Tab_12_-_RFP_Attachment_1_-_SOW_21_Mar_2017.pdf
PDF 418 KB Posted
- Solicitation number
- FA8629-17-R-5004
About this file
Amended Statement of Work, 21 March 2017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q&A_21_March_2017.pdf | ||
| RFP_Attachment_3_-_CDRLs.pdf | ||
| RFP_Attachment_2_-_GFP.pdf | ||
| RFP_Attachment_4_-_PPQ.doc | DOC document | |
| RFP_Attachment_1_-_SOW_10_Mar_2017.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA8629-17-R-5004
Attachment 1 - Statement of Work (SOW)
21 MAR 2017
Guardian Angel Air-Deployable Rescue Vehicle (GAARV)
Post-Block 1 Upgrade Validation Testing
Statement of Work (SOW)
1.0 Objective
The objective of the Guardian Angel Air-Deployable Rescue Vehicles (GAARV) Block 1 testing is to validate/verify the functionality of system design changes from the Block 0 configuration and to establish baseline operational ride quality.
2.0 Scope
The Contractor shall conduct a 1,000 mile air filtration system evaluation on each of two GAARV Block
1 test vehicles, totaling 2,000 miles, based on the proposed profile identified in Table 2 (below). The
Contractor shall also complete a ride quality evaluation, under off-road operational representative conditions, on a third GAARV Block 1 vehicle. The Government will provide a fourth vehicle as a spare.
The Contractor shall develop and deliver a Final Test Report (A001) and Ride Quality Report (A004) to capture findings in addition to other reports as specified herein.
3.0 Background
The GAARV is an air transportable all-terrain light tactical vehicle. The vehicle provides an air-deployable, surface recovery platform capable of maneuvering over adverse terrain in order to search for and recover Isolated Personnel (IP) and/or sensitive equipment, while also providing the capability of transporting the Recovery Team (RT) and the IP to a defendable location for recovery by either aircraft, or self-recovery, to the final destination. The GAARV is deployable/recoverable by fixed wing and heavy lift rotary wing aircraft using airdrop, on/off load or sling load techniques.
The GAARV provides maximized capabilities including transportability, horsepower, torque, suspension, seating, field of view, litter and payload capacity, protection, and vehicle range. The vehicle features special solid axles, long suspension travel, and a low Center of Gravity (CG) allowing the GAARV to traverse rocks and debris. The engine sits low in the vehicle between the front and rear axles (mid-engine design) for a lower CG providing greater stability when ascending or descending steep grades. Curb weight dimensions are 177 inches long (without front bumper and spare), 78 inches wide and 69 inches high. The vehicle is equipped with dual internal gas tanks and external gas cans for long-range missions.
The modified transmission and transfer case provide Front Wheel Drive (FWD) high/low, All-Wheel
Drive (AWD) high/low and Rear-Wheel Drive (RWD) low-only modes (accessible while en route) to provide the driver the flexibility to expeditiously transition across diverse terrain and confront various operational scenarios. The GAARV data plates are located on the left side of the vehicle adjacent to the left wheel well. These plates identify the manufacturer, vehicle model designation, CG, weight information and miscellaneous limits and ratings.
4.0 Tasks/Technical Requirements
4.1 Task 1 Test Plan Development
The Contractor shall develop a Test Plan (A002) that defines the setup, procedures and support to be utilized for the test efforts described herein. This shall include a detailed description for each test requirement as well as a test schedule that captures the key milestones/activities and durations associated with the tasks defined in this SOW. The Contractor shall submit the test plan for AFLCMC/WISN
(hereby referred to as “The Government”) approval 10 business days after contract award. The
Government will review the plan and provide comments within three (3) business days, at which time an additional two (2) business days shall be utilized to incorporate changes pursuant to the Government’s comments.
4.2 Task 2 Receiving Inspection, Training, and Property
The Government will ship each test vehicle to the Contractor with a half tank of 87 octane gasoline; the
Contractor shall return the vehicles with the equivalent amount. The Contractor shall supply all 87 octane fuel required for testing.
Each GAARV vehicle is equipped with one spare Tire and Wheel Assembly (TWA), which is mounted on the rear of the vehicle. The Government will provide a total of four additional spare TWAs with the vehicles. The Contractor shall acquire all items identified in Table 1; these items shall be on site no later than 15 business days after contract award. The Contractor shall compile an Inventory Report (A005) for the consumable items as well as the spare TWAs, and submit the report to the Government Program
Manager (PM) for verification. The Contractor shall complete a second inventory report at the conclusion of testing in accordance with SOW Section 4.5.
Table 1. Contractor-Acquired Material
Manufacturer
P/N
Description Initial Stock
QTY (ea.)
290-0632 BRAKE FLUID, DOT 3, HIGH TEMP, 570 DEG F, WILWOOD DISK
BRAKES, 12 oz., 290-0632, ZXEL-1 COOLANT, DEX-COOL, ZXEL-1, Gal., 16
ATC BT4S-M0 WIRE TIE, LENGTH: 15.1", BLACK, MATERIAL: WEATHER
RESISTANT NYLON 6.6, TEMPERATURE RANGE: -76°F (MIN.) &
185°F (MAX.), PANDUIT #BT4S-M0
200 ea. (2pk)
ATC 97526A350 RIVET, 3/16 AL DOME .251-.375 GRIP, BLACK, MCMASTER P/N,
97526A350
ATC 10051MC NUT, CLIP, 1/4-20, BLACK PHOSPHATE, AVVECO P/N, 10051MC 128
ATC 8814 NUT, CLIP, 5/16-18, BLACK PHOSPHATE, AVVECO P/N, 8814 112
ATC 00585 SCREW & WASHER, 1/4-20 X 7/8, HHCS, SS, BLACK, BLACK
OXIDE, PATCHED, ATC P/N 00585-ATC
ATC SCREW- 5/16-18 X 1-1/2" SOCKET FLAT HEAD STAINLESS STEEL
WITH LOCKING PATCH
SL3144 GREASE, MULTI-PURPOSE,EXTREME PRESSURE, 3 Pack, SL3144, 16
102991 OIL, 5W-30, MOBILE 1, QT, 102991, 192
PF48 FILTER, ENGINE OIL, 6.2 LS3, AC Delco, PF48 16
1326 PWR STEERING FLUID, ROYAL PURPLE, 01326 32
130307-Kit FILTER, POWER STEERING, TRAIL GEAR, 130307-Kit 16
P608675 PRIMARY AIR FILTER, P608675 16
P606121 SAFETY AIR FILTER, P606121 16
30704 ATF, DEXRON-VI, REDLINE D6, 30704 128
2408576 KIT, TRANSMISSION, SERVICE KIT, GM 2408576, 16
230605ERL ELEMENT, FUEL FILTER, 10 MICRON, 100GPH, EARLS P/N
230605ERL
VV982 OIL, GEAR LUBE, SAE 75W-140, FULL SYNTHETIC, VALVOLINE,
VV982
Manufacturer
P/N
Description Initial Stock
QTY (ea.)
K040425 BELT, COMPRESSOR, HDT STORM, GATES P/N, K040425 16
K060798 BELT, ENGINE, HDT STORM, GATES K060798, 16
32992 TOWEL, ROLL, PRO SHOP TOWELS, BLUE, 32992 64
24240 LOCTITE, BLUE, 1.22 Oz, Permatex, 24240, ET300263 (H009258)
Medium Strength
19647 DRAIN PAN, OIL, POLYETHYLENE, BLACK, 11Qt, 19647 8
PRESV 10 FLUIDS, PRESERVATION OIL, 10, 5, GAL 16
11722 FLUIDS, FUEL STABILIZER, ROYAL PURPLE, 20 OZ, 11722 16
602247 FLUIDS, FUEL WATER ABSORBING ADDITIVE, Valvoline, 12 OZ, 602247
230616-ORING O-RING KIT, REPLACEMENT FOR ET300258, 230616-ORING 16
81343 CONSUMABLE, ANTI-SEIZE, Permatex, 1 OZ, 81343 16
230609ERL ELEMENT, FUEL FILTER, 100 MICRON, 100GPH, EARLS P/N
230609ERL
5110 MAF SENSOR, CLEANER, CRC, 11 OZ SPRAY, 05110 16
MSDS- BENCH Material Safety Data Sheet (MSDS) PACKET 2
Upon receipt, the Contractor shall photograph the GAARV test vehicles and conduct detailed inspections to identify and document anomalies that may have resulted during shipping or prior vehicle operation.
Additionally, configuration information (e.g., serial numbers, registration numbers, vehicle weight, model numbers, and dates of manufacture, etc.) shall be recorded, as applicable, in a test logbook which shall be included in the Quick Look Report (A003) and Final Test Report (A001) with the inspection documentation and photographs.
All test drivers shall attend a five (5) day basic operator course at the test facility. Immediately prior to testing, training will be provided by the Original Equipment Manufacturer (OEM), HDT. This training will include both classroom and hand-on instruction, as well as practical exercises of vehicle operations and maintenance procedures. During this event, the Contractor shall provide instruction areas that can accommodate up to 10 personnel for indoor classroom activities, as well as outdoor environments for hands-on driving exercises.
4.3 Task 3 Evaluation
4.3.1 1,000-Mile Air Filtration System Evaluation
The 1,000 mile evaluation for each of the two GAARV test vehicles is based on the proposed mission profile shown in Table 2. The objective of the evaluation is to demonstrate the functionality of the air filter system, and identify and record component failures, as well as any issues with the maintenance procedures provided by the vehicle manufacturer.
Table 2. 1,000 Mile Evaluation Mission Profile Test Courses
Course Type Distance Average Speed
Primary Roads 50 miles 50 mph
Secondary Roads 500 miles 37 mph
Trails 400 miles 25 mph
Cross-Country 50 miles 15 mph
Two (2) cycles of the obstacle mobility course 5 mph
Total 1,000 miles (not including the mobility course) Average Speed 28 mph
The mission profile operation shall be conducted over the range of terrain, to include desert environment, the test vehicles are expected to traverse. All miles the test vehicles attain while at the test facility will be counted toward the 1,000 mile threshold.
The Contractor shall instrument the test vehicles with a Solid State Vehicle Recorder (SSVR), accelerometers, and other associated instrumentation to capture data. Representative operations on the mission profile courses shall be documented using video and still digital cameras for inclusion in the
Final Test Report (A001) in accordance with SOW Section 4.6.
An endurance evaluation shall be conducted by operating each test vehicle over the predetermined courses for the specified duration (reference Table 2). The Contractor shall develop a test route utilizing a mixture of courses (i.e. rather than completing each course type serially) in order to realistically simulate operational conditions.
The Contractor shall verify the presence and proper function of electrical components, map alternator output vs. engine speed, and perform load analysis on one (1) vehicle. TOP 2-2-601 shall be used as a guide for taking measurements and interpreting results. Additionally, the amperage found at the
Alternating Current (AC) to Direct Current (DC) power converter unit shall be verified with the manufacturer’s specification on all four (4) GAARV vehicles.
After initial test vehicle operations for course speed confirmation, each test vehicle shall be operated daily for five (5) consecutive days each week for the duration of the test. Prior to each shift, all test vehicles shall undergo a brief daily safety inspection as described in Section 4.7. The inspector shall upload the inspection into the OEM’s maintenance tracker (FIST). Training on FIST will be conducted during the driver’s training course.
The test personnel shall complete daily drivers’ logs which capture fuel consumption and route utilization, and which supplement the automated data that is collected by the instrumentation package that is downloaded at the end of each shift. The fuel consumption for each vehicle shall be measured and evaluated throughout the evaluation, and consumption reported in miles per gallon (mpg) based on total fuel used and miles traveled. The mission profile fuel economy is a composite of the fuel consumption over each of the individual terrain types that make up the mission profile. The Contractor shall compile this information and provide, via email, it to the Government PM each week through the date of completion. In the event of a deficiency, there shall be a Government-led Deficiency Review Board
(DRB) with the Contractor via teleconference.
4.3.2 Ride Quality Evaluation
The Contractor shall conduct a ride quality baseline to determine the amount of vibration transmitted from the road to the vehicle operator and crew over terrain of increasing roughness. Shock and vibration shall be measured at the various positions outlined below: Root Mean Square (RMS) ride quality courses, Wave Number Spectrum (WNS) ride quality courses and half-round obstacles. The RMS courses shall be conducted at both the Operational Weight (OW) of 2,000 lbs and the Gross Vehicle Weight (GVW) of
3,500 lbs. All other ride quality testing shall be performed on the test vehicle in the OW configuration.
Vehicle ride vibration performance shall be recorded and reported in a supplemental Ride Quality Report
(A004).
Table 3. Ride Quality Baseline Instrumentation
Measurement Location
Data Acquisition Vehicle cab
Vehicle Ground Speed GPS-based speed sensor in vehicle cab
Triaxle Acceleration Driver’s seat base
Triaxle Acceleration Driver’s seat pad
Triaxle Acceleration Driver’s seat back
Triaxle Acceleration Rear passenger’s seat base
Triaxle Acceleration Rear litter base
Triaxle Acceleration IMU near vehicle CG
Roll Rate IMU near vehicle CG
Yaw Rate IMU near vehicle CG
Pitch Rate IMU near vehicle CG
4.4 Task 4 Test Incidents
In the event of any operational test incident, the Contractor shall prepare a Test Incident Report (TIR)
(A006), which documents the incident and provides supporting information that includes but is not limited to: testers, observers, date/time, expected results, actual results, anomalies, attempts to repeat, photographs, the severity of the incident (i.e. mission critical, major or minor) and the priority to fix (i.e..
immediate, delayed or deferred), etc. . The Contractor shall provide each TIR to the Government
Program Office within 72 hours of incident. Severity and priority ratings are defined here:
• Mission Critical - Application will not function or system fails
• Major - Severe problems, but possible to work around
• Minor - Does not impact the functionality or usability of the process, but is not according to requirements/design specifications
• Immediate - Must be fixed as soon as possible
• Delayed - System is usable, but incident must be fixed prior to next level of test or shipment
• Deferred - Defect can be left in if necessary due to time or costs
4.5 Task 5 Final Inspection and Shipment
The Contractor shall remove all testing instrumentation installed during the test, conduct a maintenance post-test inspection of each vehicle, and prepare the vehicles for return shipment. All unused Table 1 consumables, including spare TWAs, shall be inventoried and packaged for return with the vehicles. A copy of the Inventory Report (A005) shall be sent to the Government no later than five (5) business days after test completion.
4.6 Task 6 Quick Look Report and Final Test Report
Within 10 business days of test completion, the Contractor shall deliver a Quick Look Report (A003) of the overall test findings, which includes, but is not limited to:
o Test data/observations o Daily Log Summary o Mileage by vehicle o Fuel Usage o TIR Summary o Damages o Maintenance Summary
The Contractor shall prepare the Quick Look Report in a brief-type format; however, no formal briefing presentation is required.
Within 30 business days of test completion, the Contractor shall develop a Final Test Report (A001) that includes:
o Pre-test inspections o Post-test inspections o Test data/observations o Instrumentation type, location, and calibration certifications o Photographs and edited video of representative portions of test conduct o Results of each run
4.7 Task 7 Vehicle Maintenance
The Contractor shall inspect the test vehicles for serviceability in accordance with the OEM-provided
Operations and Maintenance (O&M) Manual and the Preventative Maintenance Checks and Service
(PMCS) checklist (Provided as Appendix A to this SOW) prior to, and after, daily operations in order to verify that the test vehicles’ systems are free from damage and are adjusted as required. All test incidents shall be reported to the Government, via email, for a determination of maintenance repair requirements within 72 hours of incident. The Government must acknowledge receipt of this email. All test incidents and repairs shall be documented for inclusion in the Final Test Report (A001).
The Contractor shall perform scheduled maintenance on the test vehicles, refueling, and services of fluids and tire changes throughout the duration of testing, and shall perform a thorough visual inspection of each vehicle the conclusion of the evaluations in accordance with the maintenance manual. All maintenance actions shall be reported in the OEM’s maintenance tracker (FIST). All other maintenance shall be coordinated through the Government. A representation of the periodic maintenance is provided in Table
4 below.
Table 4. Periodic Maintenance
Periodic Maintenance Daily Weekly Monthly Semiannual Annual
150 miles 350 miles 500 miles 2,500 miles 5,000 miles
PMCS Before Operation X X X X X
Clean Air Pre-filter X X X X X
Inspect/Clean Air Filter X X X X X
Clean Fuel Pre-filters X X X
Inspect Belts and Hoses X X X
Inspect Fuel Hoses X X X
Transmission Oil and Filter X
Transfer Case Oil Change X
Change Oil and Filter X X
Change Power Steering Fluid & Filter X
Replace Differential Fluid X X
Grease Drive Line U-joints X(1) X
NOTE: (1) Grease Drive Line U-Joints every 2,500 miles or six months, whichever comes first
5.0 Minimum Requirements
5.1 Facilities
Due to the tight schedule of the program, which is precipitated by outside factors, testing is anticipated to start approximately the beginning of April 2017, and last approximately sixty (60) calendar days, including inspections. The Contractor must be able to support this testing start date and have flexibility in its schedule. The test start date is dependent on the upgrade of the vehicles. The Government will notify the Contractor at least ten (10) days prior to test start to schedule shipping. The Contractor shall own, or have access to, a facility/facilities that can accommodate testing and training activities identified in
Section 4 and that can support this test schedule.
5.2 Place of Performance
The vehicles to be tested are military vehicles currently located at Nellis AFB, NV. A commercial transport vehicle will transport the vehicles to and from the testing facility. The testing facility shall be located within a reasonable distance from a single day’s drive of Nellis AFB, NV to enable the military transport vehicle to deliver (and subsequently retrieve) the vehicles within one a two-days’ drive (i.e.
consecutive business days).
5.3 Personnel
All drivers, test instrumentation, and maintenance personnel shall be qualified and experienced. A qualified driver is one that has a minimum of two years professional driving experience of similar off-road or military vehicles. While the OEM will conduct the driver training, the course assumes experienced and qualified drivers. A qualified test instrumentation personnel is one that has experience with Global Positioning Satellite (GPS), accelerometer, and recording devices. A qualified maintainer is one that has an Automotive Service Excellence (ASE) or comparable certification.
5.4 Accessibility and Accommodation
Members of the 46th Test Squadron, Eglin AFB, FL will be available 24/7 during the training and testing of these vehicles. Additionally, personnel from the Program Office (AFLCMC/WISN), Air Combat
Command (ACC) and the 59th Test Squadron out of Nellis AFB, NV may be present at the test events as pre-coordinated. All such personnel shall be given access to all test events and test facilities as coordinated.
6.0 Deliverables
All deliverables listed below shall be delivered to the Government in accordance with the applicable DD
Form 1423, Contract Data Requirements List (CDRL):
CDRL No. Title Initial
Submission
Revisions Final
Submission
Format SOW
Reference
A001
(DI-NDTI-
80809B)
Test/Inspection
Report (Final Test
Report)
NLT 30 business days after completion of testing
As required NLT 30 business days after completion of testing
MS Word 2.0, 4.2, 4.3.1, 4.6, 4.7
A002
(DI-NDTI-
80566A)
Test Plan NLT 10 business days after contract award
As required NLT 5 business days after receipt of customer comments
MS Word and
Adobe(.pd f)
4.1
A003
(DI-MGMT-
81605)
Briefing Material
(Quick-Look
Report)
NLT 10 business days after completion of testing
N/A NLT 10 business days after receipt of customer comments
MS Word and
Adobe(.pd f)
4.2, 4.6
A004
(DI-MISC-
80508B)
Technical Report-
Studies/Services
(Ride Quality
Report)
15 business days after completion of testing
N/A 15 business days after completion of test
MS Office 2.0, 4.3.2
A005
(DI-MISC-
80508B)
Technical Report-
Studies/Services
(Inventory Report)
(1)15 days after contract award
(2)5 days after test completion
N/A (1)15 days after contract award
(2)5 days after test completion
MS Office 4.2, 4.5
A006
(DI-NDTI-
80809B)
Test/Inspection
Report (Test
Incident Report)
Within 72 Hours of
TIR
N/A Within 72 Hours of
TIR
MS Office 4.4
APPENDIX A: Preventative Maintenance Checks and Services (PMCS) Checklist
PMCS Form (Front)
PMCS Form (Back)