Attachment 3. Master Contract Data Requirements List.docx
DOCX document 491 KB Posted
- Attached to
- DRAFT FOPR for 24/7 NOC _ OASIS+ Total Small Business Federal contract opportunity
- Solicitation number
- FA880625RB003
- Issued by
- Department of the Air Force
About this file
This document is a Contract Data Requirements List (CDRL) that establishes the minimum requirements for the data to be delivered by the contractor under an indefinite delivery, indefinite quantity (IDIQ) multiple award contract for the Acquisition and Management of Supply Contract.
The CDRL identifies four key data items to be delivered: 1) Contract Funds Status Report, 2) Program Protection Implementation Plan, 3) Data Accession List, and 4) Program Management Review. It specifies the frequency, distribution, and government acceptance criteria for each data item. The CDRL also includes definitions for various terms and an index of the CDRL items. The overall contract is for a 24/7 Network Operations Center to be acquired under the One Acquisition Solution for Integrated Services (OASIS+) Total Small Business contract vehicle, with the Department of the Air Force as the procuring agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 24x7 NOC FORP PCO Letter.pdf | ||
| Attachment 4 Supply Pricing Table.xlsx | XLSX spreadsheet | |
| Attachment 7. Contract Security Classification Specification DD254.pdf | ||
| Attachment 8. Comments Resolution Matrix.docx | DOCX document | |
| Solicitation - FA880625RB003.pdf | ||
| Attachment 1. Stament Of Work.pdf | ||
| Solicitation - Clauses and Provisions.pdf | ||
| Attachment 2. Placement Procedures.pdf | ||
| Attachment 5. Organizational Conflict of Interest Checklist.pdf | ||
| Attachment 6. Quality Assurance Surveillance Plan.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Acquisition and Management of Supply Contract Master Contract Data Requirements List
Issued Under the Multiple Award Indefinite Delivery Indefinite Quantity Contract:
One Acquisition Solution for Integrated Services + Total Small Business
For
SSC/BCC Operational Space C2 Acquisition Delta
Date:
9 October 2024
Contract Data Requirements List
24/7 Network Operations Center
Contents
| Scope | 3 |
| General | 3 |
| Distribution Statement | 3 |
| Contract Data Requirements List Items | 4 |
| Government Acceptance | 4 |
| Definitions | 5 |
| MASTER CDRL INDEX | 7 |
| CONTRACT DATA REQUIREMENTS LIST DISTRIBUTION | 7 |
| MASTER ADDRESS LIST | 7 |
Scope This instruction establishes the minimum requirements for the data to be delivered by the contractor in performance of this task order and the process for the submittal, distribution, inspection, approval, and acceptance of all the contract data requirements list items contained within Exhibit A.
Data Rights The Contractor shall grant the Government Purpose Rights in all technical data, deliverables and supply performed under this contract, including rights to use, duplicate, modify, release, perform, display, or disclose technical data for this supply within the Government. This includes any supply or deliverable that is produced, procured or manufactured as a result of this contract. The Government requires these rights to fulfill its mission and to ensure that the work performed under this contract is available for use by other Government agencies or contractors, as well as for public release as applicable.
General Data Item Descriptions referenced in Block 4 of the contract data requirement list are listed in the Acquisition Streamlining and Standardization Information System, which can be accessed via the following website: http://quicksearch.dla.mil/qsSearch.aspx. Only unique Data Item Descriptions or attachments will be included in Exhibit A.
Distribution Statement The designation "D" in Block 9 of the Contract Data Requirements List indicates that the following distribution statement shall be annotated on each data item in accordance with DoDD 5230.24.
Unclassified Distribution Statement D: Distribution authorized to DoD and US DoD contractors: due to the sensitive information (as defined in DoD 5230.24) associated with this effort.
Other requests for this document shall be referred to the Contracting Officer's Representative. Unclassified deliverables may be destroyed by any method that will prevent disclosure of contents or reconstruction of material.
Classified Distribution Statement D: Distribution authorized to DoD and US DoD contractors only, due to the sensitive information (as defined in DoD 5200.1-R) associated with the One Acquisition Solution for Integrated Services effort. Other requests for this document shall be referred to the Contracting Officer's Representative. For destroying Classified Deliverables follow the procedure identified in DoD 5200.1-R, Information Security Program (ISP) or DoD 5220.22-M, National Industrial Security Program Operating Manual (NJSPOM). Additionally, the following notice will be used on all classified deliverables documents:
WARNING
INFORMATION SUBJECT TO EXPORT CONTROL LAWS
This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C. 2571 et seq.) or Executive Order 12470. Violators of these export laws are subject to severe criminal penalties. Dissemination of this document is controlled under DoD Directive 5230.24.
Contract Data Requirements List Items Letters of Transmittal (Block 7) - Delivery of contract data requirements list items shall be a physical hard copy and electronic format to the Contracting Officer's Representative. The Contractor shall provide notification to the applicable government counterpart and the Contracting Officer's Representative. A separate transmittal letter shall be included for each Contract Data Requirements List item and shall include (at a minimum) contract number, Contract Data Requirements List sequence number, document title/subtitle, and identification of approval required. Each letter shall be assigned a contractor program unique number.
All data delivered with the Letter of Transmittal shall be collectively accounted for under the Material Inspection and Receiving Report (DD Form 250). The period of performance shall reflect the duration of the task order. The DD Form 250 shall be prepared and submitted by the Contractor to the Government Contracting Officer's Representative within 30 calendar days after the end of the based period and each option period of performance unless otherwise stated in the contract.
The DD Form 250 shall list and account for all data delivered to the Government during contractual period of performance. Do not list Data items that were not previously accepted by the Contracting Officer's Representative during the period of performance.
The DD Form 250 list shall identify Contract Data Requirements List sequence number, document title, document number, contractor transmittal letter number, date of delivery, acceptance method and disposition for each delivery item. The Contractor's computerized printout may be used in lieu of a DD Form 250 if the deliverable is in a government usable format. The Contracting Officer's Representative will determine what is acceptable and may change the format of delivery at will.
The contractor shall immediately notify the Government Contracting Officer of any request that the contractor feels increases the contract price and will not comply with the request until directed by the contracting officer.
Government Acceptance Deliverable acceptance is at the discretion of the Contracting Officer's Representative. Acceptance indicates agreement or concurrence with the contractor's furnished data only and shall not be construed as changing any of the terms or conditions of the subject contract.
Only when an "A" is indicated in Block 8 of the Contract Data Requirements List form is formal acceptance required. Unless indicated otherwise in the specific Contract Data Requirements List item, the contractor should anticipate a cycle time of approximately 30 days.
Accepted - No further action required.
Accepted with comments - The contractor shall revise the deliverable in accordance with Contracting Officer's Representative input(s) and resubmit. Reference the Services Summary of the Performance Work Statement for timeliness standards.
All data shall be delivered/deposited no later than 1730 at the end of the business day for specified due date. The contractor is considered delinquent when a Letter of Transmittal is not received by the Contracting Officer's Representative before the dates specified in blocks 12, 13, and/or 16 of the Contract Data Requirements List Form. If the due date falls on a weekend or government holiday, then the delivery date becomes the first government business day following the weekend and/or holiday.
Management, administrative and product descriptive data shall be developed in a Government usable format. The contractor may not construe acceptance of a document by the Government as relief from contractual requirements should the document not meet those requirements. The Government does not assume responsibility for errors contained in contractor submitted documents and resubmission may be required at no additional costs to the Government.
Updates and/or Changes to data items may require a complete reissuance of the data items in entirety, or change pages, when the use of the change pages does not affect the readability and understanding of the data item. Change pages shall have the revised information identified and shall be accompanied by a remove and replace listing of the affected pages.
Definitions A: Government Approval Required ASREQ: As Required ASGEN: As Generated ANNLY: Annually BI-MO: Each 2 months BI-WE: Each two weeks CA: Contract Award CD: Calendar Days CDRL: Contract Data Requirements List COR: Contracting Officer's Representative D: Distribution Statement DAAP: Days After Accounting Period DAC: Days After Contract Award DAEO: Days After Exercised Option DAILY: Daily DAS: Days after contract start DAT: Days after Task Order Anniversary DACM: Days after contract modification DID: Data Item Description DIN: Data Item Number EOC: End of Contract EOM: End of Month EOQ: End of Quarter EOW: End of Week F: Reference to block 9, Distribution- Further dissemination only as directed by controlling office.
LT: Letter of Transmittal MTHLY: Monthly NLT: No Later Than ONE/P: One Time Preliminary Draft ONE/R: One Time, and Updates OTIME: One Time QRTLY: Quarterly SEMIA: Every 6 months REV: Revisions as required WD: Working Days WEKLY: Weekly XTIME: Multiple Separate Submittals (i.e., 2 times, 3 times)
| Contract: | TBD |
| Exhibit: | A |
24/7 Network Operations Center Contractor: TBD
MASTER CDRL INDEX
| CDRL |
| Data Item Number |
| Title and Subtitle |
| A001 |
| DI-MGMT-81928 |
| Contract Funds Status Report |
| A002 |
| DI-ADMIN-8 l306 |
| Program Protection Implementation Plan (PPIP) |
| A003 |
| DI-MGMT-81453A |
| Data Accession List (DAL) |
| A004 |
| DI-ADMIN-81373 |
| Program Management Review (PMR) |
CONTRACT DATA REQUIREMENTS LIST DISTRIBUTION
| CDRL |
| Title and Subtitle |
| OPR / Office |
| Final |
| A001 |
| Cost Funds Status Report (CFSR) |
| COR & ML |
| LT w/ encl. |
| A002 |
| Program Protection Implementation Plan (PPIP) |
| COR & ML |
| LT w/ encl. |
| A003 |
| Data Accession List (DAL) |
| COR & ML |
| LT w/ encl. |
| A004 |
| Program Management Review (PMR) |
| COR & MIL |
| LT w/ encl. |
MASTER ADDRESS LIST
| Office Symbol / Organization |
| Address |
Contracting Officer
SSC/BCK
Space Systems Command
SSC/PK
483 N. Aviation Blvd El Segundo, CA 90245-2808
Contracting Officer Representative
SSC/BCC
Space Systems Command
SSC/BCC (COR)
483 N. Aviation Blvd El Segundo, CA 90245-2808
Materiel Leader
SSC/BCC
Space Systems Command
SSC/BCC (ML)
483 N. Aviation Blvd El Segundo, CA 90245-2808
CDRLS are embedded below.
image1.emf
CDRL A001 - Contract Funds Status Report.pdf
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
PREVIOUS EDITION MAY BE USED.
DD FORM 1423, FEB 2024
Page of
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoDM 5010.12 for detailed instructions.)
DD FORM 1423, FEB 2024
Page of
CONTRACT DATA REQUIREMENTS LIST
C. CATEGORY:
14. DISTRIBUTION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft
Final
Reg
Repro
16. REMARKS
14. DISTRIBUTION
15.TOTAL
Image of arrow pointing towards totals
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Name of preparer of CDRL.
Item H. Date CDRL was prepared and signature of preparer of CDRL.
Item I. Name of CDRL approval authority.
Item J. Date CDRL was approved and signature of CDRL approval authority.
Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.
Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.
9.0.0.2.20120627.2.874785
DD Form 1423, "Contract Data Requirements List"
CurrentPage:
PageCount:
Select Classification from drop-down list.: 1
DI:
Click on this button to attach a file(s).:
A. CONTRACT LINE ITEM NUMBER: 001
exhibit: A
C. CATEGORY: Select for "TDP.": 0
C. CATEGORY: Select for "TM.": 0
C. CATEGORY: Select for "OTHER.": 1
C. CATEGORY: Enter specification for "Other.": Report
System: OASIS+ Total SB
ContractNum: TBD
Contractor: TBD
1. DATA ITEM NUMBER: A001
titleDataItem: Contract Funds Status Report subtitle: CFSR
4. AUTHORITY (Data Acquisition Document Number): DI-MGMT-81928 contractRef: SOW, PARA 2.4.1 PAGE 10 reqOffice: SSC/BCCS
7. DD 250 REQUIREMENT: N/A
8. APPROVAL CODE : A
9. DISTRIBUTION STATEMENT REQUIRED: D
freq: MTHLY asOfDate: Fiscal Month End dateFirstSub: Next Fiscal Month End dateSubseqSub: Following Month End
16. REMARKS: Compliance: N/A Reference: N/A
Blocks 4:
Contractor Format Authorized
Blocks 10-14: The Contractor shall submit CFSRs monthly no later than 10 business days after each Contractor fiscal month end.
The CSFR shall be broken out by CLIN
Click to add continuation field for Remarks:
14. DISTRIBUTION - a. ADDRESSEE, new line: PCO
14. DISTRIBUTION - a. ADDRESSEE, new line: PM
14. DISTRIBUTION - a. ADDRESSEE, new line: COR
14. DISTRIBUTION - a. ADDRESSEE, new line: ATLAS PM
15.TOTAL - Total draft copies is automatically calculated.:
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 4
15.TOTAL - Total final reproducible copies is automatically calculated.:
priceGrp:
estTotalPrice:
remarks:
preparedBy: BOLITHO, LOGAN
J. SIGNATURE: H. SIGNATURE
J. SIGNATURE: J. SIGNATURE
J. SIGNATURE:
approvedBy: GONZALEZ, MATTHEW
Click to add additional data items.:
Click to delete additional data items.:
image2.emf
CDRL A004 - Space C2 PMR Template.pptx DD Mmmmm YYYY
Project Name PMR
Program Manager/Lead Name
UNCLASSIFIED
Program Overview / OV-1
BLUF Chart
Staffing
Roadmap
Schedule
Financials
GFE/GFI Update
Risks
Challenges / Opportunities
Open Issues
Action Items
Overview
Graphical & verbal description of requirement
Program Overview
Quick summary of where the program is at. Include underrun/overrun for budget, tasks and schedule as well as a CPI (Cost Performance Index) number.
NOTE: This is different from the program overview chart. It assumes the audience understands the overview of the program. Its purpose is to state where the program is at with regard to budget, schedule and task completion.
BLUF
Visual of team structure showing what members support, staff names, and FTE associated with staff (only if partial FTEs)
Provide a total number of FTE and highlight any new additions
Identify staff changes
Organizational Chart
Pull up roadmaps in Jira to show quarterly, 1-year, and 5-year outlooks
Roadmap
Include a snapshot from your scheduling tool and place various pointers on the schedule to indicate where there is slack in the schedule.
A chart summarizing total schedule margin to start, percentage of schedule margin consumed. Also include a chart in this section that summarizes metrics such as CPI (Cost Performance Index), BAC (Budget at completion), etc.
Schedule
List here
Weekly-Reported Accomplishments
As specified within requirements document, one or more charts
Development Metrics
Funding Status
Example Only – modified to CDRL A001 as appropriate
(Forecast % is arbitrary and can be changed)
Jan Feb Mar Apr May Jun Jul Aug Nov End of PoP
CLIN 001 - Name $ 42,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00
*CLIN 001 - Subcontract Labor $ 16,000.00 $ 16,000.00 $ - $ 50,000.00 $ 50,000.00 $ 16,000.00 $ 16,000.00 $ 16,000.00 $ 16,000.00 $ 16,000.00
CLIN 002 - Name $ 58,000.00 $ 12,000.00 $ 5,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00 $ 2,000.00
Etc.
Total $ 116,000.00 $ 78,000.00 $ 55,000.00 $ 102,000.00 $ 102,000.00 $ 68,000.00 $ 68,000.00 $ 68,000.00 $ 68,000.00 $ 68,000.00
Expenses to Date $ 116,000.00 $ 194,000.00 $ 133,000.00 $ 157,000.00 $ 204,000.00 $ 170,000.00 $ 136,000.00 $ 136,000.00 $ 136,000.00 $ 136,000.00
*Example additional breakout: subcontractor labor that invoices 30-days later than prime labor to show how CFSRs might differ or need amendments due to invoicing timelines
$ 136,000.00
Forecast >5%
Forecast <= 5%
Forecast on Track
Actuals
Insert a Line Chart here that shows cost increase per month accumulating to End of PoP compared to a Line that shows anticipated cost per month that accumulates to the actual contract value (should be a line graph mapping to the excel table below)
Previous 6 Months
Next 3 Months
*** Please break down status by 9 months. Previous 6 months and next 3 months
*** We are more interested in the actuals than the projections
Total Requirements for FY 22: $xxx
Total Amount Funded : YTD $xx
Current Month Invoice (expenditures) : $xx
YTD Invoice (cumulative) : $xx
Expected Next Month Burn Rate (Invoice amount): $xx
Remaining Available Funds after this month Invoice: $xx
Current Funds Run-Out Date
Financials
*Identify any unexpected or new items e.g., new license expenses
*Add the actual date of submission of invoice and date of payment for invoice this month
5x5 of current program risks OR drop in ROAM model or other graphic from appropriate tool (ROAM = Resolved, Owner, Accepted, Mitigated model in Jira Align)
Program Risk Overview
Challenge: What are key challenges to project progress
Major challenge description
Detail one
Detail two
Describe the impact of the challenge to project progress
Opportunity: What are anticipated opportunities
Major opportunity description
Detail one
Detail two
Describe the impact of the challenge to project progress
Challenges / Opportunities
Contains an issues list that includes any liens, waivers or deviations.
The charts for this could be added in backup charts section if there are too many issues.
Open Issues
Action Items
| # | Description | Requester | Assigned To | Date | |
| Assigned | Due Date | Status | Comments |
| 1 | TBD | Name | ||
| Org | Name | |||
| Org | DD-MMM-YY | DD-MMM-YY | Open | TBD |
| 2 | TBD | Name | ||
| Org | Name | |||
| Org | DD-MMM-YY | DD-MMM-YY | Open | TBD |
Back-Up Charts
Materials Breakout
CDRLs Status
Retired Action Items
Government Furnished Equipment/Information (GFE/GFI)
Move material up / add material as needed to address current program priorities, risks, issues, etc.
Materials Breakout
Description Cost Purchase Date Type
X License $10,000 14 Jan 22 1-year
Y License $15,000 14 Jan 22 3-year
X Hardware $56,000 ~June 22 One Time
Total $81,000
CDRL Status
CDRL Name Frequency by Contract Current Requested Frequency Last Delivery Date
X As Required Monthly 15 March 2022
X Monthly Monthly 15 March 2022
X Etc. Etc. 15 March 2022
Retired Action Items
| # | Description | Requester | Assigned To | Date | |
| Assigned | Due Date | Status | Comments |
| 1 | TBD | Name | ||
| Org | Name | |||
| Org | DD-MMM-YY | DD-MMM-YY | Closed | TBD |
| 2 | TBD | Name | ||
| Org | Name | |||
| Org | DD-MMM-YY | DD-MMM-YY | Closed | TBD |
Identify what GFE/GFI is currently being used on the contract
GFE/GFI
Other Examples
License Usage
Provide which tools your team is using and how many licenses you actively have
Highlight any monthly changes to the # of licenses
Call out any licensing needs as well
License # Bought # Actively Using Validation Date
(Classic 5x5 template Pt 1)
Consequence
| Negligible | ||
| (1) | Minor | |
| (2) | Moderate | |
| (3) | Major | |
| (4) | Catastrophic (5) |
L I ke I i h ood Almost Certain (5)
Likely (4)
Possible (3)
Unlikely (2)
Rare (1)
(Classic 5x5 template Pt 2)
Risk # Title Prob. Rating Cons. Rating Risk Rank
Total Risks 30
Total Open 22
Total Red 1
Total Yellow 16
Total Green 5
(Classic 5x5 template Pt 3 for Red Items only)
| Title | Program Impact |
| Mitigation Plan | |
| Timetable for resolution | |
| Comments |
*Include dates for mitigation plans and identify when they became issues.
image1.png image3.png image2.png image3.emf
CDRL A003 - Data Accession List (DAL).pdf viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other
Page of
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoDM 5010.12 for detailed instructions.)
DD FORM 1423, FEB 2024
Page of
CONTRACT DATA REQUIREMENTS LIST
C. CATEGORY:
14. DISTRIBUTION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft
Final
Reg
Repro
16. REMARKS
14. DISTRIBUTION
15.TOTAL
Image of arrow pointing towards totals
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Name of preparer of CDRL.
Item H. Date CDRL was prepared and signature of preparer of CDRL.
Item I. Name of CDRL approval authority.
Item J. Date CDRL was approved and signature of CDRL approval authority.
Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.
Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.
9.0.0.2.20120627.2.874785
DD Form 1423, "Contract Data Requirements List"
CurrentPage:
PageCount:
Select Classification from drop-down list.: 1
DI:
Click on this button to attach a file(s).:
A. CONTRACT LINE ITEM NUMBER: As Required exhibit: A
C. CATEGORY: Select for "TDP.": 0
C. CATEGORY: Select for "TM.": 0
C. CATEGORY: Select for "OTHER.": 1
C. CATEGORY: Enter specification for "Other.": Report
System: OASIS+ Total SB
ContractNum: TBD
Contractor: TBD
1. DATA ITEM NUMBER: A003
titleDataItem: Data Accession List subtitle: DAL
4. AUTHORITY (Data Acquisition Document Number): DI-MGMT-81453A contractRef: SOW - PARA 2.4.4 PAGE 10 reqOffice: SSC/BCCS
7. DD 250 REQUIREMENT: NO
8. APPROVAL CODE : R
9. DISTRIBUTION STATEMENT REQUIRED: D
freq: As Required asOfDate: N/A dateFirstSub: ATP + 15 Business Days dateSubseqSub: As Required
16. REMARKS: COMPLIANCE: N/A
REFERENCE: N/A
Block 4:
Contractor format authorized.
Blocks 10-13:
The Contractor shall submit a Data Accession List to the Government no later than 10 business days before each Program Management Review (PMR) when changed or updated.
The DAL shall include, at a minimum; On-Ramp Plan, Transition Plan, Small Business Contract Plan as applicable, PMR material and meeting minutes, weekly activity reports, 24x7 NOC specific procedures, training, call-trees, any applicable architectural drawings, program management plan, staffing plan, subcontract information, and organizational conflict of interest plan.
The Contractor shall submit all versions electronically in either PDF or MS Office file format compatible with the Government program office.
The Contractor shall include all classified and unclassified content in unified classified documents. Unclassified submissions missing classified content will not be accepted.
Click to add continuation field for Remarks:
14. DISTRIBUTION - a. ADDRESSEE, new line: PCO
14. DISTRIBUTION - a. ADDRESSEE, new line: PM
14. DISTRIBUTION - a. ADDRESSEE, new line: COR
14. DISTRIBUTION - a. ADDRESSEE, new line: ATLAS PM
15.TOTAL - Total draft copies is automatically calculated.:
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 4
15.TOTAL - Total final reproducible copies is automatically calculated.:
priceGrp:
estTotalPrice:
remarks:
preparedBy: BOLITHO, LOGAN
J. SIGNATURE: H. SIGNATURE
J. SIGNATURE: J. SIGNATURE
J. SIGNATURE:
approvedBy: GONZALEZ MATTHEW
Click to add additional data items.:
Click to delete additional data items.:
image4.emf
CDRL A002 - Program Protection Implementation Plan (PPIP).pdf viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other
Page of
INSTRUCTIONS FOR COMPLETING DD FORM 1423
(See DoDM 5010.12 for detailed instructions.)
DD FORM 1423, FEB 2024
Page of
CONTRACT DATA REQUIREMENTS LIST
C. CATEGORY:
14. DISTRIBUTION
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
Draft
Final
Reg
Repro
16. REMARKS
14. DISTRIBUTION
15.TOTAL
Image of arrow pointing towards totals
FOR GOVERNMENT PERSONNEL
Item A. Self-explanatory.
Item B. Self-explanatory.
Item C. Mark (X) appropriate category: TDP - Technical Data Package; TM - Technical Manual; Other - other category of data, such as "Provisioning," "Configuration Management," etc.
Item D. Enter name of system/item being acquired that data will support (e.g., Mission Design Series (MDS) designator).
Item E. Self-explanatory (to be filled in after contract award).
Item F. Self-explanatory (to be filled in after contract award).
Item G. Name of preparer of CDRL.
Item H. Date CDRL was prepared and signature of preparer of CDRL.
Item I. Name of CDRL approval authority.
Item J. Date CDRL was approved and signature of CDRL approval authority.
Item 1. See DFARS Subpart 204.71 for proper numbering. To add or delete additional data items, point and click the plus or minus sign to the right of Block J.
Item 2. Enter title as it appears on data acquisition document cited in Item 4.
Item 3. Enter subtitle of data item for further definition of data item (optional entry).
Item 4. Identify only one Data Acquisition Document No. If a single work task generates more than one deliverable data product, prepare a separate data item for each deliverable data product.
Item 5. Enter reference to tasking in contract that generates requirement for the data item (e.g., Statement of Work/Performance Work Statement paragraph number).
Item 6. Enter technical office responsible for ensuring adequacy of the data item.
Item 7. Specify requirement for inspection/acceptance of the data item by the Government.
Item 8. Specify requirement for approval of a draft before preparation of the final data item.
Item 9. For technical data and computer software, specify the contractor's requirement to mark the appropriate distribution statement on the technical data or computer software (ref. DoDI 5230.24).
Item 10. Specify number of times data items are to be delivered.
Item 11. Specify as-of date of data item, when applicable.
Item 12. Specify when first submittal is required.
Item 13. Specify when subsequent submittals are required, when applicable.
Item 14. Enter addressees and number of draft/final copies to be delivered to each addressee. Explain reproducible copies in Item 16.
Item 15. Enter total number of draft/final copies to be delivered.
Item 16. Use for additional/clarifying information for Items 1 through 15. Examples are: Tailoring of documents cited in Item 4; Clarification of submittal dates in Items 12 and 13; Explanation of reproducible copies in Item 14; Desired medium for delivery of the data item.
Identify for which data item additional remarks are provided. When tailoring the Data Acquisition Document invoked in Item 4, identify which portions of that Document are being tailored.
Identify any referenced attachments to the form. Attachments can be added using the button at the bottom of page 1.
FOR THE CONTRACTOR
Item 17. Specify appropriate price group from one of the following groups of effort in developing estimated prices for each data item listed on the DD Form 1423.
a. Group I. Definition - Data which is not otherwise essential to the contractor's performance of the primary contracted effort (production, development, testing, and administration) but which is required by DD Form 1423.
Estimated Price - Costs to be included under Group I are those applicable to preparing and assembling the data item in conformance with Government requirements, and the administration and other expenses related to reproducing and delivering such data items to the Government.
b. Group II. Definition - Data which is essential to the performance of the primary contracted effort but the contractor is required to perform additional work to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, or quality of the data item.
Estimated Price - Costs to be included under Group II are those incurred over and above the cost of the essential data item without conforming to Government requirements, and the administrative and other expenses related to reproducing and delivering such data item to the Government.
c. Group III. Definition - Data which the contractor must develop for his internal use in performance of the primary contracted effort and does not require any substantial change to conform to Government requirements with regard to depth of content, format, frequency of submittal, preparation, control, and quality of the data item.
Estimated Price - Costs to be included under Group III are the administrative and other expenses related to reproducing and delivering such data item to the Government.
d. Group IV. Definition - Data which is developed by the contractor as part of his normal operating procedures and his effort in supplying these data to the Government is minimal.
Estimated Price - Group IV items should normally be shown on the DD Form 1423 at no cost.
Item 18. For each data item, enter an amount equal to that portion of the total price which is estimated to be attributable to the production or development for the Government of that item of data.
These estimated data prices shall be developed only from those costs which will be incurred as a direct result of the requirement to supply the data, over and above those costs which would otherwise be incurred in performance of the contract if no data were required. The estimated data prices shall not include any amount for rights in data. The Government’s rights to use the data shall be governed by the pertinent provisions of the contract.
9.0.0.2.20120627.2.874785
DD Form 1423, "Contract Data Requirements List"
CurrentPage:
PageCount:
Select Classification from drop-down list.: 1
DI:
Click on this button to attach a file(s).:
A. CONTRACT LINE ITEM NUMBER: As Required exhibit: A
C. CATEGORY: Select for "TDP.": 0
C. CATEGORY: Select for "TM.": 0
C. CATEGORY: Select for "OTHER.": 1
C. CATEGORY: Enter specification for "Other.": Report
System: OASIS+ Total SB
ContractNum: TBD
Contractor: TBD
1. DATA ITEM NUMBER: A002
titleDataItem: Program Protection Implementation Plan subtitle: PPIP
4. AUTHORITY (Data Acquisition Document Number): DI-ADMN-81306 contractRef: SOW - Para 3.0 & 3.3 reqOffice: SSC/BCCS
7. DD 250 REQUIREMENT: LT
8. APPROVAL CODE : A
9. DISTRIBUTION STATEMENT REQUIRED: D
freq: As Required asOfDate: N/A dateFirstSub: ATP + 30 Calendar Days dateSubseqSub: As Required
16. REMARKS: CCompliance: N/A Reference: DoD Joint SAP Implementation Guide (Jan 2016)
Blocks 4:
Contractor Format Authorized
Blocks 10-13:
The Contractor shall submit the inital Program Protection Implementation Plan (PPIP) for Government approval no later than 30 calendar days after DO award/ATP. Subsequent updates will be provided 5 days prior to a scheduled Program Management Review (PMR), when the PPIP is updated.
The Contractor's submission shall comply with the DD-254.
The PPIP shall contain and address and minimum the following elements: Program Description, Program Structure, CPIs and Criticality Analysis, Threats/Vulnerabilities/Countermeasures, Supply Chain Risk Management, Multi-Level Security, OPSEC and Legends, and Traditional Security.
The Contractor shall submit all versions electronically in either PDF or MS Office file format compatible with the Government program office.
The Contractor shall include all classified and unclassified content in unified classified documents. Unclassified sumissions missing classified content will not be accepted.
Click to add continuation field for Remarks:
14. DISTRIBUTION - a. ADDRESSEE, new line: PCO
14. DISTRIBUTION - a. ADDRESSEE, new line: PM
14. DISTRIBUTION - a. ADDRESSEE, new line: COR
14. DISTRIBUTION - a. ADDRESSEE, new line: ATLAS PM
15.TOTAL - Total draft copies is automatically calculated.:
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 1
15.TOTAL - Total final regular copies is automatically calculated.: 4
15.TOTAL - Total final reproducible copies is automatically calculated.:
priceGrp:
estTotalPrice:
remarks:
preparedBy: BOLITHO, LOGAN
J. SIGNATURE: H. SIGNATURE
J. SIGNATURE: J. SIGNATURE
J. SIGNATURE:
approvedBy: GONZALEZ MATTHEW
Click to add additional data items.:
Click to delete additional data items.:
image5.emf
CDRL A001 - Cost Funds Status Report Template.xlsx Cover
Cover Sheet
&"Arial,Regular"&10&K000000&P of &N &"Arial,Regular"&10&K0000009/27/21
LOE
Cover Sheet
MONTHLY CONTRACT STATUS REPORT - LOE
MONTH
NAME OF CONTRACTOR: CONTRACT TYPE:
CONTRACT NO: REPORTING PERIOD START:
PERIOD OF PERFORMANCE: REPORTING PERIOD END:
CONTRACT SUMMARY:
Action Contract / TO CLIN PoP Modification No. Ceiling Funding
Monthly Report CPFF 0102 8/1/2018 - 7/31/2019 $ 500,000.00 $ 500,000.00
Monthly Report CPFF 2102 8/1/2018 - 7/31/2019 $ 10,000.00 $ 10,000.00
Monthly Report CPFF 0202 8/1/2018 - 7/31/2019 $ 500,000.00 $ 500,000.00
Monthly Report CPFF 2202 8/1/2018 - 7/31/2019 $ 10,000.00 $ 10,000.00
Monthly Report CPFF 0402 8/1/2018 - 7/31/2019 $ 500,000.00 $ 500,000.00
Monthly Report CPFF 2402 8/1/2018 - 7/31/2019 $ 10,000.00 $ 10,000.00
None CPFF 0103 8/1/2019 - 7/31/2020 $ 500,000.00 $ 500,000.00
None CPFF 2103 8/1/2019 - 7/31/2020 $ 10,000.00 $ 10,000.00
None CPFF 0203 8/1/2019 - 7/31/2020 $ 500,000.00 $ 500,000.00
None CPFF 2203 8/1/2019 - 7/31/2020 $ 10,000.00 $ 10,000.00
None CPFF 0403 8/1/2019 - 7/31/2020 $ 500,000.00 $ 500,000.00
None CPFF 2403 8/1/2019 - 7/31/2020 $ 10,000.00 $ 10,000.00
<Insert new rows above this line>
Total Est Cost (OY2): $ 1,530,000.00 $ 1,530,000.00
Total Est Cost (OY3): $ 1,530,000.00 $ 1,530,000.00
Total Est Cost (OY4): $ - 0 $ - 0
Total Est Cost: $ 3,060,000.00 $ 3,060,000.00
Can the contract/work be completed within the available funding and on schedule? YES/NO If not, why not? Yes
EXPENDITURES AND COMMITMENTS:
CLIN % Funding Expended Funds Exhaustion Date Funds Remaining ESTIMATE AT COMPLETION
0102 ERROR:#REF! N/A ERROR:#REF!
2102 ERROR:#REF! 12/1/19 ERROR:#REF!
0202 ERROR:#REF! N/A ERROR:#REF!
2202 ERROR:#REF! 12/1/19 ERROR:#REF!
0402 ERROR:#REF! N/A ERROR:#REF!
2402 ERROR:#REF! 12/1/19 ERROR:#REF!
LEVEL-OF-EFFORT (LOE) (+/-X%)
CLIN Target Hours % Hours Expended to Date % Hours Expended in this Period
0102 4650 ERROR:#REF! ERROR:#REF!
2102 N/A N/A N/A
0202 4650 ERROR:#REF! ERROR:#REF!
2202 N/A N/A N/A
0402 4650 ERROR:#REF! ERROR:#REF!
2402 N/A N/A N/A
COMMENTS: (Details of anomalies identified in the current month’s costs)
(Explanation of any variations exceeding 15%)
RATE CHANGES: (Identification of new proposed/negotiated rates with DCAA)
Please attach copies of your corresponding monthly invoice(s).
&"Helvetica Neue,Regular"&12&K000000&P
Labor
Labor CLIN 1001
Actuals Actuals Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted
Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23
Position Title Level Project Name/Number Last Name First Name Company Status Fully Burdened Rate Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost Hours Cost
Program Manager Doe John XXX Filled $100.00 160 $16,000.00 155 $15,500.00 145 $14,500.00 130 $13,000.00 155 $15,500.00 155 $15,500.00 155 $15,500.00 155 $15,500.00 155 $15,500.00 155 $15,500.00 155 $15,500.00 155 $15,500.00
Senior Software Engineer III Doe Jane XXX Filled $120.00 120 $14,400.00 130 $15,600.00 125 $15,000.00 155 $18,600.00 140 $16,800.00 140 $16,800.00 140 $16,800.00 140 $16,800.00 140 $16,800.00 140 $16,800.00 140 $16,800.00 140 $16,800.00
Senior Developer II Vacant
Total 280 $30,400.00 285 $31,100.00 270 $29,500.00 285 $31,600.00 295 $32,300.00 295 $32,300.00 295 $32,300.00 295 $32,300.00 295 $32,300.00 295 $32,300.00 295 32300 295 $32,300.00
Cumulative Expenditures $30,400.00 $61,500.00 $91,000.00 $122,600.00 $154,900.00 $187,200.00 $219,500.00 $251,800.00 $284,100.00 $316,400.00 $348,700.00 $381,000.00
Total Funding $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00 $100,000.00
T&M
CPFF (Modification)
Warp Core
Travel V1
Travel CLIN 1002
Actuals Actuals Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted
Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23
Trip From To Duration (Days) FTE Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
Exercise SATX BOS 7 1 $2,500.00
Exercise SATX Lackland 7 3 $7,500.00
Future Exercises $5,000.00 - $2,500.00 - $7,000.00 $5,000.00 $2,500.00 $7,500.00 - $2,500.00
Total $2,500.00 $7,500.00 $5,000.00 $0.00 $2,500.00 $0.00 $7,000.00 $5,000.00 $2,500.00 $7,500.00 0 $2,500.00
Cumulative Expenditures $2,500.00 $10,000.00 $15,000.00 $15,000.00 $17,500.00 $17,500.00 $24,500.00 $29,500.00 $32,000.00 $39,500.00 $39,500.00 $42,000.00
Total Funding $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00 $50,000.00
Travel
Travel CLIN 1002
Last Name First Name Trip Depart Date Return Date From (Origin) Destination Duration Projected Cost Actual Cost
Doe Jane Exercise 1 11-Nov-22 18-Nov-22 SATX BOS 7 $ 2,500.00 $2,400.00
Doe John Exercise 1 11-Nov-22 18-Nov-22 SATX BOS 7 $ 2,500.00 $2,400.00
Doe Jane Exercise 2 1-Dec-22 7-Dec-22 SATX Lackland 7 $ 2,500.00 $2,350.00
Doe John Exercise 3 10-Dec-22 17-Dec-22 SATX BOS 7 $ 2,500.00 $2,400.00
Cumulative Expenditures $9,550.00
Total Funded $50,000.00
ODC V1
ODC CLIN 1003
Actuals Actuals Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted Forecasted
Nov-22 Dec-22 Jan-23 Feb-23 Mar-23 Apr-23 May-23 Jun-23 Jul-23 Aug-23 Sep-23 Oct-23
Item Part Number Quantity Unit Price Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost Cost
Server XXXX-XXXX 10 $27,000 $270,000.00
Linux XXXX-XXXX 20 $420 $8,400.00
Future Procurement $140,000.00 - $150,000.00 $200,000.00 $50,000.00 - $150,000.00 $200,000.00 $50,000.00 -
Total $270,000.00 $8,400.00 $140,000.00 $0.00 $150,000.00 $200,000.00 $50,000.00 $0.00 $150,000.00 $200,000.00 50000 $0.00
Cumulative Expenditures $270,000.00 $278,400.00 $418,400.00 $418,400.00 $568,400.00 $768,400.00 $818,400.00 $818,400.00 $968,400.00 $1,168,400.00 $1,218,400.00 $1,218,400.00
Total Funding $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00 $1,500,000.00
ODC
ODC CLIN 1003
Item PK Number Manufactuer Part Number Procurement Date Quantity Unit Cost Total Cost
Server XXX-XXXX 11-Dec-22 10 $ 27,000.00 $ 270,000.00
Linux XXX-XXXX 15-Dec-22 20 $420.00 $8,400.00
Cumulative Expenditures $278,400.00
Total Funded $1,500,000.00
Directions
Directions
Tab 1 (Cover)
1) Fill out with traditional contractor cover sheet
Tab 2 (LOE)
1) Fill out all highlighted areas
1a) Some sections only need to be filled out once or per PoP
1b) Specifics below:
Lines 3-7
Month: Fill out month of CDRL data
Name of Contractor: Fill out Contractor Name
Contract No: Fill out Contract Number
Period of Performance: PoP for current option period
Contract Type: Fill out Contract Type
Reporting Period Start: Beginning date of CDRL data
Reporting Period End: End date of CDRL data
Lines 11-22
Action: Monthly Report or other notable action (mod, etc.)
Contract / TO: CLIN type (FFP, CPFF, etc.)
CLIN: Name of given CLIN
PoP: Period of Performance for given CLIN
Modification No.: Mod #, if any
Ceiling: Current ceiling on given CLIN
Funding:…