AEDC Industry Day FARM III_Final.pdf
PDF 2 MB Posted
- Solicitation number
- FA9101-25-R-FARMIII
About this file
This is an Industry Day presentation document for the Arnold Engineering Development Complex's (AEDC) Facilities Acquisitions for Restoration and Modernization (FARM) III contract, held on August 7, 2025. The FARM III acquisition is a multiple award Indefinite Delivery/Indefinite Quantity (IDIQ) contract with firm-fixed-price task orders, featuring a five-year base period with a three-year option, performance starting September 2026, awards to up to eight contractors, and an anticipated $900 million contract ceiling. The procurement will cover restoration and modernization projects across AEDC facilities at Arnold Air Force Base, Tennessee, and geographically separated units including National Full Scale Aerodynamics Complex in California, Tunnel 9 in Maryland, and multiple locations at Holloman AFB, Kirtland AFB, Wright Patterson AFB, and White Sands Missile Range.
The presentation outlines specific example task orders including a $13-15 million maintenance building construction, a $20-30 million high pressure air bottle farm installation, cooling water infrastructure projects, office building renovations, and various pump/motor replacements. The government is considering a Highest Technically Rated Offeror (HTRO) evaluation methodology using a weighted scoring matrix where offerors self-score and submit substantiation. The schedule shows Industry Day on August 7, 2025, Request for Information responses due August 22, 2025, contract award targeted for August 2026, and contract start in September 2026. The presentation emphasizes that all information is predecisional and for planning purposes only, with no commitment that a procurement action will be issued.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936.
Facilities Acquisitions for Restoration and
Modernization (FARM) Ill
Industry Day
7 August 2025
FARM III Industry Day
Information provided and discussed is for planning purposes only and DOES NOT constitute a commitment, implied or otherwise, that a procurement action will be issued.
All information provided and discussed is pre-decisional.
FARM III Industry Day Agenda
0800 – 0830 Registration
0830 – 0835 Administrative Remarks
0835 – 0840 Welcome and Opening Comments
0840 – 0910 Arnold Engineering Development Complex (AEDC) 101
0910 – 1035 Topics of Interest
1035 – 1100 Questions and Answers (Q&A)
1100 – 1230 Lunch
1230 – 1400 One-on-ones with Government Team (Group A)
1230 – 1400 Base tour (Group B)
1400 – 1530 One-on-ones with Government Team (Group B)
1400 – 1530 Base tour (Group A)
Administrative Remarks
• Restrooms are located near the lobby entrance
• Snacks and drinks available (donations welcome)
• Lunch is on your own
• Gossick Leadership Center (GLC) emergency response
– In case of fire, gathering point is in the parking lot
– In case of severe weather, the restrooms are designated shelters
• Questions
– We will attempt to answer questions during the briefings, but…
– …if we begin to exceed our time slots, please use provided notecards to record your question(s) and deposit notecards in the provided basket
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 5
Welcome and Opening Remarks Lt Col Tony Brunson
AEDC Program Management Division
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 6
AEDC 101
Charlie Jenkins, AEDC/PMD
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 7
Topics of Interest
• FARM History
• FARM III Acquisition
• Examples of Task Orders
• Security Requirements
• Safety Requirements
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 8
FARM History
Nikki Tracey, AEDC/PMD
FARM History
• AEDC’s test facilities and supporting plant and infrastructure systems were built primarily in the 1950s and 1960s, with a few additions up through the 1990s
– Many of the individual test facilities are unique in the country or the world
• Test infrastructure restoration and modernization efforts were routinely underfunded for decades
– Resulted in diminished test capability and increased energy and maintenance costs
– Increased risk for AEDC’s test customers – program offices who are tasked with fielding future aerospace systems
FARM History, cont.
• In the mid-2010s, Air Force Test Center (AFTC) and Air Force Materiel
Command (AFMC) leadership successfully advocated for funding to restore and modernize AEDC’s test infrastructure
– Air Force (AF) budgeted for major investments beginning in FY17 to start the process of mitigating long-term risk in support of next generation weapon system development
– Funding plus-up targeted specific Service Life Extension Programs (SLEPs)
• To effectively execute the increased workload of restoration and modernization efforts, AEDC established the FARM contract vehicle
– Multiple award Indefinite Delivery/Indefinite Quantity (IDIQ) with a variety of design-build and/or construction work
– Promotes the efficient execution of restoration and modernization projects while minimizing time and impact on existing test activities
Typical Aging Infrastructure
Hydraulic System Unit Sub-Station
Stacks and Control Valves
Exhaust Motors Surface Coolers
Typical Aging Infrastructure (cont’d)
Bearing Lube Oil System
Heaters
Control Cabinet
161kv Substation
Barrowell
FARM Operating Locations
• Arnold Air Force Base (AFB) TN
• AEDC’s Geographically Separated Units (GSUs)
– National Full Scale Aerodynamics Complex (NFAC), Moffett Field CA*
– Tunnel 9, White Oak MD
– 704th Test Group, Holloman AFB NM*
• 704th’s GSUs: OL-AA, Kirtland AFB NM, and OL-AC Wright Patterson AFB OH
• 586th Flight Test Squadron, White Sands Missile Range NM
*Locations added for FARM II
FARM I
• Awarded 8 August 2016
– Full and open competition
– Performance-price tradeoff with technical acceptability (PPT/TA)
• Four awardees
• Five-year period of performance
– 12-month base period
– Four 12-month option periods
• $400M contract ceiling (~$300M awarded)
• Firm-fixed-price (FFP) task orders
– ~50 task orders awarded
– Typically ranging from $250K-$15M
FARM II
• Awarded 4 March 2022
– Full and open competition
– Best value utilizing full tradeoff procedures (Technical, Past Performance, and Price, with technically acceptable Small Business Subcontracting Plan)
• Four awardees
• Five-year period of performance
• $300M contract ceiling
• FFP task orders (~$150M awarded to date)
– 14 task orders awarded to date
– Typically ranging from $1.5M-$30M
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 16
FARM III Acquisition
Robert Mosley, AFTC/PZI (Arnold)
Anticipated FARM III Contract
• Multiple Award IDIQ
– FFP task orders
– Ordering period – Five-year base, three-year option
– Performance start September 2026
– Award to up to eight contractors
– $900M contract ceiling anticipated
• Five-year outlook
– 50+ potential task orders have been identified
• Statement of Work (SOW) currently in draft form
– Addresses specific requirements
– Provided as attachment to the FARM III Industry Day announcement
– Please review and provide any comments/concerns
What We Need From You
• We need input at Industry Day
– Provide thoughts or recommendations for acquisition strategies and contract types
– Bring/submit questions about FARM III requirements
– Provide thoughts on task order packaging
– Provide suggested North America Industry Classification System (NAICS) codes
– Provide suggestions to support GSUs
• Review draft SOW and provide concerns / comments
• Participate in draft Request for Proposal (RFP) and ultimately the final RFP
Need your help to develop the right acquisition strategy
Highest Technically Rated Offeror (HTRO)
• Previous Acquisitions
– FARM I – Past Performance/Price Tradeoff with Tech
– FARM II – Full Tradeoff
• Considering HTRO for FARM III
– Award to highest technically rated offerors
– Weighted scoring matrix
– Offerors self-score and submit substantiation with proposal
– Govt team validates proposals starting with highest self-scores
FARM III Notional Acquisition Schedule
• Industry Day 7 Aug 25
• Request for Information (RFI) responses 22 Aug 25
• Draft RFP release ???
• Final RFP release ???
• Contract award Aug 26
• Contract start Sep 26
What We Will Provide
• We will provide as much information as possible on SAM.gov
• Please follow FA9101-25-R-FARMIII for updates
The FARM Ill Team is here to assist you with any questions you may have
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 22
Examples of Task Orders
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 23
Maintenance Building
Tanya Bradford, AEDC/PMDC
Objective (General Scope/Requirement)
• Construct a Maintenance Facility for Propulsion Wind Tunnel (PWT)
• Complete a design, build and install for a new 100’X150’ maintenance facility on a predetermined location at AEDC
– A 35% design will be provided
• The selected location, which will not require an Environmental
Assessment, is on previously disturbed ground maintained as a grassy field
– There are no utility interferences, yet utilities are available on the periphery of the footprint to serve it
• Demolition and disposal of approximately 800 yd2 asphalt, 150 LF concrete curb, 100 LF sanitary piping, and 70 LF water piping
• Design-Build contract
Current State / Future State
• Current State
– Difficult to stage PWT maintenance activities
• Future State
– Future projects are expected to increase the required footprint for covered and conditioned maintenance activity
– The Maintenance Facility will be a new construction building of approximately
13,000 ft2
– The building will be used to perform maintenance on components and will include some storage of various parts
Requirements
• Requirements for Maintenance Facility:
– Approximately 13,000-15,000 ft2
– Pre-fabricated structure with foundation on grade
– High-bay space (~30’x100’) for parts to be off-loaded from a tractor trailer using a diesel-powered 30,000 lb forklift
– 38’ Upper eave height
– 14’x12’ overhead door, coiling
– Side-bay spaces (~40’x100’ and 60’x100’), 24’ lower eave height
– Options for varying the square footage, single restroom, small office, ceiling heights
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 27
High Pressure Additional Air
Capacity 3 (HPAAC 3)
George Allen, AEDC/PMDC
HPAAC 3 Objective
• Improve the shared high-pressure air (HPA) storage and configuration capabilities of AEDC
• Provide ~7,000 ft3 HPA bottle farm, consisting of pressure vessels, supports, access platform, foundation, and associated distribution piping, that will provide 4,400 psia HPA
• Work includes design, demolition, procurement, site preparation, fabrication, installation, and checkout of the proposed solution to meet the performance requirements
• Current State
– Demands for AEDC’s HPA resources frequently exceed available capacity
– Drives challenges in AEDC’s integrated scheduling process
– Increases costs incurred by test programs
• Future State
– Increased HPA availability, with capability to share HPA across multiple test cells
HPAAC 3 Requirements
• Install a new bottle farm to increase overall storage and system flexibility
– Collaborative effort w/ on-base contractors for checkout/commissioning purposes
• Total of 72 pressure vessels at 94.1 ft3 capacity each for a total of 6,775 ft3
• All pressure vessels shall be in accordance with AEDC Specification 16426-24-
001, “Item Specification for High Pressure Air Vessels.” The Contractor shall submit all documentation and submittals required within the Specification to the Government.
• Bottle support structure, piping, valves, electrical, pipe bridge, lightning protection, wind and seismic load analysis, and site to be designed
– Install valves to existing main HPA distribution system to enable flexible configuration of HPA delivery
– Install issue line to High Temperature Laboratory (HTL) facility
• Work includes demolition of existing infrastructure as required to accommodate for new equipment
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 31
C-Plant Return Basin
Isolation Valve
Michelle Young, AEDC/PMDC
• Install a discharge isolation valve within a permanent valve pit on the 72" cooling tower return line
• Design the new isolation valve and structural design for the valve pit will be required
• Excavation of the valve pit will be required
• Close collaboration between stakeholders in this project and the exhaust cooler project is crucial to ensure seamless integration of designs solution to meet the performance requirements
• Current State
– Original design of the cooling water return basin did not provide sufficient drain flow capacity for the facility cooling water when also operating the exhaust cooler
– The exhaust cooler is presently being upgraded/replaced
– This valve must be installed to take advantage of the new exhaust cooler
• Future State
– New 72” American Water Works Association (AWWA) C504 butterfly valve with a motorized modulating operator/actuator and construction of a permanent valve pit for isolation of the cooling tower return line
Isolation Valve Requirements
• Size: 72”
• Open/Close Time: 1-1.25 minutes
• Pressure Rating: 150 psi
• Max Flow: 200,000 gpm, less than 25 ft/s
• Material: American Society for Testing and Materials (ASTM) A536 grade 65-45-12 ductile iron and flat-faced flange drilling per American Society of Mechanical Engineers (ASME) B16.10, ASME
B16.47, and AWWA C504 class 150B
• Disc: stainless steel type 316 or nickel alloy (seating edge)
• Seats: Synthetic compound, without retaining bolt penetrations, mechanically retained in the valve body with one-piece metal seat ring retainer and fully field adjustable, while in-line, without special tools
– Exclude AWWA C504 Section 4.3.5.3.3; sprayed mating seat surfaces are unacceptable
– The valve seats shall be replaceable without removing the valves from the line
• Leakage: Zero leakage under operating conditions
• Reliability: Designed for 25-year life, Mean Time Between Failure (MTBF) of at least 1,000 cycles
• Maintainability: Designed for Mean Time to Repair (MTTR) of no more than eight hours
• Control System Integration: Electric actuating valve
Valve Pit Requirements
• Structural Design: Design valve pit to withstand and permanently hold back all soil and surcharge loads
– All designs as well as stamped shoring and detailed drawings must be stamped and approved by Professional Engineer licensed in the state of Tennessee, and drawings must clearly show new equipment locations, interfaces, and interferences
• Sizing: Concrete floor 48-60” below water pipe bottom, valve pit must be sized to give sufficient working room and allow personnel safe entry and exit via a permanent ladder
• Drainage: Sump and sloped floor (max 1/8” per ft)
• Piping Support: Provide support for piping and valve, maintaining 4 ft clearance from valve face
• Access:
– A. Permanent ladder, removable platform, and railings compliant with 29 Code of Federal Regulations (CFR) 1926.1053, Air Force
Instruction (AFI) 91-203, and American National Standards Institute (ANSI) 14.3 Standards
– B. Ladder access shall extend to concrete floor
– C. Ladder safety climb devices shall be required where the length of the climb is greater than 24’ to meet Occupational Safety and
Health Administration (OSHA) requirements
– D. Cages not permitted on ladders
– E. Platform height for ergonomic hand-wheel operation
– F. 36” clear space around equipment
– G. Removable cover with manway and sump pump hatches (20 per ft2 live load rating)
– H. Bolted manway (min. 30” inside diameter) located at least 36” from any pit wall.
• Sump Pump: Shall have necessary capacity to drain excess water in pit, discharge to existing storm drain without causing erosion
• Other: A. Top of pit wall 18" above grade; B. Valve position visible without pit entry
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 36
Renovate Engine Test Facility
(ETF) Office, Bldg 877
Nick Hibdon, AEDC/TSDCN
• Renovate ETF Office Building, Bldg 877 (in execution now)
• Design/Build services including engineering, plans, labor, equipment, supplies, and materials to renovate the ETF Office Building
• Contract was awarded at roughly $18.5M
• Project Details: Demolish and replace the heating, ventilation, and air conditioning
(HVAC) system and associated piping, ceiling, windows, interior finishes, doors, door hardware, electrical power, lighting, flooring, walls, communications, alarm systems, restrooms and associated plumbing, systems furniture, and provide a facility wide fire suppression system
• Requirements include having the executing contractor:
– Provide the necessary trailer/temporary space for personnel to be relocated during renovation work
– Perform the site-prep needed to support the trailers
– Running utilities both temporary and permanent
– Being the primary responsible party for moving needed materials from the building to the temporary trailers and back once work is complete
Previous State / Current State
• Previous State
– The facility was first constructed in 1957 with the last major renovation around 1989
– Thirty years later the facility needed an interior facelift to meet the current fire, force protection, energy, accessibility, and mass notifications codes along with interior remediation of mold
– Interior materials and finishes needed to be replaced along with upgrades to HVAC, power, fire alarm, communications, restrooms, audio/visual, and lighting
– The interior layout no longer meet organizational needs, housing roughly 145 personnel
• Current State
– Complete renovation to the interior of the facility is nearly complete
– The final product will be an entirely renovated interior for the facility including an updated layout that better meets current organizational needs with a capacity for roughly 195 personnel
ETF Office Building Requirements
• Complete design incorporating installation requirements and addressing Unified
Facilities Criteria (UFC) code compliance issues
• Renovate ETF Office Building, constructed in 1957, roughly 35,500SF
• Systems to be replaced: HVAC and associated plumbing, ceiling, windows, interior finishes, relocate interior walls, doors, door hardware, electrical power systems, lighting, communications, fire alarm systems, restrooms and associated plumbing, and fire protection system
• Provide temporary trailers (roughly 14,000 ft2) to relocate personnel during renovation of the facility
• Original layout allowed for 145 personnel, new layout allows for 195 personnel
• Support inspections by system engineers as need, coordinate power/utility outages, maintain schedule flexibility to support other mission requirements
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 40
Von Karman Facility (VKF)
Raw Water Lines
• Repair by Replace, VKF Raw Water Lines-expected to award in FY26-29 timeframe
• Design/Build service including engineering, plans, labor, equipment, supplies, and materials to replace the cooling water infrastructure that supports the VKF Plant
• Contract award expected range: $20M-$30M
• Project Details: Demolish roughly 800-900 ft of raw water piping and as necessary replace with new piping ranging from 12’ to 48’ diameter raw water header and branch piping
• Scope will include design analysis on soil conditions, development of drawings, potentially dealing with hazardous materials in the soil, installing new valves, strainers, concrete slabs and trenches, and connecting this new infrastructure to existing infrastructure
• Requirement will include verifying other utilities in the area using hydro-excavation techniques
• Current State
– The cooling water system within the scope of this project has a high leak rate
– Pressure loss within the system will continue to worsen if not repaired
– Another concern is erosion issues due to current leaks and potential future leaks
• Future State
– Brand new piping with an improved layout and sizing plan will lead to more efficient operation of the plant equipment and lead to less maintenance within the cooling water system
– Layout modifications could also better support concurrent operations of the plant and other test facilities on the installation
VKF Cooling Water Lines Requirements
• Soil contamination analysis and condition testing
• Designing (receiving approval) of proposed execution plan and new layout prior to executing work
• Confirming nearby utilities and other underground hazards during design
• Replacing 800-900’ of 12”-48” raw water header and branch lines, ensuring the plant is back up and operational over a 6-month outage
• Outage window will be limited to April-October time frame to avoid any concerns of freeze protection for nearby system components
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 44
Primary Pumping Station
Pump/Motor Replacement
• Primary Pumping Station Pump and Motor Assembly #1 Replacement, Bldg 3038
• Design/Build services including engineering, calculations, develop drawings, all labor, materials, equipment needed to execute the above project
• Contract ROM: $3M-$5M
• Project Details: Modify roof with hatch so that entire pump and motor assembly can be removed/installed at one time
– Remove existing pump and motor assembly
– Install new pump and motor assembly
– Perform required checkouts before Government accepts work completed
Previous State / Current State / Future State
• Previous State
– Primary Pumping Station, Pump and Motor Assembly #1 along with the 5 other pump and motor assemblies at the Primary Pumping Station, the 12 pump and motor assemblies at the Secondary Pumping Station, and the 6 pump and motor assemblies at Rowland Creek Pumping Station have reached the end of life and need to be replaced
• Current State
– Primary Pumping Station, Pump and Motor Assembly #1 has been replaced through a FARM contract and is running efficiently, with a reduced maintenance tail
• Future State
– Replace all 23 remaining pump and motor assemblies across these three pumping stations to ensure efficient and reliable operations moving forward
Pump/Motor Replacement Requirements
• Requirements for ALL Primary, Secondary, and Rowland Creek Pumping
Stations
– Primary Pumping Station: Constructed in 1953 houses 6-25K GPM pump/motor assemblies (5 still needing to be replaced), will include roof modifications for hatch access to assemblies
– Secondary Pumping Station: Constructed in 1953 houses 8-25K GPM, 1-10K GPM, and 3-3.3K
GPM pump/motor assemblies
– Rowland Creek Pumping Station: Constructed in 2000 houses 4-25K GPM and 2-12.5K GPM pump/motor assemblies
– Major Constraints: Test and Installation Operations constantly require cooling water meaning that execution of this work would occur one pump/motor assembly at a time (per facility)
– Contractor will have to coordinate local outages in advance and request may be denied depending on test schedule
– Expectation is each pump/motor assembly will require between two and four three-day outages
– Operational checkouts required prior to Government acceptance of the product
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 48
Holloman AFB Task Orders
Jason Casebolt, AEDC/704TSS/TGSO
Introduction
• 704th Test Group Campuses
• Successful FARM Projects at Holloman AFB
• Example Future Project
704th Test Group Campuses
1000 Campus
1200 Campus
1100 Campus
Intent to fund $4M - $6M work per year with FARM contractors to support repair and modernization of 135 facilities on three Test and Evaluation campuses.
FARM III Conceptual Funding Target
Hanger Renovation Project
• Objective
– Restore drain, waste, vent utility service to the facility, repair slab, update restrooms to modern standards with Americans with Disabilities Act (ADA) compliance, provide showers for maintenance personnel, and reconfigure interior to modernize mission capabilities
– Associated constraint was that contractors were required to be escorted at all times
• Previous State
– 40-year-old facility experiencing significant sewer service line backups
– Restrooms were outdated and voids located under the slab
– Floorplan configuration was inadequate to meet modern mission requirements and rooms were dated with antiquated fixtures and finishes
• Current State
– Renovated restroom down to the studs, demolished restroom slab and 200 LF of slab covering existing sewer service line
– Installed new men’s and women’s restrooms with showers, sewer service line to main, and upgraded 5,000 ft2 of facility interior
Convert Storage Facility to Weld Shop Objectives
• Improve Holloman High Speed Test Track (HHSTT) sled test capability and mission throughput
• Convert existing 5,000 ft2 storage facility to weld shop to include new interior electric, HVAC, fire suppression, structural components, ventilation, as well as construct new break room and mechanical room
• Work includes 35%, 65%, 95%, and 100% design efforts, demolition, fabrication, installation, and customer collaboration to achieve performance requirements
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 53
Current State / Future State
• Current State
– Welders are performing work in cramped workspaces with OSHA writeups, inadequate HVAC cooling system, poor fume ventilation, logistical inefficiencies, inefficient electrical systems
– Existing facility is not capable of supporting future sled types
• Future State
– Modify existing storage facility to enhance safety, quality of life, and retainability of welders
– Improve sled manufacturing processes and provide new modern facility with welding platforms capable of supporting test assets coming down the pike
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 54
Requirements
• Existing Conditions: Demolish existing electrical system, rollup doors, man doors; no existing fire suppression or HVAC system
• New Construction: break room and mechanical room additions, fence, and storage sheds
• HVAC: New ductwork, HVAC units, and ventilation to include fume extractors for welding ops
• Electrical: Provide new electrical distribution system to support welding ops including but not limited to new main distribution panel (MDP), safety switches, conductors, light-emitting diode (LED) lighting, 240V welding outlets
• Fire Protection: Install wet pipe fire protection system, fire alarm panels, and mass notification system
• Structural: Install interior insulated wall panels, roof insulation, new rollup doors, man doors.
• Constraints: Project is relatively unconstrained as the facility is unoccupied; no special access program, entry authorization lists, or escorting required
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 55
Security Requirements
Keith Davis, AEDC/TSD-SF
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 56
Safety Requirements
Billy Childress, AEDC/SE
Distribution A. Approved for public release. Distribution Unlimited. IRA-25-0936. 57
Q&A
Closing Remarks
• This briefing provided a “high level” requirements overview
• Questions can be asked during one-on-one sessions or by sending an email to robert.mosley.3@us.af.mil
• You will have the opportunity to ask questions and engage with functional experts during one-on-one sessions. We encourage you to take advantage!
F-35 Lightning IINASA Orion Crew Exploration Vehicle
Thank You for Supporting AEDC’s
FARM III Industry Day
| Slide 1: Facilities Acquisitions for Restoration and Modernization (FARM) Ill Industry Day |
| Slide 2: FARM III Industry Day |
| Slide 3: FARM III Industry Day Agenda |
| Slide 4: Administrative Remarks |
| Slide 5 |
| Slide 6 |
| Slide 7 |
| Slide 8 |
| Slide 9: FARM History |
| Slide 10: FARM History, cont. |
| Slide 11: Typical Aging Infrastructure |
| Slide 12: Typical Aging Infrastructure (cont’d) |
| Slide 13: FARM Operating Locations |
| Slide 14: FARM I |
| Slide 15: FARM II |
| Slide 16 |
| Slide 17: Anticipated FARM III Contract |
| Slide 18: What We Need From You |
| Slide 19: Highest Technically Rated Offeror (HTRO) |
| Slide 20: FARM III Notional Acquisition Schedule |
| Slide 21: What We Will Provide |
| Slide 22 |
| Slide 23 |
| Slide 24: Objective (General Scope/Requirement) |
| Slide 25: Current State / Future State |
| Slide 26: Requirements |
| Slide 27 |
| Slide 28: HPAAC 3 Objective |
| Slide 29: Current State / Future State |
| Slide 30: HPAAC 3 Requirements |
| Slide 31 |
| Slide 32: Objective (General Scope/Requirement) |
| Slide 33: Current State / Future State |
| Slide 34: Isolation Valve Requirements |
| Slide 35: Valve Pit Requirements |
| Slide 36 |
| Slide 37: Objective (General Scope/Requirement) |
| Slide 38: Previous State / Current State |
| Slide 39: ETF Office Building Requirements |
| Slide 40 |
| Slide 41: Objective (General Scope/Requirement) |
| Slide 42: Current State / Future State |
| Slide 43: VKF Cooling Water Lines Requirements |
| Slide 44 |
| Slide 45: Objective (General Scope/Requirement) |
| Slide 46: Previous State / Current State / Future State |
| Slide 47: Pump/Motor Replacement Requirements |
| Slide 48 |
| Slide 49: Introduction |
| Slide 50: 704th Test Group Campuses |
| Slide 51: Hanger Renovation Project |
| Slide 52: Convert Storage Facility to Weld Shop Objectives |
| Slide 53: Convert Storage Facility to Weld Shop Current State / Future State |
| Slide 54: Convert Storage Facility to Weld Shop Requirements |
| Slide 55 |
| Slide 56 |
| Slide 57 |
| Slide 58: Closing Remarks |
| Slide 59 |