FA8604‐21‐R‐B013
Eglin Air Force Base, Florida Questions/Answers Set 3 2 June 2021
Questions/Responses:
1. Quick question RE: app “A” – widespan shelving – 3.2.6. calls out for through bolts with metal plate, washer & nut. Is this a base request? In the past we have always used lag screws through both the floor decking & B deck. Would this be acceptable in this install?
PROPOSED LAG SCREWS ARE ACCEPTABLE WHERE APPLICABLE. IF ANCHORING OCCURS AT BOTTOM FLANGE OF B‐
DECK, LAG SCREW MUST GO THROUGH BOTTOM FLANGE OR UTILIZE BOLT, WASHER AND NUT TO SECURE TO
BOTTOM FLANGE OF B‐DECK.