Attach__3_--_PWS_Airfield_Lighting_13_June_18.pdf
PDF 1 MB Posted
- Attached to
- Airfield Lighting Control Monitoring System Federal contract opportunity
- Solicitation number
- FA9301-18-R-0003
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Eaton_Crouse-Hinds_Justification__Approval_Document_Signed_Redacted.pdf | ||
| Attach__6_--_General_Decision_CA_180031_CA31_7-6-2018.pdf | ||
| Attach__4_--_Bid_Sheet.pdf | ||
| Attach__1_--_Combined_Synopsis_Solicitation.pdf | ||
| Attach__5_--_SCA_WD_15-5603_(Rev_-7)_1-10-2018.pdf | ||
| Attach__2_--_Mission_Essential_Services_Plan_TEMPLATE.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
For
Maintenance and Repair
Of
Airfield Lighting and Control Monitoring System
(ALCMS)
U.S. Air Force Test Center
Edwards Air Force Base (EAFB), California
13 June 2018
1 of 14 ALCMS
FA9301-18-R-0003
Attachment 3
24 February 2018
TABLE OF CONTENTS
Section Page
I. Description of Services/General Information
1.0. Scope of Work 3
1.1. Airfield Lighting Control and Monitoring System 3
1.1.1. Preventive Maintenance (PM) 3
1.1.2. Hardware 3
1.1.3. Emergency Service Calls 3
1.1.4. Site Clean-Up 4
1.1.5. Technical Support 4
1.1.6. Software and Hardware Upgrades 4
1.1.7. Records 4
1.1.8. Training 4
1.2. General Information 4
1.2.1. Time Notification Prior to PM Inspection (PMI) 4
1.3. Preventive Maintenance Program 4
1.3.1. Preventive Maintenance Plan (PMP) 5
1.3.2. Maintenance and Repair Parts 5
1.4. Quality Control Plan 5
1.5. Quality Assurance 5
1.6. Contract Manager 5
1.7. Over and Above 6
1.7.1. Over and Above Repair Procedures 6
II. Services Summary 7
III. Government-Furnished Property and Services 8
IV Appendices
Appendix A – Over and Above Estimate Form 10
Appendix B – Workload Estimate 11
Appendix C – Sample PMI Report 12
Appendix D – Glossary and Terms 14
2 of 14 ALCMS
SECTION I
DESCRIPTION OF SERVICES/GENERAL INFORMATION
1.0. Scope of Work. The Contractor shall provide all management, personnel, tools, vehicles, supplies, materials, parts, equipment, system training and labor necessary to maintain and repair Airfield Lighting
Control and Monitoring System (ALCMS) at Edwards Air Force Base (EAFB). All work shall comply with Federal Aviation Administration (FAA), Military, and International Civil Aviation Organization
(ICAO) standards. This contract will include a one-time testing of 10 Constant Current Regulators
(CCR) to be performed upon initial service to EAFB, CA; and will be noted as CLIN 0004 and is included in the Services Summary. Initial inspection and recommended replacement of inoperable system parts, software and equipment shall take place within 30 days of award of this contract. All parts and labor required will be provided and installed by contractor and invoiced on the applicable CLIN.
1.1. Airfield Lighting Control and Monitoring System (ALCMS) Maintenance. Maintain the existing ALCMS located in the airfield vaults in buildings 1720, 4452 and the control tower residing in building 1727.
1.1.1. Preventive Maintenance (PM). The contractor shall perform all required inspections and maintenance of the airfield lighting control and monitoring system; shall provide a technician that has been factory-trained by Eaton Crouse-Hinds to perform all required inspections and maintenance of the airfield lighting control and monitoring system; and all PM shall be in accordance with (IAW) manufacturers’ specifications/instruction and commercial/industrial standards. If manufacturers recommended parts are not available, replacement parts shall be equal to or better than the manufacturer’s recommended part. The contractor shall correct all deficiencies within 3 working days unless approved by the Contracting Officer (CO).
1.1.2. Hardware. The major components of the existing ALCMS include the following:
1.1.2.1 Air Traffic Control (ATC) tower Human Machine Interface (HMI) hardware
1.1.2.2 ATC tower computers and processors
1.1.2.3 Transmission lines (fiber optic and line-of-sight radio system) between the tower and the electrical vaults
1.1.2.4 Electrical vault #1 HMI hardware
1.1.2.5 Electrical vault computers and processors
1.1.2.6 Electrical vault control and monitoring equipment interface devices
1.1.2.7 Electrical vault #2 HMI hardware
1.1.2.8 Electrical vault computers and processors
1.1.2.9 Electrical vault control and monitoring equipment interface devices
1.1.3. Emergency Service Calls. The contractor shall respond to emergency repair calls within 24 hours after notification with a competently trained computer/electrical technician. Examples of emergency service calls are: loss of computer video, audio or analog, inoperative HMI touch screen monitor, poor computer resolution, system is not interfacing with vault communication network, system is not transmitting equipment performance and circuit data to the vault network, loss interfaces inputs and outputs data with control tower system or vice versa, low input and output signal, loss of link
3 of 14 ALCMS between vault processor and control monitoring equipment, loss of communication network between the electrical vault computer and any controlled or monitored equipment. Emergency service calls will either be remedied or a workaround devised within the 24 hours of arrival at least 90% of the time.
1.1.4. Site Clean Up. The contractor shall ensure the area is clean, orderly and free of debris upon completion of each service.
1.1.5. Technical Support. Contractor shall provide unlimited phone and e-mail technical support 24 hours a day, 7 days a week. The contractor shall provide the Program Manager a 24-hour contact number prior to contract start. The contractor’s technician will work directly with the airfield management office, or the flight line maintenance personnel.
1.1.6. Software and Hardware Upgrades. System down-time should be kept to a minimum and shall be coordinated with the Program Manager 72 hours in advance. Provide hard-covered copy of the
Operation & Maintenance (O&M) manual suitable for daily O&M of the system. The manuals must include operational overview, system theory of operation and HMI equipment manuals. The contractor shall be responsible to ensure compliance with Eaton Crouse-Hinds manufacturer's system specification and requirements.
1.1.6.1. Software Upgrades. Contractor shall provide any newly released upgrades for the operating software that will enhance the overall performance of the system.
1.1.6.2. Hardware Upgrades. Provide one copy of as–installed drawings. The as-installed drawings must reflect the final installation including system 1-line drawings, wiring diagrams, assembly or assembly wiring diagram. Provide test documents from the manufacturer detailing the level of testing performed.
1.1.7. Records. Maintain accurate records and logs in building 1720. Records shall include a PM
Inspection (PMI) checklist and a log of repairs, maintenance, upgrades, the technician(s) who performed the work and any other recommended work.
1.1.8. Training. Provide system training including training on software and hardware upgrades to CE electrical technicians.
1.2. General Information.
1.2.1. Time Notification. Contractor shall provide 30 calendar days’ notice to the Program Manager prior to the scheduled PMI or system training. Contractor shall notify the PM once they have arrived at
EAFB.
1.2.2. Hours of Operation. Normal duty hours for EAFB are 7:00 a.m. to 5:00 p.m. Monday through
Friday, except federal holidays. The contractor may establish work hours as necessary for the performance of work under this PWS.
4 of 14 ALCMS
1.3. Preventive Maintenance and Repair Programs. The purpose of the program is to prevent and correct deficiencies with ALCMS, minimize system breakdowns and service interruptions, extend component service life and maximize operating efficiency.
1.3.1. Preventive Maintenance Plan (PMP). The contractor shall submit a PM Plan to the Program
Manager for approval within 10 calendar days of award. The plan shall include ALCMS components to be inspected and maintained, inspection and maintenance techniques, schedule of on-site inspection and maintenance and reporting methodology.
The plan shall also include a PMI checklist that incorporates the areas mentioned above. A sample checklist and report can be found at Appendix C. The contractor shall update schedules as necessary to reflect any changes in equipment inventory.
1.3.2. Maintenance and Repair Parts. Maintenance and repair parts are classified as either Major or
Minor. Keyboards, hard drives, RAM, DVD/CD-RW, operating software, database software, and other items are considered Minor parts if they cost $500 or less per piece or item. Minor repair parts cost shall be absorbed by the contractor under CLIN 0001 and CLIN 0002. Major parts would include touchscreen monitors, entire CPU tower, UPS, or other items that cost over $500 per piece or item. The cost of Major parts, with prior approval, will be paid to the Contractor under Over and Above procedures utilizing the Over and Above CLIN 0003.
1.4. Quality Control Plan. The contractor shall submit a quality control plan (QCP) to the Program
Manger and CO for approval within 10 calendar days of award. The QCP shall ensure all ALCMS maintenance and repair services are performed IAW with applicable commercial standards, regulations, laws and codes, and contractor’s PMI Plan. The QCP must describe the overall quality approach and quality control inspection system tasks to identify and prevent defective services from occurring or recurring. As a minimum, the contractor shall develop quality control procedures that address the areas identified in the Services Summary and an internal inspection/surveillance system. The contractor shall maintain all quality control records for the duration of the contract and will make them available to the government Program Manager or CO within 24 hours upon request. Provide quality control inspector(s) contact information to the CO and Program Manager for notification of customer complaints, government concerns, or emergency situations. This listing should contain current names and phone numbers and be updated when changes occur. The plan shall be maintained and updated as necessary throughout the life of this contract.
1.5. Quality Assurance. The government will evaluate the contractor’s performance IAW the
Performance Plan (PP). In addition, the government will periodically evaluate the contractor’s performance by appointing a representative(s) to monitor performance to ensure services are received.
The government may increase or decrease the number of quality control inspections as performance dictates. The Contracting Officer’s Representative (COR)/Program Manager will receive and investigate customer complaints and make the final determination of the validity of the complaint.
1.6. Contract Manager. The contractor shall identify a contract manager who is authorized to represent the contractor and make binding contractual agreements with the government. Provide the contact information for the contract manager and alternate(s) to the CO prior to the contract start date
5 of 14 ALCMS and shall be updated as needed. The contract manager or alternate(s) shall be available by phone within
24 hours. The contract manager or alternate(s) shall read, write, speak and understand English.
1.7. Over and Above. This allows the government and the contractor to negotiate parts and labor for repairs not identified in the PMI plan. Over and Above requirements are provided in DFARs clause
252.217-7028, Over and Above and Additional Over and Above Work Procedures.
1.7.1. Over and Above Repair Procedures. The contractor shall submit a written work request form
(Appendix A), with a detailed cost estimate and warranty terms, to the government Program Manager and COR within 5 business days of identification of required repairs. If the government and Contractor cannot agree upon a firm-fixed price for the Over and Above work request, the government has the right to openly compete the Over and Above work. The Contractor shall commence and complete work by the negotiated dates. Schedule repairs with the Program Manager at least 48 hours in advance. All Over and Above requests exceeding $2,500.00 will be routed by the Program Manager to the CO for a price fair and reasonable determination. The contractor shall not proceed with the Over and Above repair work until the work order has been approved. The contractor shall commence Over and Above repair work after notification from the CO or their designated representative. Parts shall be based on established market prices less customer discounts, and excluding handling charges, and shall be supported by supplier invoices (and attached to work request forms). Contractor invoices shall contain copies of supply invoices for parts approved by the Program Manager or the CO for payment. Over and
Above repairs will be warranted by the contractor for labor for at least 12 months from completion and acceptance by the Program Manager/COR.
6 of 14 ALCMS
SECTION II
SERVICES SUMMARY
2.0. The contractor service requirements are summarized into performance objectives that relate to mission essential items. The performance thresholds briefly describe the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Performance Objective PWS Para. Performance Threshold
Constant Current Regulator Testing.
Contractor shall perform a one-time test of the
10 associated CCR’s during the initial service.
1.0., Appendix B
Perform testing IAW FAA AC 150/
5340-26C (ce). Testing shall include: output load values, short circuit test, open circuit test, and an over current test, and provide a report 100% after the service is complete.
Preventive Maintenance. Contractor shall check all items identified in the PWS.
1.1.1., 1.1.2. Contractor shall check all items listed 100% of the time upon each
PM visit.
Emergency Service Calls. Contractor shall respond within 24 hours.
1.1.3. Contractor responds within 24 hours
of notification and all work remediated at least 90% of the time.
Over And Above. Contractor shall prepare an
O&A request and deliver to the CO/Program
Manager prior to the start of any work.
1.7., 1.71. O&A filled out with cost estimate to repair within 3 days after identifying
O&A need 100% of the time.
Site Clean Up. The contractor shall ensure the area is clean, orderly and free of debris upon completion of each service.
1.1.4. Will be free of debris 100% of the
time after completion of services.
Records. The contractor shall maintain accurate records and logs.
1.1.7. Records are maintained 100% of the
time after each service.
7 of 14 ALCMS
SECTION III
GOVERNMENT-FURNISHED PROPERTY AND SERVICES
3. Government-Furnished Property (GFP). There is no GFP or Facilities provided on this contract.
3.1. Fire Prevention and Protection. Fire department telephone extension is 911 when calling from land line or 661-277-4540 from a cellphone.
3.2. Security Police. The government will provide general on-base Security Police service. Security
Police telephone extension is 911 when calling from land line or 661-277-3340 from a cellphone.
3.3. Emergency Medical Service. The government will provide emergency medical treatment and emergency patient transportation service for contractor personnel who are injured or become critically ill during the performance of this contract. The contractor shall reimburse the government for the cost of medical treatment and patient transportation service at the current in-patient or outpatient treatment rate, as appropriate.
8 of 14 ALCMS
SECTION IV
APPENDICES
A. Over and Above Work Request Form
B. Estimated Workload Data
C. Sample PMI Inspection Checklist and Report
D. Glossary and Terms
9 of 14 ALCMS
Appendix A
OVER AND ABOVE WORK REQUEST FORM
Control Number__________
Description of work to be performed: _________________________________________________
Costs:
Labor: The total labor price shall include all labor costs to include General and Administrative costs and profit.
Labor Number Price Total
Classification of Hours Per Hour Labor price
Total of Labor Costs $_____________
Materials, Supplies, Equipment. Contractor shall identify all materials, supplies, and equipment required regardless of cost. For any single item in excess of $3,000, contractor shall provide the quote from vendor. For any single item in excess of $5,000, the contractor shall provide at least 3 competing vendor quotes.
Vendor Name & Contact Info Item Cost
Total of Materials, Supplies, Equipment Costs $____________
Total of all work request costs $____________
Warranty period: Parts_____________ Labor_____________
Schedule of Work: Start_____________ Complete_____________ Days and Hours _____________
Other Conditions:
Contractor CE Program Manager Government COR Contracting Officer
Signature & Date Signature & Date Signature & Date Signature & Date
10 of 14 ALCMS
Appendix B
WORKLOAD ESTIMATE
AIRFIELD LIGHTING CONTROL AND MONITORING SYSTEM MAINTENANCE
(Based on data collected from previous 10 years of service)
At a minimum, a preventative maintenance inspection (PMI) shall include all items listed below for each Vault ALCS and Tower ALCS:
Brightness calibration check and adjustment for each Computer Controlled Regulator
Run diagnostic tests on Echelon cards
Visually inspect digitrac interface
Visually inspect computer network
Visually inspect potential transformer current
Optimize all hard drive functions
Defrag hard drives
Vacuum all CPU components
Vacuum keyboards
Clean all CPU components
Clean all monitors
Test communication systems
Run diagnostic tests on network cards
Run diagnostic tests for each alarm setting
Reseal all compartments
Clean equipment racks
Clean digitrac interface
Check internal batteries
Check UPS battery
All cables and contact connections checked to ensure all are tightened and cleaned
Check, replace and maintain all UPS units
Check and adjust touch screen calibrations
A one-time requirement due at first service interval for: Constant Current Regulators: test, evaluate, and report the operational condition of Constant Current Regulators to include: Output Load Values
(in KW), Short Circuit Test, Open Circuit Test, Over Current Test.
11 of 14 ALCMS
Appendix C
Date of Report
Name of Individual Completing Service
Procedure Initial for C/W or Check for N/A
01. Cleaning & Vacuuming
Computer Screens
Keyboards
All CPU Components
Equipment Rack
Digitrac Interface
02. Diagnostics
Alarm List Review
History Review
Test Echelon Cards
Test Network Cards
Internal CPU Batteries
Test Commication System
03. Visually Inspect
Potential Transformer
Current Transformer
Digitrac Interface
Industral Computer
Network Equipment
Patch Panels
Peripherals
UPS
04. Replace Defective or Failing Parts
Disk Drives
Computer Cards
UPS Batteries
Other Components
05. Optimize Performance
Defrag & Optimize
Network Equipment
Calibrate Touch Screen Monitors
Update Software
06. Complete Summy Report
07. Deliver Report to Program Manager
N/A
Airfield Lighting Control and Monitoring System
Preventative Maintenance Inspection Report
Site Locations
Tower N/A North Base N/A South Base N/A
***SAMPLE***
***SAMPLE***
***SAMPLE***
12 of 14 ALCMS
Appendix C (con’t)
Report should include nature of visit, duration at site, actions completed, parts replaced, notification of system readiness and whether follow up for cause is necessary
Signature
Airfield Lighting Control and Monitoring System Summary Report
***SAMPLE***
***SAMPLE***
***SAMPLE***
13 of 14 ALCMS
Appendix D
GLOSSARY AND TERMS
ALCMS - Airfield Lighting Control and Monitoring System
ATC - Air Traffic Control
CCR - Constant Current Regulators
CO - Contracting Officer
COR - Contracting Officer’s Representative
EAFB - Edwards Air Force Base
FAA - Federal Aviation Administration
GFP - Government-Furnished Property
HMI - Human Machine Interface
ICAO - International Civil Aviation Organization
O&M - Operation & Maintenance
PM - Preventive Maintenance
PMI - PM Inspection
PMP - Preventive Maintenance Plan
PP - Performance Plan
PWS - Performance Work Statement
QCP - Quality Control Plan
14 of 14 ALCMS