DRAFT Scope of Work (SOW) dated 25 Nov 2013. The purpose of this notice is to obtain Questions/Comments. All questions/comments pertaining to the DRAFT SOW and DRAFT Home/Field Labor Categories shall be provided to the Government for consideration in the provided matrix excel spreadsheet.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final_REC_SOW_Comments_Labor_Categories__19_Feb_14.pdf | ||
| FINAL_REC_SOW_19_Feb_2014.pdf | ||
| RE C_Contractor_Question_Comments_Matrix.xlsx | XLSX spreadsheet | |
| Table_Attachment_L8_to_the_Offeror_REC.doc | DOC document | |
| RE C_DRAFT_ITO_and_EVC_MATRIX_18_Dec_13_Final.xlsx | XLSX spreadsheet | |
| Contractor_Question_Template_REC.xlsx | XLSX spreadsheet | |
| RE C_Home-Field_Category.xlsx | XLSX spreadsheet | |
| RE C_Regional_Map.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8903-14-R-0008
Attachment 1 08 Nov 13
BASIC CONTRACT
STATEMENT OF WORK
for
REGIONAL ENGINEERING AND CONSTRUCTION CONTRACT (RE&C)
SOLICITATION NUMBER: FA8903-14-R-0008
25 NOV 2013
FA8903-14-R-0008
Attachment 1 25 Nov 2013
TABLE OF CONTENTS
| SECTION |
| TITLE |
| PAGE |
| 1.0 | SCOPE | 4 |
| 2.0 | APPLICABLE DOCUMENTS | 6 |
| 3.0 | GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP) | 6 |
| 4.0 | MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS | 7 |
| 4.1 | Work Breakdown Structure (WBS) | 7 |
| 4.2 | Schedule and Planning Requirements | 7 |
| 4.2.1 | Project Planning Chart and/or Construction Planning Chart | 7 |
| 4.2.2 | Integrated Master Schedule (IMS) | 7 |
| 4.3 | Cost and Status Reporting | 8 |
| 4.3.1 | Contractor’s Progress, Status, and Management Report (CPSMR) | 8 |
| 4.3.2 | Funds and Man-Hour Expenditure Report (FMER) | 8 |
| 4.3.3 | Performance and Cost Report (PCR) | 8 |
| 4.3.4 | Contract Funds Status Report (CFSR) | 8 |
| 4.3.5 | Cost/Schedule Status Report (C/SSR) | 9 |
| 4.3.6 | Cost Performance Report (CPR) | 9 |
| 4.4 | Meeting and Conference Requirements | 9 |
| 4.4.1 | Meeting/Teleconference Support (IMS) | 9 |
| 4.5 | Contractor Documentation | 10 |
| 4.6 | Notification Requirements | 10 |
| 4.7 | Permits | 10 |
| 4.8 | Photo Documentation | 10 |
| 4.9 | Remote and/or Austere Sites | 11 |
| 4.10 | Site Access Badges | 11 |
| 4.11 | Worksite Activities and Coordination | 11 |
| 4.11.1 | Coordination of Activities | 11 |
| 4.11.2 | Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting | 12 |
| 5.0 | PLANS AND REPORTS | 12 |
| 5.1 | Project Data/Project Deliverables | 12 |
| 5.1.1 Administrative, Physical, and Technical Safeguards | 12 | |
| 5.1.3 | Inspections of the Contractor’s IT Environment | 14 |
| 5.1.4 | Secure Protection and Handling of Data | 15 |
| 5.1.4.1 | Data Storage | 15 |
| 5.1.4.2 | Data Transmission | 15 |
| 5.1.4.3 | Data Encryption | 15 |
| 5.1.4.4 | Data Re-Use | 15 |
| 5.1.4.5 | End of Agreement Data Handling | 16 |
| 5.1.4.6 | Security Breach Notification | 16 |
| 6.0 | SITE WORK | 18 |
| 6.1 | Conservation | 19 |
| 6.2 | Site Preparation | 19 |
| 6.3 | Demobilization | 19 |
| 7.0 | FACILITY CONSTRUCTION TASK ORDER TYPES | 20 |
| 7.1 | Turnkey | 20 |
| 7.2 | Design Build (D-B) | 20 |
| 7.2.1 | Design Completion | 20 |
| 7.2.2 | Project Construction | 21 |
| 7.3 | Design-Bid-Build (D-B-B) | 21 |
| 7.5 | Construction Operation Services | 21 |
| 7.5.1 | Construction | 22 |
| 7.5.2 | Inspections | 22 |
| 7.5.2.1 | Pre-Final Inspection | 22 |
| 7.5.2.2 | Final Inspection | 22 |
| 7.5.3 | Delivery and Warranty | 23 |
| 7.6 | Demolition | 23 |
| 7.7 | Emergency Response | 23 |
| 7.8 | Maintenance and Repair | 23 |
| 7.9 | Ordnance Removal and Support | 23 |
| 8.0. | ADDITIONAL REQUIREMENTS | 24 |
| 8.1 | Other Construction | 24 |
| 8.2 | Military Family Housing | 24 |
| 8.3 | Fueling System Projects | 24 |
| 8.4 | Range Construction | 24 |
| 9.0 | POINTS OF CONTACT (POCs) | 24 |
| 10.0 | ABBREVIATIONS, ACRONYMS and TERMS | 25 |
1.0 SCOPE
This Basic Contract Statement of Work (SOW) defines the scope of a full range of Design, Construction and Engineering activities necessary to meet Air Force and other customer requirements for the Regional Engineering and Construction Contract (RE&C). This basic contract SOW will be tailored to identify specific requirements at the Task Order (TO) level. SOWs or Statements of Requirements (SOR) may be used under this contract. Projects will be located at various locations within the United States. For the purpose of regional awards, the United States has been divided into three regions.
East Region is defined as the following states:
| Maine | New Hampshire | Vermont | Massachusetts | Rhode Island |
| Connecticut | New York | New Jersey | Pennsylvania | Delaware |
| Ohio | Michigan | Indiana | Wisconsin | Illinois |
| Kentucky | West Virginia | Maryland | Virginia | North Carolina |
| Tennessee | South Carolina | Georgia | Alabama | Mississippi |
| Florida | Puerto Rico |
Central Region is defined as the following states:
| Minnesota | North Dakota | South Dakota | Montana | Wyoming |
| Nebraska | Iowa | Missouri | Kansas | Colorado |
| Arkansas | Oklahoma | New Mexico | Texas | Louisiana |
West Region is defined as the following States:
| Idaho | Washington | Oregon | Utah | Nevada |
| California | Arizona | Alaska | Hawaii |
Prior to issuing any work under this SOW, the Government will develop a Concept Definition (CD) of the requirement either through Government in-house resources or through private consultant. The CD will clearly define the project requirements in terms of performance, appearance, criteria and/or specification with sufficient detail that permits a Contractor to provide a proposal with reasonable performance, cost and schedule risk.
This SOW is organized and developed to provide maximum flexibility in the use of this contract vehicle. Basic requirements described here are further refined through the use of individual project Task Orders (TO). Task Orders will be issued for projects at various stages of development. General performance requirements for construction activities are described in Section 2.0 of this SOW. Depending on the project development stage and level of design required, TOs will be issued for Design-Build (DB), or Traditional Design-Bid-Build Construction (D-B-B) as determined by the Contracting Officer in consultation with the Program Manager and Base Civil Engineer. Each method is separately described in Section 7.0 of this SOW.
This SOW encompasses the full range of methods, technologies, and supporting activities necessary to conduct project construction at Air Force installations and other locations within the United States in accordance with technical and regulatory requirements. Stand-alone design is not included in the scope of this contract. All new facilities shall attain LEED Silver designation in accordance with the Air Force Sustainable Design and Development (SDD) Implementing Guidance. The REC Contractor shall prepare a LEED Silver scorecard with the 65% Design Analysis or as directed in the TO Planning Charette reports.
The Contractor shall function as an integral team member in support of the Air Force Civil Engineering Center (AFCEC) mission, to include sharing information with other AFCEC contractors and cooperation with communities and other Government entities.
Requirements include efficient management of TOs including, but not limited to, the submission of accurate, on-time, quality contract deliverables and timely identification and solution of impediments to successful project execution. Technical requirements include, but are not limited to, early involvement in the process to allow for the development of the most cost-effective and technically sound approach or solution. AFCEC will rely on the Contractor’s expertise in recognizing and addressing problematic issues and successful execution of each TO. The Contractor shall perform all work in accordance with federal, state, and local statutes and regulations.
It is the intent of the Government to identify two categories of Contractors for this multi-award RE&C contract. General Contractors are those who in addition to having sufficient bonding capacity to accept large project Task Orders, have a proven track record of success in prosecuting these large projects. These contractors generally do not perform significant portions of the construction work with their own workforce, rather they provide a management team which identifies, enlists contracts with, manages, and controls a group of competent subcontractors who will be executing the actual construction work. All subcontractors will be subject to all regulatory aspects as well as licensing requirements of the local jurisdiction where the project is located. The General Contractor will integrate the subcontractors’ individual schedules into the master project schedule as well as coordinate the subcontractors’ efforts to avoid conflicts and to maximize both synergy and efficiency of the subcontractors in completing the work. The General Contractor will be responsible for all reporting required on each project, and will assume full responsibility for the project quality and timeliness.
The second category of Contractors shall be General Construction Contractors. These contractors will in addition to having sufficient bonding capacity to accept a wide range of project sizes, generally perform substantial portions of the construction work with their own workforce and equipment, while subcontracting for other specialized portions of the construction work with competent subcontractors. Substantial in this context will be dependent on the size and breadth of a particular project. It may be less in a project with many disciplines of work like a new building, or it could be more in a large project with only a few disciplines like a paving project. The General Construction Contractor will retain full responsibility for the quality and timeliness of the project, and will integrate subcontractors’ individual schedules into the master project schedule. The General Construction Contractor will coordinate the subcontractors’ efforts to avoid conflicts and to maximize both synergy and efficiency of subcontractors pursuing the aspects of the project for which they were subcontracted. The General Construction Contractor will be responsible for all reporting required on each project.
It is possible for any individual Contractor to qualify as both a General Contractor and a General Construction Contractor through his record of past accomplishments.
It is anticipated that Regional Task Orders will be accomplished by General Construction Contractors, however, at the discretion of the Government, General Contractors may be used for certain projects based on the size, location, and complexity of the project.
2.0 APPLICABLE DOCUMENTS
The Contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) and all of the related libraries. The primary Criteria is the Air Force Criteria from the Documents Library, but other agency Criteria may be directed for use, depending on the customer agency for a particular TO. It is the Contractor’s responsibility to identify and comply with all applicable requirements. The Contractor shall not delete any design specifications of the specific applicable UFGS or elements therein without Government concurrence. It shall be the Contractor’s responsibility as the DOR to identify any design/construction criteria waivers that are warranted for the TO and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers by the Contracting Officer (CO),and/or Contracting Officer’s Representative (COR).
In addition, the Contractor shall refer to the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States Air Force Construction Management Implementation Guide. Base-specific documents shall be identified in each TO.
3.0 GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)
GFI, GFE, GFP requirements will be specified in each TO, to include delivery, management, accountability and disposition. FAR52.245-1 defines Government Property and the procedures for accounting for and disposition of property. Defense Contract Management Agency (DCMA) instructions for reporting of and including in the Plant Clearance Automated Reutilization Screening System (PCARSS) will be followed for any Government Property remaining at the end of the project.
To the extent it is available, the Government will provide information in the form of available conceptual design plans, reports, maps, drawings, and as-built drawings as necessary to facilitate accomplishment of the work required in the contract Statement of Work. However, these GFIs are to be utilized by the RE&C Contractor as guidance to facilitate a complete, technically adequate design and are not warranted to show conditions as they actually exist. The designer shall verify (by field investigation and through design development) information shown on all GFIs (relevant to the project) for accuracy to ensure technical adequacy of the design.
4.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS
The Contractor shall implement a full range of design, construction and engineering activities as specified in each TO and in accordance with all applicable compliance documents. The Contractor shall supply all labor, equipment, and materials necessary to accomplish the work assigned unless otherwise specified in each TO. The Contractor shall perform management and planning functions, including performance measurement and fund status reporting to effectively secure and monitor prime and sub-contract work, as required in each TO.
4.1 Work Breakdown Structure (WBS)
The Contractor shall prepare and submit, for approval, by the Contracting Officer Representative (COR) and Contracting Officer (CO), a WBS in a logical sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The WBS shall be reflective of the entire project schedule, to include design and construction activities. The WBS shall be consistent with the current Construction Specifications Institute (CSI) Master format for construction activities. The WBS shall be used to report the cost and schedule status for this project. All tasks required under this TO shall be included in the WBS and be identified by unique Construction Activity Identification Number. (Contract Data Requirements List [CDRL] B001)
4.2 Schedule and Planning Requirements
The Contractor shall provide schedules for tracking work progress. The SOW for each TO will identify which of the following schedules is required. Generally the Government will require Project Planning Charts (PPCs) and/or Construction Planning Charts (CPCs) for less complex projects and Integrated Master Schedules (IMS) for more complex projects.
4.2.1 Project Planning Chart and/or Construction Planning Chart
The Contractor shall prepare and submit a PPC and/or CPC for approval. The PPC/CPC shall detail the project schedule and status through the use of Gantt charts, which shall depict percent, complete for each task. The project schedule shall be reported using the approved WBS. (CDRL B002)
4.2.2 Integrated Master Schedule (IMS)
The Contractor shall prepare and submit an IMS and AF Form 3064 for approval. The format for the submitted IMS will be specified in each TO. All review times for the project submittals that are to be incorporated into the IMS will also be specified with each TO. Compliance with UFGS 01 32 01.00 10 Project Schedule is required. The IMS shall detail the project schedule and status through the use of Gantt charts, and Critical Path Method (CPM) analyses. The project schedule shall be resource loaded and reported using the approved WBS. All Definable Features of Work (DFOW) shall be depicted in the IMS. (CDRL B003)
4.3 Cost and Status Reporting
The Contractor shall provide cost and status reports for all cost based TOs. Cost and status reports are listed below in order of increasing complexity. The government will specify one of the following reports or combination of the following depending on the complexity and size of the TO. Task orders under $500,000 typically require Contractor’s Progress, Status, and Management Reports (CPSMR) with cost information. Task orders under $2M typically require either a Performance and Cost Report (PCR) or a Funds and Man-Hours Expenditure Report (FMER). Task orders between $2M-$5M typically require a Cost/Schedule Status Report (C/SSR). Typically TOs over $5M require a Cost Performance Report (CPR). A Contract Funds Status Report (CFSR) may be required in conjunction with a CPR or C/SSR.
4.3.1 Contractor’s Progress, Status, and Management Report (CPSMR)
The Contractor shall prepare and submit a CPSMR. The CPSMR shall be used to review and evaluate the overall progress of the project, along with any existing or potential problem areas. The report shall be prepared in a format coordinated with the Contracting Officer’s Representative (COR). The CPSMR shall include a summary of the events that occurred during the reporting period, discussion of performance, identification of problems, proposed solutions, corrective actions taken, and outstanding issues. Cost information may be included or omitted in this report as required in each TO. (CDRL B004)
4.3.2 Funds and Man-Hour Expenditure Report (FMER)
The Contractor shall implement and maintain a cost accounting system and prepare a FMER to correlate the status of expensed funds and manhours against the progress of the work completed and the negotiated budget. The FMER and associated graphics shall detail the current project status and identify funds and manhours required to complete the assigned tasks. (CDRL C001)
4.3.3 Performance and Cost Report (PCR)
The Contractor shall prepare and submit a PCR. The PCR provides the current status and projected requirements for funds, man-hours, and work completion relative to the negotiated budget. (CDRL C002)
4.3.4 Contract Funds Status Report (CFSR)
The Contractor shall prepare CFSRs as specified in individual TOs where a cost-reimbursement pricing arrangement is involved, The purpose of the CFSR is to update and forecast funding requirements, funding changes and budget estimates, identify funds in excess under the task order which may be available for de-obligation, and provide estimates of termination costs, if applicable. (CDRL C003)
4.3.5 Cost/Schedule Status Report (C/SSR)
The Contractor shall prepare C/SSRs, which summarize performance information for program management purposes as specified in individual TOs where a cost reimbursement pricing arrangement is involved. The C/SSR contains contract data, including original and current contract values and management estimate at completion, performance data, and narrative explanations which present information on significant cost, schedule variances, contractual problems, or other areas of interest. (CDRL C004)
4.3.6 Cost Performance Report (CPR)
The Contractor shall implement and maintain a performance measurement system to support the gathering of cost and schedule data for the purpose of determining program status under task orders where a cost reimbursement pricing arrangement is involved. The WBS or equivalent task breakdown shall be used for reporting cost. The CPR presents the performance measurement baseline and actual cost and schedule performance against that baseline. Submittals shall include appropriate figures containing cost and related data for measuring project cost and schedule status. (CDRL C005)
4.3.7 Requirements for Firm Fixed Price (FFP)
Cost reports are not required under FFP TOs. Firm Fixed Price TOs are usually limited to status reports, project schedules, and invoices and will be specified in each TO.
4.4 Meeting and Conference Requirements
4.4.1 Meeting/Teleconference Support (IMS)
The Contractor shall attend meetings necessary to support design coordination, design review, construction activities, etc. The Contractor also shall attend and support periodic meetings and/or teleconferences through the construction phase of the contract. Frequency of periodic meetings will be specified in the Task Order Requirements Document. The Contractor shall prepare and maintain the periodic meeting report which shall include the record of new and old discussion of technical issues, periodic earned value progress showing percent complete actual versus plan, tabular report of late tasks derived from the progress updated IMS, a three week look ahead, and tabular report for RFIs and submittals (open and upcoming). The Contractor shall prepare, and submit for review, presentation materials for meetings and an agenda. The Contractor shall prepare minutes for meetings attended, including teleconferences, design reviews, and “Red Zone Meetings”, and distribute minutes to attendees within 3 working days. (CDRLs B005, B006, B007)
4.5 Contractor Documentation
The Contractor shall create and maintain a Master Document List (MDL) that includes all documents, whether the document is a deliverable or not, which are prepared during the course of the TO. This includes, but is not limited to correspondence, requests for information, material submittals, schedule submittals, status reports, schedule updates, etc. The MDL will include the dispatch/receipt date, any suspense for each document, and the final disposition of those suspense’s. The MDL and its documents shall be maintained in libraries readily available for submittal to the Government. All Material Submittals shall be accomplished in accordance with the instructions pertaining to AF Form 3000, Material Approval Submittal. (CDRL B008)
4.6 Notification Requirements
The Contractor is required to notify the CO and COR of critical issues that may affect the contract performance and/or human health and the environment. The types of issues that require notification include, but are not limited to, health risks, spills, changes in critical personnel, and finding unexploded ordnance (UXO). As an example, if unanticipated UXO were discovered during field activities, the Contractor will immediately stop work, report the discovery to the facility Point of Contact (POC) (for Air Force installations POC is the Facility Manager), CO, and COR, and implement the appropriate safety precautions. Field activities could not continue until clearance was received from the CO. On critical issues, verbal notification should be made immediately, followed by written notification as soon as practical. (CDRL A002)
4.7 Permits
The Contractor shall develop, coordinate, and assist the installation in applying for and obtaining all applicable permits, access (including off-base easements and leases), agreements, licenses, and certificates required to perform and complete effort as specified under each TO. The Contractor shall maintain a library of these documents at the Contractor’s site office as well as the corporate facility handling each TO. The Contractor shall comply with all applicable permit conditions, and shall keep all permits “current” until the TO is 100% construction complete. (CDRL A003)
4.8 Photo Documentation
The Contractor shall prepare digital photo documentation, including site(s) and building(s) under construction, field activities, and sample locations if applicable. Digital photos will be submitted using a minimum five (5) mega pixel camera in JPEG format. The Contractor shall provide an index for each set of photographs submitted, identifying the base or facility, project number, contractor, and a brief description. Photography of any kind must be coordinated through the installation, customer, or facility POC. Photo documentation shall be loaded to the project website, as requested by the base POC. (CDRLs B010, B011)
4.9 Remote and/or Austere Sites
Work at Remote and/or Austere Sites is not anticipated under this contract.
4.10 Site Access Badges
The Contractor shall obtain and monitor assigned security badges or passes (used by both Contractor and subcontractor personnel) for the duration of this contract. All security badges or passes shall be returned to the base POC upon expiration of the badge, upon completion of the project, or when possession of the badge is no longer necessary (e.g., upon removal of Contractor personnel from specific projects). Requirements for Common Access Cards (CACs) will be specified at the TO level.
4.11 Worksite Activities and Coordination
4.11.1 Coordination of Activities
The Contractor shall be responsible for protecting the lives and health of employees and other persons on the work site; preventing damage to property, materials, supplies, and equipment, avoiding work interruptions and complying with Occupational Safety and Health Administration (OSHA) safety and local safety office requirements. The Contractor shall perform all operations in a prudent, conscientious, safe and professional manner and conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work. The Contractor shall maintain documentation supporting training records on site and have written Health and Safety Plans on site and available for workers and/or regulatory review. The Contractor shall provide the CO copies of any OSHA report(s), regarding a project site, submitted during the duration of the TO. For areas not covered by OSHA, the Contractor shall comply with regulations regarding safety and health and the current edition of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. (CDRL A002)
The Contractor shall record and report promptly (within 1 hour) by telephone, facsimile or other direct means to the CO, COR, the base POC, and to the military installation’s Safety Office, all available facts relating to each instance of damage to Government property or injury to either Contractor or Government personnel. In the event of an accident/mishap, take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, preserve evidence until released by the accident/mishap investigative authority through the CO, and immediately report the incident to the Fire Department at 911. If the Government elects to conduct an investigation of the accident/mishap, the Contractor shall cooperate fully and assist Government personnel in conducting of the investigation until it is completed.
The Contractor agrees that his personnel and equipment are subject to safety inspections by Government personnel while on federal property.
4.11.2 Radiological Waste, Hazardous Material and Hazardous Waste Permitting and Reporting
The Contractor shall sample and handle all radiological waste, hazardous materials and waste in accordance with applicable federal, state, and local requirements. The Contractor shall provide all radiological waste, hazardous materials use and hazardous waste disposal documentation to the Base Environmental Office, or Installation Hazardous Waste Program Manager, and shall register with the Hazardous Materials Pharmacy program (if available) at the installation to ensure appropriate and efficient tracking of the Contractor’s hazardous material purchases, inventories, use, and releases such as required by the Emergency Planning and Community Right-to-Know Act (EPCRA), Executive Orders, or any installation reporting requirements. (CDRLs A001, A003, A009)
The Contractor shall also comply with federal, state, and local requirements for any task involving the transportation of radiological waste, hazardous wastes and/or contaminated materials to off-site treatment, storage and/or disposal facilities. The Contractor is responsible for the disposition of all Radiological, Hazardous Material and Waste produced by activities directly involved in the construction related operations. This includes 40 CFR 260, 49 CFR 172, 173, 178, 179 and all other applicable local, state, and federal transportation regulations.
The Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste be trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures and spills. The Contractor shall provide handling and personnel protective equipment to ensure safe handling of the hazardous/asbestos waste. The Contractor must agree that his personnel and equipment are subject to safety inspections by Government personnel while on Federal property.
5.0 PLANS AND REPORTS
5.1 Project Data/Project Deliverables
Project data and deliverables, as specified in each TO shall be provided to AFCEC personnel by the Contractor to support multiple projects with real-time or near real-time access. Deliverables may include, but are not limited to, a submittal tracker or register, a Request for Information (RFI) tracker, a change order tracker, a photographic log, status reports and project schedule(s).
5.1.1 Administrative, Physical, and Technical Safeguards
Contractor shall implement appropriate administrative, physical, and technical safeguards to protect the confidentiality and integrity of all Government Digital Data obtained in compliance with Federal Information Processing Standards (FIPS), the “Special Publications 800 series” guidelines published by NIST, and the requirements of FISMA.
· Federal Information Security Management Act (FISMA) of 2002.
· Clinger-Cohen Act of 1996 also known as the “Information Technology Management Reform Act of 1996.”
· Privacy Act of 1974 (5 U.S.C. § 552a).
· Homeland Security Presidential Directive (HSPD-12), “Policy for a Common Identification Standard for Federal Employees and Contractors”, August 27, 2004.
· Office of Management and Budget (OMB) Circular A-130, “Management of Federal Information Resources”, and Appendix III, “Security of Federal Automated Information Systems”, as amended.
· OMB Memorandum M-04-04, “E-Authentication Guidance for Federal Agencies.”
· FIPS PUB 199, “Standards for Security Categorization of Federal Information and Information Systems.”
· FIPS PUB 200, “Minimum Security Requirements for Federal Information and Information Systems.”
· FIPS PUB 140-2, “Security Requirements for Cryptographic Modules.”
· NIST Special Publication 800-18 Rev 1, “Guide for Developing Security Plans for Federal Information Systems.”
· NIST Special Publication 800-30, “Risk Management Guide for Information Technology Security Risk Assessment Procedures for Information Technology Systems.”
· NIST Special Publication 800-34, “Contingency Planning Guide for Information Technology Systems.”
· NIST SP 800-37, Revision 1, “Guide for the Security Certification and Accreditation of Federal Information Systems.”
· NIST Special Publication 800-47, “Security Guide for Interconnecting Information Technology Systems.”
· NIST Special Publication 800-53 Revision 3, “Recommended Security Controls for Federal Information Systems.”
· NIST Special Publication 800-53A, “Guide for Assessing the Security Controls in Federal Information Systems.”
5.1.2 FIPS 200, “Minimum Security Requirements for Federal Information and Information Systems”
FIPS 200 is a mandatory federal standard that defines the minimum security requirements for federal information and information systems in seventeen security-related areas. Contractor systems supporting AFCEC must meet the minimum security requirements through the use of the security controls in accordance with NIST Special Publication 800-53, Revision 3 (hereafter described as NIST 800-53), and “Recommended Security Controls for Federal Information Systems.
To comply with the federal standard, AFCEC must determine the security category of the Government information maintained/hosted by the contractor in accordance with FIPS 199, “Standards for Security Categorization of Federal Information and Information Systems”, and then the contractor shall apply the appropriately tailored set of Low, Moderate, or High impact baseline security controls in NIST 800-53, as determined by AFCEC.
NIST 800-53 controls requiring organization-defined parameters (i.e., password change frequency) shall be consistent with AFCEC specifications.
The Contractor shall use NIST guidelines, Center for Internet Security (CIS) guidelines (Level 1), or industry best practice guidelines in hardening their systems, as deemed appropriate by the Authorizing Official.
5.1.3 Inspections of the Contractor’s IT Environment
The Government has the right to perform manual or automated audits, scans, reviews, or other inspections of the Contractor’s IT environment being used to provide or facilitate services for the Government. In accordance with the Federal Acquisitions Regulations (FAR) clause 52.239-1, the Contractor shall be responsible for the following privacy and security safeguards:
i. The Contractor shall not publish or disclose in any manner, without the Contracting Officer’s written consent, the details of any safeguards either designed or developed by the Contractor under this TO or otherwise provided by the Government. Exception - Disclosure to a Consumer Agency for purposes of C&A verification.
ii. To the extent required to carry out a program of inspection to safeguard against threats and hazards to the security, integrity, and confidentiality of any non-public Government data collected and stored by the Contractor, the Contractor shall afford the Government logical and physical access to the Contractor’s facilities, installations, technical capabilities, operations, documentation, records, and databases within 72 hours of the request. Automated audits shall include, but are not limited to, the following methods:
· Authenticated and unauthenticated operating system/network vulnerability scans
· Authenticated and unauthenticated web application vulnerability scans
· Authenticated and unauthenticated database application vulnerability scans
Automated scans can be performed by Government personnel, or agents acting on behalf of the Government, using Government operated equipment, and Government specified tools. If the Contractor chooses to run its own automated scans or audits, results from these scans may, at the Government’s discretion, be accepted in lieu of Government performed vulnerability scans. In these cases, scanning tools and their configuration shall be approved by the Government. In addition, the results of Contractor-conducted scans shall be provided, in full, to the Government.
iii. If new or unanticipated threats or hazards are discovered by either the Government or the Contractor, or if existing safeguards have ceased to function, the discoverer shall immediately bring the situation to the attention of the other party.
5.1.4 Secure Protection and Handling of Data
5.1.4.1 Data Storage
Contractor agrees that any and all AFCEC data will be stored, processed, and maintained solely on designated target servers and that no AFCEC data at any time will be processed on or transferred to any portable or laptop computing device or any portable storage medium, unless that device or storage medium is in use as part of the Contractor's designated backup and recovery processes and encrypted in accordance with “5.1.4.3 Data Encryption”.
5.1.4.2 Data Transmission
Contractor agrees that any and all electronic transmission or exchange of system and application data with AFCEC and/or any other parties expressly designated by AFCEC shall take place via secure means (using HTTPS or SFTP or equivalent) and solely in accordance with “5.1.4.4 Data Re-Use”.
5.1.4.3 Data Encryption
Contractor agrees to store all AFCEC backup data as part of its designated backup and recovery processes in encrypted form, using a commercially supported encryption solution. Contractor further agrees that any and all AFCEC data defined as personally identifiable information under current legislation or regulations stored on any portable or laptop computing device or any portable storage medium be likewise encrypted. Encryption solutions will be deployed with no less than a 128-bit key for symmetric encryption and a 1024 (or larger) bit key length for asymmetric encryption.
5.1.4.4 Data Re-Use
Contractor agrees that any and all data exchanged shall be used expressly and solely for the purposes enumerated in the current contract/TO. Data shall not be distributed, repurposed or shared across other applications, environments, or business units of Contractor. Contractor further agrees that no AFCEC data of any kind shall be transmitted, exchanged or otherwise passed to other contractors or interested parties except on a case-by-case basis as specifically agreed to in writing by AFCEC.
5.1.4.5 End of Agreement Data Handling
Contractor agrees that upon termination of each TO it shall transfer all data to AFCEC and erase, destroy, and render unrecoverable all AFCEC data hosted at the Contractor site and certify in writing that these actions have been completed within 30 days of the termination of the TO or within 7 days of the request of an agent of AFCEC, whichever shall come first. At a minimum, a “Clear” media sanitization is to be performed according to the standards enumerated by the National Institute of Standards, Guidelines for Media Sanitization, SP800-88, Appendix A - see http://csrc.nist.gov/.
5.1.4.6 Security Breach Notification
Contractor agrees to comply with all applicable laws that require the notification of individuals in the event of unauthorized release of personally identifiable information or other event requiring notification. In the event of a breach of any of Contractor’s security obligations, or other event requiring notification under applicable law, Contractor agrees to:
a. Notify AFCEC and CO by telephone and e-mail of such an event within 24 hours of discovery, and
b. Assume responsibility for informing all such individuals in accordance with applicable law, and
c. Indemnify, hold harmless and defend AFCEC and its trustees, officers, and employees from and against any claims, damages, or other harm related to such Notification Event.
5.1.4.7 Right to Audit
AFCEC or an appointed audit firm (Auditors) has the right to audit the Contractor and the Contractor’s sub-Contractors or affiliates that provide a service for the processing, transport or storage of AFCEC data. AFCEC will announce their intent to audit the Contractor by providing at a minimum two weeks (10 business days) notice to the Contractor. This notice will go to the Contractor with whom this contract is executed. A scope document along with a request for deliverables will be provided at the time of notification of an audit. If the documentation requested cannot be removed from the Contractor’s premises, the Contractor will allow the Auditors access to their site. Where necessary, the Contractor will provide a personal site guide for the Auditors while on site. The Contractor will provide a private accommodation on site for data analysis and meetings; the accommodation will allow for a reasonable workspace, with appropriate lighting, electrical, a printer and Internet connectivity. The Contractor will make necessary employees or contractors available for interviews in person or on the phone during the time frame of the audit. In lieu of AFCEC or its appointed audit firm performing their own audit, if the Contractor has an external audit firm that performs a certified Type II SAS 70 review, AFCEC has the right to review the controls tested as well as the results, and has the right to request additional controls to be added to the certified Type II SAS 70 review for testing the controls that have an impact on AFCEC data. Audits will be at AFCEC’s sole expense, except where the audit reveals material noncompliance with contract specifications, in which case the cost will be borne by the Contractor.
5.2 Health and Safety Plan (HSP)
The Contractor shall provide a Health and Safety Plan (HSP) in accordance with EM385-1-1. (CDRL A004)
5.3 Quality System Plan (QSP)
The Contractor shall prepare, for AFCEC review and approval, a site-specific QSP that is inclusive of Design Quality Control where required for each TO. Approval by the CO of the Design Quality Control plan is required before design may proceed. The Quality Control Plan must indicate the designer’s integral role throughout design and construction for each TO. (CDRL A005)
The Contractor must implement, maintain, and comply with the approved site-specific QSP and post results to the project web site. The Contractor shall organize, document, prepare procedures for, and implement a management-driven system to provide maximum assurance that products and services conform to specified requirements. Products and services submitted in the performance of this contract shall be according to the American National Standard Institute (ANSI)/American Society for Quality Control (ASQC) standards if applicable, or Best Commercial Practice, and contract requirements. All work accomplished by the Contractor shall be of sufficient quality and level of acceptance by Federal, State, and local regulators or code inspectors. The Contractor shall submit a Quality Control Program Plan detailing the execution of this program to the CO for approval which is required prior to receiving a Notice to Proceed (NTP).
5.4 Technical Plans and Reports
The Contractor shall provide technical plans, specifications, and reports as defined below and implemented at the TO level. Some of these may include, but are not limited to, the following:
5.4.1 Construction Work Plan
The Contractor shall prepare a Construction Work Plan that may include, but is not limited to, any or all of the following subsections as identified in each TO. (CDRL A006)
1) Work Sequencing
2) Design Analysis
3) Security
4) Site Analysis
5) Site Preparation
6) Excavation
7) Spill and Discharge Control
8) Explosive Safety
9) Hazardous Materials Management
10) Asbestos Abatement
11) Surface Water Management
12) Ground Water Management
13) Erosion Control
14) Emissions Control
15) Material and Equipment Control and Storage
16) Transportation
17) Startup Testing and Commissioning Plans
18) Warranty Call Out Program
19) Draft 1354s
20) Demobilization
5.4.2 Technical Reports
The Contractor shall prepare and submit the following technical reports as identified in each TO. Each of the following technical reports may not be required at the TO level and will be specified as such in each individual TO.
1) Miscellaneous Technical Report (CDRL A001)
2) Construction Cost Estimates (CDRL A007)
3) Site/Project Summary (CDRL A001)
4) Daily Technical/Field Reports (Status Reports) (As a part of the daily technical/field reports, all tasks shall be identified by Construction Activity Identification number and correspond with the approved baseline schedule and the WBS.) (CDRL A008)
5) Hazardous Materials Survey Report (CDRL A009)
6) Hazardous Material and/or Hazardous Waste Disposal Report (CDRL A001)
7) Design Drawings (CDRL A010)
8) Shop Drawings and/or As-built Drawings (CDRL A011)
9) Design Specifications (CDRL A001)
10) Geographical Information Systems Updates (CDRL B010)
11) Computer Aided Design Drawings (CDRL B011)
12) Survey Reports (CDRL A009)
13) Quality Assurance/Quality Control Surveillance Plan
14) O&M Training Manuals
15) Startup and Commissioning Report
16) Warranties
17) Call Out Procedures
6.0 SITE WORK
The Contractor shall perform site preparation, incidental characterization and field investigation, conservation, and demolition of sites as required in each TO.
6.1 Conservation
Activities shall be planned and implemented in a manner that protects existing site utilities, structures, surface features, service operations, monitoring and other types of wells, and the general site environment. This includes the protection of trees, shrubs and other vegetation not in the affected zone from dust damage, soil compaction, and physical contact with machines and equipment. If appropriate, the Contractor shall conserve uncontaminated topsoil by removal, storage, or redistribution. All reasonable measures shall be taken to minimize and suppress fugitive emissions of dust, vapors, and other site materials during site work. All fill materials shall be non-contaminated. The Contractor shall conduct all operations and activities with the intent of reducing the amount of pollution generated. Specific areas to be focused on are generation of solid waste, use of hazardous materials, use of ozone depleting chemicals, generation of hazardous waste, and use of energy and water. During site work the Contractor shall plan, construct, operate, maintain, optimize, and decommission systems necessary to control storm water run-on and run-off; and transport surface water drainage to a treatment plant, discharge location, or any other appropriate destination for discharge in accordance to local environmental regulations.
6.2 Site Preparation
The Contractor shall perform site work as necessary to prepare sites for construction activities. Security and access controls shall be implemented to prevent unauthorized entry to sites and to protect wildlife from site exposure. The Contractor shall survey existing utilities to determine adequacy and need for modifications to support site activities. The Contractor shall obtain appropriate approvals and shall construct connections or new systems for electrical power, water, sewer, gas distribution, telephone, and other utilities, as required, to accomplish the activities specified in each TO. (CDRL A012)
6.3 Demobilization
The Contractor shall decontaminate equipment and facilities, decommission facilities as necessary, and restore the site back to its pre-project condition or as directed in the TO. The Contractor shall remove any temporary facilities and implement erosion control measures such as seeding, mulch, sodding, and erosion control fabrics; restore roads, structures and utilities; and plant trees, shrubbery, grasses and other vegetation. The Contractor shall document and report on activities and train Government personnel to perform required maintenance, as requested. (CDRL A001)
The Contractor shall abide by FAR 52.245-1 Government Property and DCMA instructions pertaining to disposal of Government Property and reporting through the Plant Clearance Automated Reutilization Screening System (PCARSS) in the removal and disposition of any Government Property during the Demobilization from the project sight.
7.0 FACILITY CONSTRUCTION TASK ORDER TYPES
7.1 Turnkey
Under 10 USC 2862 One-step turnkey selection procedures may be used for the purpose of entering into contracts for the construction of authorized military construction projects only, both CONUS and OCONUS, which include regular Military Construction (MILCON), Unspecified Minor Military Construction (UMMC), Military Family Housing (MFH), and Base Realignment and Closure (BRAC). In this section, the term “one-step turn-key selection procedures” means procedures used for the selection of a contractor on the basis of price and other evaluation criteria to perform, in accordance with the provisions of a firm fixed-price contract, both the design and construction of a facility using performance specifications supplied by the Secretary concerned. This selection procedure is highly specialized and unique and shall only be awarded under the rules set forth by 10 USC 2862. Given the WE&C Contractor’s level of involvement in one-step turnkey, the WE&C contractor will serve as both the Architect/Engineer of Record for completed projects as well as the Contractor of Record.
Turnkey or one step construction is restricted by Federal Law to MILCON construction only, and it is not anticipated that any Turnkey TO will be authorized for the RE&C contractors’ accomplishment.
7.2 Design Build (D-B)
From USC Title 10 Section 2305, design-build may be used to perform the design and construction of a public building, facility, or work. D-B can be used, for the construction of authorized military construction projects such as Military Construction (MILCON), Unspecified Minor Military Construction (UMMC), Military Family Housing (MFH), and Base Realignment and Closure (BRAC). In addition to these types of projects, D-B can also be used for projects outside of authorized military construction such as, but not limited to, Army and Air Force Exchange Services (AAFES), Air Force Services Agency (AFSVA), Defense Energy Support Center (DESC), Defense Logistics Agency (DLA), etc. The RE&C contractor shall manage and perform D-B construction work as defined in the TO. The following are typical D-B construction TO requirements: completion of working drawings, permitting, construction, construction management, scheduling, inspection and testing, maintaining construction facilities and temporary controls, environmental protection, quality control, construction quality control, and project closeout. Specific requirements will be provided at the TO level.
7.2.1 Design Completion
Prior to beginning onsite construction, the RE&C Contractor, as directed in the RFP, will initiate the Construction Phase by completing project working drawings and the various plans and schedules, including a construction schedule using Program Evaluation and Review Technique (PERT), Critical Path Method (CPM), or equivalent scheduling tools, and obtaining submittal approvals and permits. Working drawings and specifications shall comply with codes, laws, the RFP, and the TO. The working drawings shall be submitted for review as directed in the TO statement of work. The RE&C Contractor shall be responsible for implementation, coordination, and execution of all regulatory reviews, ensure technical adequacy of the final design, and provide quality control of all phases of the TO. Further details regarding design requirements will be provided at the TO level.
7.2.2 Project Construction
The RE&C contractor may with approval of the Contracting Officer begin onsite construction in a fast-track method as proposed during the design completion phase by completing said design in defined phases to permit early start of construction prior to final working drawings for all phases of the construction. If the RE&C Contractor chooses to exercise fast-track construction, he remains fully responsible for coordination of all aspects of the design and the Government will permit no consideration for delays if early construction start creates inconsistencies or conflicts in later phases of the design/construction operations.
7.3 Design-Bid-Build (D-B-B)
The RE&C Contractor shall manage and perform D-B-B construction work as defined in the TO. Under this type of effort, a complete design and set of specifications shall be provided to the Contractor for construction.
7.5 Construction Operation Services
The Contractor shall perform a full range of activities to meet all customers engineering and other construction requirements as described in each TO. Requirements may include construction, completion of conceptual design and construction, demolition, decommissioning, and emergency response for traditional engineering and construction needs. All completed designs shall be signed and sealed in accordance with all applicable requirements. (CDRLs A001, A009, A013)
NOTE: Stand-alone design is not included in the scope of this contract.