This document contains questions and answers related to a solicitation for Contractor Kit Installation (CKI) of the Combined Block 7.0/8.1 Modification to the United States Government C-130J Fleet. The solicitation is being issued by the Department of the Air Force Materiel Command Lifecycle Management Center and seeks a contractor to perform kit installations and maintenance on C-130J aircraft. Key details include that the proposal due date is 6 November 2019, installations are scheduled to begin in fiscal year 2021, pricing is to be provided separately in Volume III of proposals, and the first two aircraft installation cycles are not to exceed 210 days while subsequent installations must be completed within 180 days. Subcontracting plans should address goals for small businesses including small disadvantaged businesses, women-owned small businesses, veteran-owned small businesses and HUBZone businesses. Relevant technical manuals and guidance documents can be requested from the Public Sales office.

Question and Answer spreadsheet encompassing all RFP Amendment 1 questions.

View the file

Other files

File Type Posted
CKI_RFP_AMENDMENT_1_update.zip ZIP file
CKI_RFP_AMENDMENT_1.zip ZIP file
CKI_RFP.zip ZIP file
Bidders_Library_Disclaimer_signed.pdf PDF
Bidders_Library_Disclaimer.pdf PDF
CKI_Pre_RFP_Synopsis.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Item No.ReferenceQuestionAFLCMC/WLNN Answer (23 Oct 19)
1RFP Letter, dated 3 October 2019Article 5 of the RFP Letter states that the due date for this RFP is NLT 1500 hours local time, 6 November 2019; However, Section L - Clause 2.1.6 - states: "...[P]proposal deadline, thirty (30) calendar days after RFP release" which indicates due date of 3 November 2019. Please advise what is the correct RFP due date.The proposal due date is 6 November 2019 NLT 1500 Local Time
2RFP Letter, dated 3 October 2019Article 12 of the RFP Letter states: "Installation of these kits is scheduled to begin in December 2019.” The PWS Attachment 1: Aircraft Schedule, indicates that the planned installations are to start in FY21 (Oct 2020). Please clarify.Installs begin in FY2021
3Section LReferencing Solicitation Section L, Para. 2.2.3, can Government please confirm that the Solicitation-Cross Reference Matrix (S-CRM) (Attachment 1 in Bidder's Library) is not to be included in any specific Volume (I-IV), but submitted in .xlsx file format as a stand-alone submittal? If not, please advise disposition.The Solicitation-Cross Reference Matrix is a stand alone document
4Section LReferencing Solicitation Section L, Para. 2.3, can Government please advise how Offerors should identify their electronic files (file naming requirements, inclusion of offeror name in filename, format (.docx, .pdf, .xlsx, as applicable).Contractor format is acceptable, but should be referenced in the S-CRM where appropriate
5Section LSection L - Clause 4.3.2.1 states that the installation cycle duration is not to exceed 180 calendar days; However, PWS states that the first and second aircraft's installation cycles are not to exceed 210 calendar days. Please advise firm installation cycle days.The first two installs are NTE 210 days to allow for learning curve, the remaining installs are not to exceed 180 days
6Section LSection L, Technical Volume Management, clause 4.3.3.3 states that "Propose labor categories, definitions, and associated fully burdened labor rates (to support contract period of performance) required to perform the case-by-case repairs and corrective actions that may arise as part of the Non-BU 7.0/8.1 Aircraft Maintenance Discrepancies Over & Above process per PWS 4.6.2, 4.6.2.1, 4.6.2.2, and 4.6.2.3 to include qualifications." However, Section L - Pricing Data - under clause 5.2 indicates that the pricing should not be included anywhere else in the proposal, but in Volume III - Price. Since the Pricing Matrix provided via Bidder's Library contains no fields where we may input data on associated fully burdened labor rates (to support contract period of performance) required to perform the case-by-case repairs and corrective actions that may arise as part of the Non-BU 7.0/8.1 Aircraft Maintenance Discrepancies Over & Above process per PWS 4.6.2, 4.6.2.1, 4.6.2.2, and 4.6.2.3,. Please confirm that the pricing noted under Technical Volume Management is not to be included in the Pricing Matrix of the Volume III - Price.All pricing is to be placed in Volume III of the proposal
7Section LWith regards to Section L, Clause 4.3.3.4: "The Offeror subcontracting plan shall separately address subcontracting with small business, veteran-owned small business, service- disabled veteran-owned small business, HUBZone small business, small disadvantaged business, and women-owned small business concerns" - specific percentages were not assigned to each category (i.e. veteran-owned small business, service-disabled veteran-owned small business, HUBZone small business). Please advise if there are specific percentages applied to each category.Total SBA goal is 8%
8C-130J CKI TO 1
PWS Amendment 1Draft Task Order 1 states that "This draft Task Order represents the anticipated CLIN structure associated with Task Order 1 of the CKI effort." This CLIN structure does not have CLIN 0004. When looking at the Pricing Matrix, Tab A. CLIN 0004 is listed as O&A. Please advise should the CLIN in the Pricing Matrix be listed as 0005 per the Draft Task Order 1?CLIN 0004 will be included in the awarded Task Order
9CKI DD1423
Package, Amendment 1DID A004 deletes section 3.6.7 in DI-MGMT-81861A/T, yet in section 3.7.1.4 in DI-MGMT-81861A/T it indicates Format 6 monthly analysis requirements are required as defined in 3.6.7. Please clarify.A004 will be modified to retain Section 3.6.7, Format 6 monthly schedule analysis requirements.
10CKI DD1423
Package, Amendment 1DID A004 deletes section 3.6.11.2 in DI-MGMT-81861A/T, yet in section 3.7.1.3.6.3 in DI-MGMT-81861A/T it indicates results will be reported as part of the Format 5 as in section
3.6.11.2. Please clarify.A004, Section 3.7.1.3.6.3 requirement will be removed.

Clarification: Any requirement for Format 5, Paragraph 3.6.1 will only require Paragraph 3.6.1.6) IMS discussion.

11CKI DD1423
Package, Amendment 1Is there a requirement for specific version (ex. 2010) of Microsoft Project to be used (to avoid any data corruption between the older/newer versions)?Microsoft Project version 2010 or newer should be used.
12Please advise if the following references may be supplied as they were not part of the Bidders Library files received (numbered per TCTO):

(1) Modify Pilots 697906-25 Reference Set/Mode Select Panel in accordance with KFI713140-6 and KFI713140-7 kits.

(2) Modify Copilots 697906-27 Reference Set/Mode Select Panel in accordance with KFI713140-6 and KFI713030-7 kits.

(9) Perform operational checkout of Enhanced Intercommunication System in accordance with TO 1C-130J-2-23JG-50-1, 23-50-01A.

(21) Perform operational checkout of IFF System in accordance withOfferors need to contact Ms. Kristy Pope at the Public Sales office at Robins AFB (478-222-3051) and request the specific TOs. The TCTOs call out the TOs, but the TCTO doesn’t tell you all TOs required. The Offerors may have to contact the Public Sales office more than once to determine required books.
13Bidder's Library FilesTO 1C-130J-2-34JG-50-3, 34-53-02C.

(22) Perform operational checkout of IFF System using TS- 4530A/UPM Test Set in accordance with TO 1C-130J-2-34JG-50-3, 34-53-02C.

(30) Perform operational checkout of AN/APN-218 DVS in accordance with TO 1C-130J-2-34JG-40-4, 34-44-01.

(36) Perform operational checkout of Cockpit Printer in accordance with

TO 1C-130J-2-23JG-30-2, 23-32-07.

(37) Perform operational checkout of INMARSAT System in accordance with TO 1C-130J-2-23JG-30-2, 23-32-05.

(38) Perform operational checkout of VHF Data Radio System in accordance with TO 1C-130J-2-23JG-30-2, 23-32-06.

(47) Perform CNI-MU ANT High/Low Setup and USTS/ARC-210 SEL SW Test in accordance with TO 1C-130J-2-23JG-30-2, 23-32-03.

(48) Perform alternate operational checkout of AN/ARC-210 Communication System using Satellite Simulator (SATSIM) in accordance with TO 1C-130J-2- 23JG-30-2, 23-32-04.Offerors need to contact Ms. Kristy Pope at the Public Sales office at Robins AFB (478-222-3051) and request the specific TOs. The TCTOs call out the TOs, but the TCTO doesn’t tell you all TOs required. The Offerors may have to contact the Public Sales office more than once to determine required books.
14C-130J CKI BASIC PWS
AmendmentPWS - Section 4.10 - GFP Management states: "The Contractor shall develop, maintain, and implement a GFP management program for the assets outlined in the Section J attachment to the Basic contract.”
Please provide the Section J attachment as it was not received.The GFP list is currently in the bidders library. The list will be attached to the basic contract at award.