Sources Sought Vibration Table.docx
DOCX document 18 KB Posted
- Solicitation number
- FA860426SS001
About this file
This is a Sources Sought / Request for Information (RFI) document for the construction of a seismic mass foundation for a vibration table system at Wright-Patterson Air Force Base in Ohio. The Department of the Air Force Materiel Command Lifecycle Management Center is conducting market research to identify qualified contractors capable of designing and constructing the heavy interior foundation and to solicit industry feedback on design optimization. The project requires demolition of existing concrete flooring, excavation of soil to approximately 92 inches depth, debris removal, and construction of a concrete foundation block with a minimum mass of 527,000 pounds within a footprint of 176 inches by 372 inches (14 feet 8 inches by 31 feet). All work must occur inside Building 255 with a strict 14-foot height clearance limitation, and operations are limited to Monday through Friday, 7:30 AM to 4:00 PM, excluding federal holidays.
Interested parties must submit a Capability Statement including company information (CAGE Code, UEI, point of contact, business size and socio-economic status), bonding capacity (single and aggregate), and relevant technical experience in heavy equipment foundations or seismic mass construction. The Government specifically requests engineering feedback on cost-effectiveness tradeoffs between excavation depth and material density, and recommendations for vibration isolation methods. The baseline design specifies 4000 PSI concrete at standard density (152 lb/cu foot) at an estimated depth of 92 inches; however, the Government is open to alternative approaches using high-density materials or dense reinforcement if they reduce overall project cost. This is a pre-solicitation market research effort only; no price proposals are being requested at this stage, and no solicitation number or award timeline has been established.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOURCES SOUGHT / REQUEST FOR INFORMATION (RFI)
Project Title: Construction of a Seismic Mass Foundation for a Vibration Table System
Location: Air Force Packaging Technology & Engineering Facility (AFPTEF), 5219 Forbes St. Area A Bldg. 255, Wright Patterson AFB, OH 45433
1.0 PURPOSE:
This is a Sources Sought Synopsis / Request for Information (RFI) only. This is not a Solicitation or Request for Proposal (RFP). The Government is conducting market research to identify qualified, experienced sources capable of designing and constructing a heavy interior seismic mass foundation for a vibration table system. The Government is also seeking industry feedback on the foundation design, specifically regarding material density, depth, and overall cost-effectiveness.
2.0 BACKGROUND & DRAFT SCOPE OF WORK:
AFLCMC/EZPAA (AFPTEF) requires the installation of a massive concrete foundation (seismic mass) inside Building 255 to support a new vibration testing table. The foundation must be decoupled from the surrounding building slab to isolate vibrations.
2.1 Specific Demolition & Excavation Tasks:
To achieve the foundation requirements, the contractor will be required to perform the following:
· Concrete Demolition: Saw-cut, break, and remove the existing concrete floor within the designated footprint inside the facility.
· Excavation: Dig and excavate the underlying soil to the required depth (up to 92.00 inches, pending final design).
· Debris Removal: Safely haul away and properly dispose of all excavated dirt, concrete rubble, and construction debris off-base.
2.2 Draft Technical Parameters (The Foundation):
· Target Mass: The absolute minimum mass of the foundation block must be 527,000 lbs.
· Target Footprint: 176 inches x 372 inches (14 ft. 8 in. x 31 ft. 0 in.).
· Baseline Material: 4000 PSI concrete at standard density (approx. 152 lb/cu ft).
· Baseline Depth: Based on the baseline material and footprint, the required depth is estimated at 92.00 inches (7 ft. 8 in.) to achieve the target mass.
2.3 Site Constraints & Conditions:
· Site Preparation: AFPTEF will have all product, tools, and small items removed from the designated staging and installation area prior to the contractor starting operations.
· Interior Work & Clearance: All excavation, spoil removal, and concrete pouring will occur inside Building 255. There is a strict 14-foot height limit for entry into the building. All excavation equipment (e.g., excavators, loaders, dump trucks) and concrete delivery methods must account for this constraint.
· Hours of Operation: Work must be conducted Monday through Friday, 7:30 AM to 4:00 PM (excluding Federal Holidays).
3.0 INFORMATION REQUESTED FROM INDUSTRY:
Interested parties are requested to submit a Capability Statement demonstrating their ability to fulfill this requirement. Additionally, the Government is seeking specific engineering feedback regarding the foundation mass.
Please address the following in your response:
3.1 Company Information:
· Company Name, CAGE Code, Unique Entity ID (UEI), and Point of Contact.
· Business Size and Socio-economic status (e.g., Small Business, 8(a), SDVOSB, HUBZone, Women-Owned).
· Bonding capacity (single and aggregate).
3.2 Technical Capability & Experience:
· Briefly describe your company's experience in designing and constructing interior heavy equipment foundations, seismic masses, or shaker table pits.
· Describe your capability to perform deep interior excavation, manage spoil removal, and pour large volumes of concrete within a facility with restricted overhead clearance (14 ft max).
3.3 Industry Feedback / Design-Build Approach:
· Cost-Effectiveness of Depth vs. Density: The Government's primary objective is to achieve the 527,000 lb mass requirement in the most cost-effective manner. There are no site restrictions requiring a shallow pit. However, the Government is open to shallower designs (e.g., utilizing high-density concrete or dense rebar) only if it reduces the overall project cost.
· Based on your expertise, please provide feedback on the cost-tradeoffs: Is it typically more cost-effective to perform the deeper excavation and spoil removal for a standard 92-inch deep pour, or to use more expensive, high-density materials to reduce the excavation depth?
· Are there any standard commercial practices or vibration isolation materials (e.g., perimeter isolation joints) you would recommend for a project of this nature?
File details come from the government source that posted it. Updated .