Addendum 1 dated 26 July 2011 RFP FA8751-11-R-0006.pdf

PDF 108 KB Posted

Attached to
Repair Fire Alarm System Federal contract opportunity
Solicitation number
FA8751-11-R-0006
Issued by
Department of the Air Force Materiel Command Research Laboratory

About this file

Addendum 1

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fire Alarm System, newest first.
File Type Posted
FA8751-11-R-0006 RFI 21 Answered.doc DOC document
FA8751-11-R-0006 RFI 20 Answered.doc DOC document
RFP Q A 3 —
Addendum No. 2 dated 4 August 2011 RFP FA8751-11-R-0006 Attach 7.pdf PDF
FA8751-11-R-0006 RFI 11 Answered.doc DOC document
FA8751-11-R-0006-02.pdf PDF
FA8751-11-R-0006 additional information 3 Aug 2011.doc.docx DOCX document
RFP Q A 2 —
FA8751-11-R-0006-01.pdf PDF
11r6 rfp attch 5R site visit form.doc DOC document
FA8751-11-R-0006 additional information 26 July 2011.docx DOCX document
RFP Q A 1 —
FA8751-11-R-0006 attach 3R.docx DOCX document
FA8751-11-R-0006 RFI 1 Answered.doc DOC document
FA8751-11-R-0006 additional information 19 July 2011.doc.docx DOCX document
FA8751-11-R-0006 RFI Request Form.doc DOC document
11R6 attach 4.docx DOCX document
FA8751-11-R-0006 attach 3.docx DOCX document
Drawings —
Drawings —
11r6 rfp attch 5 site visit form.doc DOC document
11R0006 Specs.zip ZIP file
FA8751-11-R-0006.pdf PDF
Show all 23

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

TO

PROJECT SPECIFICATIONS AND DRAWINGS

FOR

REPAIR FIRE ALARM SYSTEM

AT

AIR FORCE RESEARCH LABORATORY

ROME RESEARCH SITE

ROME, NEW YORK 13441

PROJECT NR: ULDF-10-0005

PREPARED BY

TOWNE ENGINEERING

CONSULTING ENGINEERS

18 SOUTH STREET

UTICA, NEW YORK 13501

JULY 26, 2011

This Addendum is issued indicating changes to the Project Specifications and Drawings dated April 14, 2011. All changes shall be incorporated into the Contractor’s Proposal as described herein, as this Addendum will become part of the Contract Documents if and when an award is made.

FOR CLARIFICATION:

1. The Proposed Riser Diagrams are shown for reference only and are not intended to be used as installation drawings; exact arrangement and wiring requirements shall be per equipment manufactures directions and shop drawings. It is the contractor’s responsibility to provide all components, wiring, etc. to meet the project specifications.

REFER TO DRAWINGS

1. Sheet 1:

a. Refer to Proposed Network Communications Schematic:

1) Delete the autonomous control unit communicator in the Rome Research Site

Guard Shack.

b. Refer to General Notes:

1) Add the following: 22. Existing raceway systems slated for removal in open and industrial areas above 20 feet may be abandoned in place; the associated wiring system shall be removed in their entirety.

2. Sheet 7:

a. Refer to Proposed Riser Diagram:

1) Provide Surge Suppressor on the 120 volt branch circuit serving each NAC.

3. Sheet 29:

a. Refer to Proposed Riser Diagram:

1) Provide Surge Suppressor on the 120 volt branch circuit serving each NAC.

REFER TO SPECIFCATIONS:

1. Section 16721 Combination Mass Notification/Emergency Communication And

Addressable Fire Alarm And Detection System:

a. Refer to Part 3-Execution, 3.08 Training; add the following:

1) B. The government/owner will pay all per diem expenses associated with the training associated with the two owner’s representatives.

END OF ADDENDUM NO. 1