accelerator Laboratory
FFDG Fermi Forward Discovery Group
Customer FFDG
SURF Sanford Underground Research Facility
LBNF Long Baseline Neutrino Facility
DUNE Deep Underground Neutrino Experiment
PTC Power, Timing, and Control
FD-HD Far Detector - Horizontal Dri
FD-VD Far Detector - Ver cal Dri
NRTL Na onally Recognized Tes ng Laboratory
LBNF/DUNE-US FDC
Fermi National Accelerator Laboratory iii
TABLE OF CONTENTS
INTRODUCTION
STRUCTURE/COMPONENT DESCRIPTION
TECHNICAL REQUIREMENTS
POST-AWARD SUBMITTALS
QUALITY CONTROL
LIST OF FIGURES
Figure 1 LBNF/DUNE-US Schema c ................................................................Error! Bookmark not de ned.
Figure 2 Example Power Supply
Fermi National Accelerator Laboratory 1
INTRODUCTION
Under contract to the U.S. Department of Energy (DOE), the Fermi Forward Discovery Group, LLC (FFDG), is leading the Long-Baseline Neutrino Facility (LBNF) Project to enable a world-class program in neutrino physics. Specifically, the LBNF Project (https://lbnf-dune.fnal.gov) provides the infrastructure for the Deep Underground Neutrino Experiment (DUNE), which will consist of two large liquid argon-based neutrino detectors located nearly a mile underground at the Sanford Underground Research Facility (SURF) in Lead, SD. See Figure 1, LBNF/DUNE-US Schematic
The Far Detector & Cryogenics (FDC) subproject of LBNF/DUNE-US installs the cryostats, detectors, cryogenics and suppor ng infrastructure at the SURF laboratory.
The DUNE Far Detectors, Horizontal Drift (FD-HD) and Vertical Drift (FD-VD) utilize Power and Timing Cards (PTC) as part of the detector Warm Interface Electronics Crate (WIEC). Each PTC require a 48V/13A DC power supply.
STRUCTURE/COMPONENT DESCRIPTION
Each multi-channel DC power supply is housed in a 4U power bin which includes a 1U cooling vent. Each power bin contains a power box that is easily remova replacement. The power supply features channel-wise fail-safe logic interlock capability, remote sensing, and remote network control and monitoring features. Local control and monitoring viewing are required via a front panel display.
Fermi National Accelerator Laboratory 2
TECHNICAL REQUIREMENTS
The vendor shall procure all materials, fabricate, assemble, test, package, and deliver the complete products as shown in Figure 2.
All components must be packaged to ensure materials will conform to specifications upon shipment, delivery, and storage.
V: up to 60V I: up to 13.5A W: 650W each channel Auto AC 94V-265V input voltage range Built in 15A AC line fuse C20, 16AWG AC cord set Safety ratings:
CE conform EN 50 081/82 part 1 (EN 50 022 B), safety in accordance with EN 60 950 or
NRTL
Noise and Ripple: for 10 m wire <3mVpp, 0-300MHz FD-HD: 27 chassis units configured for 6 independent, floating return, low voltage channels
FD-VD: 22 chassis units configured for 4 independent, floating return, low voltage channels
SNMP)
Easy extraction mechanism for power supply maintenance Front panel display Single channel interlock capability with fail safe logic (open connection trips off) Remote sensing and regulation options M6 rear panel power studs Cable strain relief bar Dual horizontal threaded hole grounding bars Chassis mounting ears Load and functionality test results Shipping address:
Fermi National Accelerator Laboratory 3
South Dakota shipping address:
Dakota Warehouse Rachel Pfaff 1313 E. Saint Patrick St.
Rapid City, SD 57701.
POST-AWARD SUBMITTALS
The Subcontractor shall comply with the following requirements once subcontract award has been made.
Finalized overall deliverable schedule/milestones
QUALITY CONTROL
The Subcontractor is responsible for all activities necessary to manage, control, and document work to ensure compliance with the subcontrac adequate Quality Control services are provided for work accomplished on- and off-site by their organization, suppliers, sub-tier subcontractors, technical laboratories, and consultants.
End of Document