About this file

Contractor questions & Government answers

View the file

Other files for this federal contract opportunity

Other files attached to Local Exchange Services for Beale AFB, CA, newest first.
File Type Posted
Attch_2_-_Beale_CSA_-_Pricing_Schedule_-_5_July_2018.xlsx XLSX spreadsheet
Attch_5__Beale_CSA__Questions_With_Answers_29_July_2018.xlsx XLSX spreadsheet
Attch_1_-_Beale_CSA_PWS__V2_5_July_2018.docx DOCX document
FA8773-18-Q-0002_Amend_0002_Beale_CSA_(signed).pdf PDF
Combined_SynSol_Amend_01_-_Beale_CSA__22_June_2018.doc DOC document
FA877318Q0002_Amend_01_22_June_2018.pdf PDF
Attch_2_-_Beale_CSA_-_Pricing_Schedule_-_31_May_2018.xlsx XLSX spreadsheet
Attch_4_-_Beale_CSA_Addendum_to_FAR_52.212-2.docx DOCX document
Attch_3_-_Beale_CSA_Addendum_to_FAR_52.212-1.docx DOCX document
Attch_5_-_Beale_CSA_-_Question_Spreadsheet_Template.xlsx XLSX spreadsheet
Attch_1_-_Beale_CSA_PWS__V1_30_May_2018.docx DOCX document
Combined_SynSol_-_Beale_CSA__8_June_2018.doc DOC document
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SOLICITATION: FA8773-18-Q-0002
Requirement: Local Telecommunications Services for Beale AFB, CA
Contractor Name and POC:
PWS Paragraph, Synopsis/Solicitation, or Attachment ReferencePage NumberContractor QuestionGovernment Response
PWS 4.39On page 9, section 4.3 of the PWS, a detailed installation and cutover plan is required for submittal with the technical proposal. Can the Government provide any floor plans for the sites?At this time, we consider this information FOUO and sensitive. Upon award to a non-incumbent contractor, we will provide a floor plan. Per PWS - In the event the award is made to a non-incumbent contractor, the incoming Contractor shall develop an installation and cutover plan for submittal to the Government with their technical proposal.