REPAIR AIR HANDLERS & CONTROLS

Building 3

Phase 1

‘CHILLER PLANT ALTERATIONS AND REPAIR (NLC)’

ADDENDUM #1

1. Section 01010, Paragraph 1.02, A. add “New door area shall require a lintel along top section. Conduit to be relocated services the fire alarm system. The Contractor must request RIOCO shut down the Building 3 alarms while conduit is being moved.”

2. Section 01010, General, add “Building roof material is BUR with an SBS cap sheet. All penetrations shall be patched to match the existing.”

3. Section 01010, Paragraph 1.02, C. add “All controls shall attach to and operate with the existing Johnson Metasys system used at the facility. Control equipment shall be Johnson, or approved equal.”

4. Section 01010, Paragraph 1.02, C. add “Chilled water and condenser water piping and connections may be grooved piping with manufacturer’s fitted insulation and jacketing.”

AFRL, Repair Air Handlers, Bldg 3GENERAL SCOPE
SECTION 01010-2