Questions_ _Answers.docx
DOCX document 12 KB Posted
- Attached to
- Stockbridge Site Access Road Upgrades Federal contract opportunity
- Solicitation number
- FA8751-16-B-0003
About this file
Questions/Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8751-16-B-0003-0003.pdf | ||
| FA8751-16-B-0003-0002.pdf | ||
| FA8751-16-B-0003-0001.pdf | ||
| ULDF_140008-FINAL_Drawings.pdf | ||
| FA8751-16-B-0003.pdf | ||
| ULDF_140008-FINAL_Specifications.pdf | ||
| 16B0003_-_Attachment_4_-_Site_Visit_Form.pdf | ||
| 16B0003_-_Attachment_3_-_Davis_Bacon_Wage_Determination.pdf | ||
| 16B0003_-_Attachment_5-_Bid_Schedule.pdf | ||
| ULDF_140008-FINAL_Drawings.pdf | ||
| ULDF_140008-FINAL_Specifications.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8751-16-B-0003
Questions & Answers
26 September 2016
Question 1. Is the contractor responsible for pouring concrete on exposed conduit if encountered without concrete?
Answer 1. Yes.
Question 2. What are the contractor’s responsibility at the crossing of the conduit?
Answer 2. See General Notes on Sheet L-2 of Drawings, note 6.