FBNV 240017 DB Period of Performance.pdf

PDF 144 KB Posted

Attached to
FA487724R0020 - Upgrade PGS Fire System Federal contract opportunity
Solicitation number
FA487724R0020
Issued by
Department of the Air Force Air Combat Command

About this file

This document is a government period of performance schedule for the FBNV 240017 Upgrade PGS Fire Suppression project. The project has a total performance period of 225 days, divided into a 160-day design phase and a 65-day construction phase. Key dates include a kick-off meeting on 6/8/2022, notice to proceed on 6/22/2022, and various design submittals and reviews occurring from July 2022 through October 2022. The construction phase begins on 11/27/2022 and is scheduled to be completed by 1/31/2023.

The related federal contract opportunity is solicitation number FA487724R0020 for the Upgrade PGS Fire System. This Request for Proposal (RFP) calls for the design, plans, specifications, and installation of a new fire suppression system for the 610 CACS Power Generation Shelter. The site visit is tentatively scheduled for 8/26/2024, RFIs are due 9/2/2024, and proposals are due 9/16/2024. The contracting agency is the Department of the Air Force Air Combat Command.

View the file

Other files for this federal contract opportunity

Other files attached to FA487724R0020 - Upgrade PGS Fire System, newest first.
File Type Posted
Solicitation Amendment FA487724R00200002 SF 30.pdf PDF
Solicitation Amendment FA487724R00200001 SF 30.pdf PDF
BLDG 74 - Upgrade PGS System Photos.pdf PDF
Solicitation - FA487724R0020.pdf PDF
Contractor EAL Template.xlsx XLSX spreadsheet
FBNV240017 - All Specifications.pdf PDF
Contractor Environmental Guide 15 May 2019.pdf PDF
FBNV240017 - AF Form 3052 Blank.xlsx XLSX spreadsheet
Wage Determination - Rev AZ202490040.pdf PDF
FBNV240017 - AF Form 66.pdf PDF
DMAFB Design Compatibility Guidelines 2017.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Government Period of Performance 225

240017 Upgrade PGS Fire Suppression Project Number FBNV240017

Projected Date Projected Duration

Actual Date Submitted

Actual Duration

Task Order Award 6/7/2022 0 -44719 Kick-off Meeting 6/8/2022 1 0 Notice to Proceed 6/22/2022 14 0

Dig Permit (AF Form 103) 6/22/2022 0 0 Investigation 6/24/2022 2 0 Charrette Submittal 7/15/2022 21 0 Charrette Meeting 7/16/2022 1 0 35% Design Submittal 7/16/2022 0 0 Government Review 7/16/2022 0 0 35% Design Review Meeting 7/16/2022 0 0 65% Design Submittal 8/6/2022 21 0 Government Review 8/27/2022 21 0 65% Design Review Meeting 8/28/2022 1 0 95% Design Submittal 9/18/2022 21 0 Government Review 10/9/2022 21 0 95% Design Review Meeting 10/10/2022 1 0 Final Contract Documents Submittal 10/24/2022 14 0 Government Review 11/14/2022 21 0

Total Design Performance Period 160 0

Div 02 Demolition 11/27/2022 13 0 Div 03 Concrete 11/27/2022 0 0 Div 04 Masonry 11/27/2022 0 0 Div 05 Metals 11/27/2022 0 0 Div 06 Wood, Plastics, and Composites 11/27/2022 0 0

Div 07 Thermal and Moisture Protection 11/27/2022 0 0 Div 08 Openings 11/27/2022 0 0 Div 09 Finishes 11/27/2022 0 0 Div 10 Specialties 11/27/2022 0 0 Div 21 Fire Suppression 1/26/2023 60 0 Div 22 Plumbing 1/26/2023 0 0

Design Phase

Construction Phase

Div 23 HVAC 1/26/2023 0 0 Div 26 Electrical 1/31/2023 5 0 Div 27 Communications 1/31/2023 0 0 Div 31 Earthwork 1/31/2023 0 0 Div 32 Exterior Improvements 1/31/2023 0 0 Div 33 Utilities 1/31/2023 0 0 Div 34 Transportation 1/31/2023 0 0

Total Construction Performance Period 65 0

Total Performance Period 225 0

Comments

Performance of period (PoP) is an estimate. The project will begin once the Award & notice to proceed is given by the Contracting Squadron (Contract Adminitrator).