Questions and Answers_Set 2_24RB009.pdf

PDF 299 KB Posted

Attached to
FA8604 Storage Aid System at Fairchild AFB, Washington MMHS Federal contract opportunity
Solicitation number
FA860424RB009
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

This document is a set of Questions and Answers related to the federal contract opportunity for the FA8604 Storage Aid System at Fairchild AFB, Washington. The key details are:

The contract is for the design, fabrication, and installation of a Storage Aid System at Fairchild AFB. It is a supply contract, not a service contract, so wage rate requirements do not apply. The contractor is only responsible for the fire suppression system under the new mezzanine, not the existing mezzanine. The order picker will interface with all racking installed for this project, but not any existing rack. The composite wood countertop for the mobile workbenches must meet the required loading specifications. The mobile tool carts referenced are existing and will be utilized, the contractor only needs to supply the wood countertop and fasteners for those two workbenches. The contract completion is required within 180 days from date of award.

View the file

Other files for this federal contract opportunity

Other files attached to FA8604 Storage Aid System at Fairchild AFB, Washington MMHS, newest first.
File Type Posted
Storage Aid System at Fairchild Air Force Base Washington Building 1414.zip ZIP file
Solicitation Amendment - FA860424RB0090001.pdf PDF
Solicitation Amendment FA860424RB0090001 SF 30.pdf PDF
Questions and Answers_Set 1_24RB009.pdf PDF
Solicitation - FA860424RB009.pdf PDF
Storage Aid System at Fairchild Air Force Base Washington.zip ZIP file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA8604-24-R-B009

Fairchild AFB, WA

Question Set #2

3 July 2024

1. General:

What are the Wage Rate Requirements for this Project?

This is a supply contract, not a service contract. Wage rate requirements are not applicable.

2. CLIN 0003:

*Ref: "3.2.1.11. FIRE SUPPRESSION SYSTEM, The Contractor shall design and install a dry-pipe preaction single interlock fire suppression system under the new mezzanine." This means that the contractor is only responsible for implementing fire suppression coverage for beneath the 20'6 x 76' New Mezzanine? Asking because we didn't see fire suppression piping shown the image provided beneath the existing mezzanine where the mobile aisle system will be installed.

“The existing mezzanine does have fire suppression installed for coverage beneath, but it’s hard to see in the provided pictures. The contractor will only be responsible for the fire suppression system being installed under the new mezzanine and bridged portion.”

3. CLIN 0006:

*What wide span shelving will the Order Picker be accessing? Are there bays of shelving that are outside of this projects scope that the Order Picker will be accessing? What is the aisleway width that the Order Picker must function within?

“The order picker will be interfacing with all racking installed for this project, as well as lifting pallet loads & the S/R Module to the upper level of the mezzanine. The order picker will not interface with any existing rack. There are no defined aisleways.”

4. CLIN 0009:

*please specify in more detail what 'composite' means for the 4x8 wood countertop.

*QTY 2 of the 4 total Mobile Workbenches have a note *Utilize Mobile Tool Carts (EXISTING),do you have specs, details, images of these Existing Tool Carts? Is the contractor to supply wood countertop and fasteners only for these 2 units?

“Composite wood countertop would just indicate that the layers have alternating grain patterns for improved strength. The countertop must meet the loading requirement.”

“The comment on the drawing *Utilize Mobile Tool Carts (EXISTING)* is just stating that the user will not require new tool carts in that space, and is more of a note to the designer. This comment is not related to the mobile workbenches.”